Matter: Nova Scotia Power Inc. - CI C0064966 – Tusket Tidal Pool Fish Passage - $1,763,971
1 passage 1 document

Depreciation Amortization across all matters →

N-1Work Order - Redacted 1 passage
Summary of Related CIs +/- 2 years: p. p. 1
Summary of Related CIs +/- 2 years: Pursuant to Section 11.2 of the CEJC, related CIs for Hydro projects include "Work completed on the same generating unit and dam structures, but not necessarily the same asset." • No other projects in 20...

AI summary The document outlines depreciation criteria for the Tusket River Hydro System's Hydraulic Production Plant, with a 25-year estimated asset life. Justification is based on environmental considerations under Section 11.2 of the CEJC, noting no related projects from 2024–2028.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →