95871NSUARB (NSPI) IR-1 to 13
5 passages
Request IR-4: - In Undertaking U-6 submitted by NS Power as part of the 2019 ACE Plan proceeding (Matter - M08984), NS Power stated: - (a) Riprap work is not included in the scope of this project. The riprap on the embankments remains in g...
AI summary The document requests confirmation of NS Power's statements regarding the scope of a project from the 2019 ACE Plan proceeding. NS Power previously stated that riprap work, minimum freeboard work, and concrete erosion work were not required or were included in the project scope. The request seeks confirmation or clarification on whether these statements still apply.
Request IR-6: In response to NSUARB IR-65f) in the 2019 ACE Plan Proceeding (M08994), NS Power stated: Potential geotechnical issues were reviewed as part of the design phase of the project. Since the existing dam is founded on bedrock and...
AI summary NS Power responded to NSUARB IR-65f) in the 2019 ACE Plan Proceeding (M08994), stating that no geotechnical issues are anticipated for the new dam, as it will be constructed on the same footprint as the existing dam. The NSUARB is requesting confirmation, details on any changes, and information on whether a detailed geotechnical investigation was completed.
Request IR-7: - Given the new (as compared to the 2019 ACE Plan Submission) project requirements and costs for environmental permitting, fish passage, environmental offsetting, temporary lowering of the reservoir, and additional archaeolog...
AI summary The document requests NS Power to re-evaluate project options for the ACE Plan, considering new requirements such as environmental permitting and Mi'kmaw engagement, and to explain why Option 4 remains the lowest cost option or provide analysis if other options were considered.
Request IR-10: - Regarding the Account Variance Sheet on pages 5 and 6 of the current Application: - a) For the "Materials" Line Item: - i. Please identify the percentage increase in materials cost that NS Power has allowed for since the 2...
AI summary The document requests detailed explanations and justifications for various cost increases and exclusions in the Account Variance Sheet related to the 2019 ACE Plan Application, including materials, contracts, consulting, and Mi'kmaw Engagement costs.
lain how the cost was developed. - k) Please explain the significant increase in Consulting "Conceptual/Detailed design of refurb" cost as compared to the 2019 ACE Plan Application "Design" cost and explain how the cost was developed.
AI summary The text requests an explanation for the significant increase in the cost of 'Consulting Conceptual/Detailed design of refurb' compared to the 2019 ACE Plan Application 'Design' cost and how this cost was developed.