HomeMattersM12746
M12746 Closed Electricity

Nova Scotia Power Inc. - CI C0064966 – Tusket Tidal Pool Fish Passage - $1,763,971

Filed 03/13/2026 9 documents

What's happened

Filing Timeline

  • 17 Aug
    Decision
    NSEB Decision Letter now available approving Nova Scotia Power's $1,763,971 Tusket Tidal Pool Fish Passage capital expenditure
  • 28 May
    Document
  • 13 Mar
    Closing Evidence

The filings themselves

Documents

Key documents 1 file
  • 103228 Decision Letter PDF · 08/17/2026
Exhibits 4 files
  • N-1 Work Order - Redacted PDF · 03/13/2026
  • N-1(C) Work Order - Confidential PDF · 03/13/2026
  • N-2 NSPI (NSEB) RIR 1 to 9 - Redacted PDF · 06/18/2026
  • N-2(C) NSPI (NSEB) RIR 1 to 9 - Confidential PDF · 06/18/2026
Other documents 4 files
  • 101252 Letter enclosing work order and request for confidentiality PDF · 03/13/2026
  • 102173 NSEB (NSPI) IR-1 to IR-9 PDF · 05/28/2026
  • 102424 Letter NSPI re: RIRs PDF · 06/18/2026
  • 103228 Decision Letter PDF · 08/17/2026

What's discussed — click to drill in

Topics

Infrastructure Planning
29 passages across 3 documents
Capital Expenditures
27 passages across 4 documents
Environmental Compliance
22 passages across 5 documents
Renewable Energy
13 passages across 1 documents
Jurisdictional Questions
7 passages across 2 documents
Cost Considerations
5 passages across 2 documents
Regulatory Approval Processes
5 passages across 3 documents
Indigenous Communities
4 passages across 2 documents
Regulatory Oversight
4 passages across 3 documents
Asset Management
3 passages across 2 documents
Confidentiality
3 passages across 2 documents
Procurement Practices
3 passages across 3 documents
System Reliability
3 passages across 1 documents
2025 Ace Plan
2 passages across 2 documents
Electricity Generation
2 passages across 1 documents
Stakeholder Engagement
2 passages across 2 documents
Affordability
1 passages across 1 documents
Boards Regulatory Rules
1 passages across 1 documents
Capacity Costs
1 passages across 1 documents
Cost Effectiveness
1 passages across 1 documents
Cost To Customer
1 passages across 1 documents
Cybersecurity
1 passages across 1 documents
Depreciation Amortization
1 passages across 1 documents
Distribution Planning
1 passages across 1 documents
Energy And Regulatory Boards Act
1 passages across 1 documents
Environmental Goals And Climate Change Reduction Act
1 passages across 1 documents
Information Disclosure
1 passages across 1 documents
Non Energy Impacts
1 passages across 1 documents
Performance Monitoring
1 passages across 1 documents
Project Schedule
1 passages across 1 documents