CI C0064966 – Tusket Tidal Pool Fish Passage (NSEB M12746) NSPI Responses to Nova Scotia Energy Board Information Requests 1 Request IR-3: 27 the tidally influenced pool area, prepared project execution schedules that incorporated the 28 t...
AI summary NS Power evaluated various project options for the Tusket Tidal Pool Fish Passage, eliminating those that impacted wetlands, species at risk, and had high costs or maintenance requirements. Option A-2 was selected as the preferred alternative due to its lower environmental impact. No lower-cost alternatives provided acceptable mitigation outcomes.