Matter: E-ENS-R-15 - EfficiencyOne Application for approval of a Supply Agreement for Electricity Efficiency and Conservation Activities between Efficiency One and Nova Scotia Power Inc.- NSPI - 2016-2019 DSM Plan IN THE MATTER OF AN APPLICATION for Approval of a Supply Agreement for electricity efficiency and conservation activities between EfficiencyOne and Nova Scotia Power Incorporated, the establishment of a final agreement between the parties, and approval of a 2016-2018 Demand Side Management Resource Plan
6 passages 5 documents

Appeal Processes across all matters →

E-1EfficiencyOne Application - Revised Application see Exhibit E-43 2 passages
4.5.2 HST p. pp. 55-57
4.5.2 HST ENSC filed a ruling request with the Canada Revenue Agency (CRA) in October 2010 on the following two issues: 1) is the corporation making a taxable supply to NS Power and, as a result, whether the corporation is required to char...

AI summary ENSC requested CRA rulings on HST applicability for DSM programs and ITC eligibility, both denied in 2012. A 2015 CRA Appeals Division confirmation upheld the denial, but ENSTC may appeal to Canada's Tax Court. The 2014 Electricity Efficiency and Conservation Restructuring Act allows ENS to claim ITCs starting in 2015.

24. SHARING OF DATA AND INFORMATION p. p. 310
24. SHARING OF DATA AND INFORMATION - 24.1 EfficiencyOne shall work co-operatively with NSPI to provide NSPI with information and data from time to time in order to assist NSPI with planning and load forecasting as may be reasonably requir...

AI summary Section 24 mandates data sharing between EfficiencyOne and NSPI for planning and load forecasting, aligning with past practices. NSPI may seek UARB intervention if disputes arise over data requests.

62378Closing Statement - Nova Scotia Department of Energy 1 passage
Deferral and Amortization p. pp. 12-16
Deferral and Amortization - 41. The Province submits that a decision on how DSM costs should be recovered (i.e. whether they are deferred or expensed) should generally be made at the same time as the DSM budget is set. The Province submits...

AI summary The Province argues that decisions on deferring or expensing DSM costs should align with DSM budget approvals, balancing affordability and iterative processes. It acknowledges discussions with the Consensus Settlement Agreement parties on cost allocation and suggests deferring DSM expenses due to both short-term and long-term benefits. The Province clarifies that s.79M(6) may apply to NSPI, not E1, and proposes that E1's financing outside NSPI's rate base should be discussed within the Consensus Settlement Agreement framework.

63106Supply Agreement 1 passage
24. SHARING OF DATA AND INFORMATION p. p. 19
24. SHARING OF DATA AND INFORMATION - 24.1 EfficiencyOne shall work co-operatively with NSPI to provide NSPI with information and data from time to time in order to assist NSPI with planning and load forecasting as may be reasonably requir...

AI summary EfficiencyOne must cooperatively share data with NSPI for planning and load forecasting, aligning with past practices. NSPI may seek UARB intervention if disputes arise over data access requests.

63151Supply Agreement Blackline Feb Application v. Sep Compliance Filing 1 passage
24. SHARING OF DATA AND INFORMATION p. p. 19
24. SHARING OF DATA AND INFORMATION - 24.1 EfficiencyOne shall work co-operatively with NSPI to provide NSPI with information and data from time to time in order to assist NSPI with planning and load forecasting as may be reasonably requir...

AI summary EfficiencyOne must cooperatively share data with NSPI for planning and load forecasting, aligned with past practices. NSPI may seek UARB intervention if disputes arise over data access requests.

63292Supply Agreement EfficiencyOne and NSPI Form of Agreement Final Executed in Counterparts 1 passage
24. SHARING OF DATA AND INFORMATION p. p. 19
24. SHARING OF DATA AND INFORMATION - 24.1 EfficiencyOne shall work co-operatively with NSPI to provide NSPI with information and data from time to time in order to assist NSPI with planning and load forecasting as may be reasonably requir...

AI summary EfficiencyOne must cooperate with NSPI to provide data for planning and load forecasting, aligning with past practices. NSPI may seek UARB intervention if disputes arise over data access requests.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →