Matter: Nova Scotia Power Inc. - CI 51956 – 6P Mobile Substation Rewind U&U $635,776 (FIN)
2 passages 2 documents

2025 Ace Plan across all matters →

N-1Application 1 passage
Why do this project now? p. p. 1
Why do this project now? If 5P is required to be installed for an emergency situation it would leave several transformers without an available spare that can be quickly installed, therefore it is essential that the 6P mobile transformer be...

AI summary The urgency of repairing the 6P mobile transformer is highlighted due to the impending end of life of the 5P transformer, which would leave transformers without spare units in emergencies. The 5P is expected to be replaced as part of the 2018 ACE Plan.

100141Letter NSPI re: Capital Items Filed Outside the Quarter Package 1 passage
2024 ACE Plan Capital Items for Subsequent Approval p. p. 0
2024 ACE Plan Capital Items for Subsequent Approval • CI C0032664 – Energy Control Centre – Optimization Tools - $7,486,068 2024 ACE amount $4,329,150 $1,776,697 spent as at September 30, 2025 Non-Confidential

AI summary The document outlines a capital item for the 2024 ACE Plan related to the Energy Control Centre and optimization tools, with a total cost of $7,486,068, of which $4,329,150 was allocated under the 2024 ACE Plan and $1,776,697 had been spent by September 30, 2025.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →