Matter: Nova Scotia Power Inc. - CI C0064966 – Tusket Tidal Pool Fish Passage - $1,763,971
1 passage 1 document

Affordability across all matters →

103228Decision Letter 1 passage
CI # C0064966 Tusket Tidal Pool Fish Passage $1,763,971
CI # C0064966 Tusket Tidal Pool Fish Passage $1,763,971 This capital item was included in NS Power's 2026 ACE Plan with an estimated cost of $1,315,495, in the list of capital items for subsequent approval. In its application, NS Power not...

AI summary NS Power submitted a capital item for a fish passage project at Tusket Tidal Pool, requesting $1,763,971. The increase from the 2026 ACE Plan is due to updated design and costs. The Board approved the request after considering environmental concerns, stakeholder input, and the need for permanent mitigation to prevent fish mortality.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →