Reason for Variance The increase of $448,476 from the 2026 ACE Plan subsequent submittal estimate of $1,315,495 is due to changes in the final design compared to the conceptual design. The preliminary design included 6 cfs of water flow ro...
AI summary The $448,476 increase in the 2026 ACE Plan's cost stems from design changes to avoid archaeological sites, requiring rerouting water flow from the powerhouse. This necessitated additional construction, materials, and higher-than-estimated RFP costs.