E-ENS-R-15 - EfficiencyOne Application for approval of a Supply Agreement for Electricity Efficiency and Conservation Activities between Efficiency One and Nova Scotia Power Inc.- NSPI - 2016-2019 DSM Plan IN THE MATTER OF AN APPLICATION for Approval of a Supply Agreement for electricity efficiency and conservation activities between EfficiencyOne and Nova Scotia Power Incorporated, the establishment of a final agreement between the parties, and approval of a 2016-2018 Demand Side Management Resource Plan
What's happened
Filing Timeline
-
14 Apr
DocumentEfficiencyOne files revised Excel spreadsheet in response to NSPI information request IR-17 in 2016–2019 DSM Supply Agreement proceeding.
-
09 Apr
DocumentNova Scotia Power filed its Alternative DSM Plan spreadsheet (Appendix B) comparing EfficiencyOne's proposed 2016–2018 DSM program costs and savings against NSPI's lower-cost alternative for the E-ENS-R-15 supply agreement proceeding.
-
27 Mar
RIRNova Scotia Power responds to Regulator Information Requests 1–47 regarding EfficiencyOne's proposed 2016–2019 DSM Supply Agreement.
-
27 Feb
DocumentEfficiencyOne files 2014 DSM program evaluation reports in support of its application for a 2016–2019 supply agreement with Nova Scotia Power.
The filings themselves
Documents
Key documents
6 files
- 60725 Notice of Hearing
- 60726 Hearing Order
- 60881 Amended Hearing Order
- 62510 Board Decision Letter re ICF International Memorandum
- 62745 Board Decision
- 63307 Board Order
Exhibits
57 files
- E-1 EfficiencyOne Application - Revised Application see Exhibit E-43
- E-2 2014 Electricity Demand Side Management Plan Evaluation Reports
- E-3 NTGR Example Calculations - Excel Spreadsheet
- E-4 REVISED Econoler Home Energy Report - March 18-2015
- E-5 REDLINE Version of Revised Econoler Home Energy Report - March 18-2015
- E-6 Verification Review of Program Year 2014 Evaluation Results
- E-7 E1 (NSPI) RIR-1 to RIR-47
- E-7(C)-(iv) E1 (NSPI) RIR-43, Attachment 1 and 2, Confidential
- E-7(v) E1 (NSPI) RIR-17, Attachment 2, Excel Spreadsheet
- E-7-(i) E1 (NSPI) RIR-10, Attachment 1, Excel Spreadsheet
- E-7-(ii) E1 (NSPI) RIR-17, Attachment 1, Excel Spreadsheet
- E-7-(iii) E1 (NSPI) RIR-19, Attachment 1, Excel Spreadsheet
- E-8 Evidence of Nova Scotia Power Inc.
- E-8-(i) Appendix B - NSPI Alternate DSM Plan - Excel Spreadsheet
- E-9 Revised Response by E1 to NSPI IR-17, Attachment 2- Excel Spreadsheet
- E-10 NSPI (AEC) RIRs to IR-1 to IR-5
- E-11 NSPI (CA) RIRs to IR-1 to IR-41 - Redacted
- E-11(C) NSPI (CA) RIRs to IR-1 to IR-41 - Confidential
- E-11(C)-(ix) NSPI (CA) IR-20 Attachment 9 F - Confidential - Electronic
- E-11(C)-(x) NSPI (CA) IR-20 Attachment 10 F - Confidential - Electronic
- E-11(C)-(xi) NSPI (CA) IR-20 Attachment 11 F - Confidential - Electronic
- E-11(C)-(xii) NSPI (CA) IR-20 Attachment 12 F - Confidential - Electronic
- E-11-(i) NSPI (CA) IR-20, Attachment 1
- E-11-(ii) NSPI (CA) IR-20, Attachment 2
- E-11-(iii) NSPI (CA) IR-20, Attachment 3
- E-11-(iv) NSPI (CA) IR-20, Attachment 4
- E-11-(v) NSPI (CA) IR-20, Attachment 5
- E-11-(vi) NSPI (CA) IR-20, Attachment 6
- E-11-(vii) NSPI (CA) IR-20, Attachment 7
- E-11-(viii) NSPI (CA) IR-20, Attachment 8
- E-11-(xiii) NSPI (CA) IR-20, Attachment 13
- E-11-(xiv) NSPI (CA) IR-30, Attachment 1
- E-11-(xix) NSPI (CA) IR-30, Attachment 7
- E-11-(xv) NSPI (CA) IR-30, Attachment 3
- E-11-(xvi) NSPI (CA) IR-30, Attachment 4
- E-11-(xvii) NSPI (CA) IR-30, Attachment 5
- E-11-(xviii) NSPI (CA) IR-30, Attachment 6
- E-11-(xx) NSPI (CA) IR-30, Attachment 8
- E-12 NSPI (EAC) RIRs to IR-1 to IR-8
- E-12-(i) NSPI (EAC) IR-07, Attachment 1
- E-13 NSPI (E1) RIRs to IR-1 to IR-50 - Redacted
- E-13(C) NSPI (E1) RIRs to IR-1 to IR-50 - Confidential
- E-13(C)-(i) NSPI (E1) IR-12 Attachment 1 F - Confidential - Electronic - Scenario A - Excel
- E-13(C)-(ii) NSPI (E1) IR-12 Attachment 2 F - Confidential - Electronic - Scenario B - Excel
- E-13(C)-(iii) NSPI (E1) IR-12 Attachment 3 F - Confidential - Electronic - Appendix A, Attachment C - Excel
- E-13(C)-(iv) NSPI (E1) IR-12 Attachment 4 F - Confidential - Electronic - Scenario D - Excel
- E-13-(v) NSPI (E1) IR-20, Attachment 1
- E-13-(vi) NSPI (E1) IR-25, Attachment 1
- E-13-(vii) NSPI (E1) IR-50, Attachment 1
- E-13-(viii) NSPI (E1) IR-50, Attachment 2
- E-14 NSPI (IG) RIRs to IR-1 to IR-4
- E-15 NSPI (Multeese) RIRs to IR-1 to IR-19 - Redacted
- E-15(C) NSPI (Multeese) RIRs to IR-1 to IR-19 - Confidential
- E-16 NSPI (NSUARB) RIRs to IR-1 to IR-15
- E-16-(i) NSPI (NSUARB) IR-04, Attachment 1
- E-17 NSPI (Peach) RIRs to IR-1 to IR-24
- E-17-(i) NSPI (Peach) IR-16, Attachment 1
Other documents
57 files
- 61805 Letter from EfficiencyOne re Board Only Confidential and confidential responses to the IRs
- 61806 Board letter re approval of print exemptions requested by EfficiencyOne
- 61807 Letter from NSPI requesting IR responses and/or attachments described herein to be held in confidence
- 61808 Confidential Undertaking
- 61809 Letter from NSPI requesting print exemptions
- 61810 Board Letter approving NSPI's print exemption requests
- 61829 Board Acknowledgment of E1 and NSPI responses to IRs
- 61830 Board letter approving confidentiality undertaking
- 61938 Letter from NSPI re outlining the revisions in the Revised DSM Plan Evidence and the Appendix B filed June 1, 2015
- 61992 Letter from E1 setting out revisions in application re-filed on June 4/15
- 62036 MEUNSC Request to Intervene
- 62037 Comments on MEUNSC Request by E1
- 62038 Board Letter - MEUNSC Request to Intervene Declined
- 62048 Board letter attaching List of Speakers for Evening Session
- 62203 Undertaking List
- 62204 Board letter enclosing Undertaking List
- 62210 Letter from EI enclosing non-confidential version of U4
- 62213 Board Letter to EOne re print exemption & confidentiality request
- 62257 Letter to E1 re the Board requests detailed explanation for request of confidential treatment of U-4
- 62258 Letter from E1 in response to Board's letter of June 25 re detailed explanation for confidential treatment of U-4
- 62282 Board Letter re confidential filings
- 62291 Letter from E1 enclosing non-confidential portions of U-4 as directed by the Board
- 62375 Closing Submission - Affordable Energy Coalition
- 62377 Closing Submission - Small Business Advocate
- 62378 Closing Statement - Nova Scotia Department of Energy
- 62379 Closing Submission - Nova Scotia Power Inc.
- 62380 Closing Submission - Efficiency One
- 62381 Closing Submission - Industrial Group
- 62382 Closing Submission - Consumer Advocate
- 62386 Final Submission - Ecology Action Centre
- 62420 Board Letter to NSPI re does NSPI have any objection to Gogan's letter of July 9
- 62435 Letter from counsel for NSPI re Board's letter of July 13 and Mr. Gogan's letter of July 9
- 62457 Reply Submission - NSDOE
- 62458 Rebuttal Submission - EfficiencyOne
- 62459 Reply Submission - Consumer Advocate
- 62460 Reply Submission - NSPI
- 62461 Letter from E1 re raise procedural matter with Board regarding NSPI Closing Submission
- 62462 Letter from SBA re not filing reply submission
- 62510 Board Decision Letter re ICF International Memorandum
- 62745 Board Decision
- 63104 Cover letter enclosing compliance filing
- 63105 Compliance Filing
- 63106 Supply Agreement
- 63107 2016-2018 DSM Supply Agreement - Schedule E - Final with Track Changes
- 63134 Board letter re black-line version required to be filed, if there were changes
- 63151 Supply Agreement Blackline Feb Application v. Sep Compliance Filing
- 63231 Compliance Comments - Small Business Advocate
- 63232 Compliance Comments - Industrial Group
- 63292 Supply Agreement EfficiencyOne and NSPI Form of Agreement Final Executed in Counterparts
- 63307 Board Order
- 63791 Grant Thornton Report - Financing Demand Side Management
- 63792 E1 Covering Letter from E1 (Gogan)
- 63821 Board Letter re Grant Thornton Report
- 63876 Board Letter re Financing DSM Grant Thornton Report
- 64047 Board letter re Financing DSM Grant Thornton Report
- 64860 Letter from EfficiencyOne re an update of efforts
- 64861 Grant Thornton Summary Update
What's discussed — click to drill in
Topics
Energy Efficiency
1470 passages across 41 documents
Demand Side Management
1257 passages across 71 documents
Program Evaluation
455 passages across 33 documents
Residential Programs
333 passages across 19 documents
Energy Efficiency Budgets
316 passages across 30 documents
Energy Efficiency Resource Assessment Model
301 passages across 17 documents
Regulatory Compliance
218 passages across 34 documents
Rate Design
213 passages across 41 documents
Energy Efficiency Financing
177 passages across 18 documents
Home Energy Report
173 passages across 11 documents
Incentive Structures
169 passages across 29 documents
Cost Effectiveness
163 passages across 32 documents
Hearing Procedures
155 passages across 52 documents
Customer Service
154 passages across 15 documents
Public Utilities Act Nova Scotia
127 passages across 33 documents
Affordability
125 passages across 28 documents
Regulatory Oversight
119 passages across 32 documents
Performance Monitoring
118 passages across 21 documents
Appliance Standards
115 passages across 12 documents
Free Ridership Measurement
113 passages across 7 documents
Confidentiality
111 passages across 34 documents
Stakeholder Engagement
109 passages across 22 documents
Procurement Practices
104 passages across 40 documents
Infrastructure Planning
93 passages across 22 documents
Net To Gross Evaluation
89 passages across 3 documents
Rates And Money
89 passages across 19 documents
Demand Side Management Resource Plan
88 passages across 20 documents
Customer Research
85 passages across 9 documents
Cost Recovery
84 passages across 31 documents
Cost Considerations
78 passages across 24 documents
Regulatory Approval Processes
56 passages across 21 documents
Integrated Resource Plan
55 passages across 12 documents
Low Income Programs
50 passages across 19 documents
Electricity Efficiency And Conservation Restructuring 2014 Act
49 passages across 13 documents
2023-2026 DSM Plan
48 passages across 15 documents
Instant Savings
44 passages across 4 documents
Revenue Requirement
44 passages across 15 documents
Building Efficiency
43 passages across 8 documents
Information Disclosure
43 passages across 26 documents
Electricity Efficiency And Conservation Act Nova Scotia
42 passages across 9 documents
Energy Efficiency Conservation Agreement
42 passages across 7 documents
Participant Costs Benefits
42 passages across 11 documents
Program Requirements
41 passages across 9 documents
Program Participation Metrics
40 passages across 6 documents
Evidence Requirements
39 passages across 23 documents
Renewable Energy
38 passages across 15 documents
Market Transformation
35 passages across 14 documents
Heat Pumps
34 passages across 3 documents
Commercial Industrial Programs
33 passages across 11 documents
Energy Efficiency Codes
29 passages across 3 documents
Fuel Cost Adjustment
29 passages across 16 documents
Rate Base
27 passages across 14 documents
Environmental Compliance
26 passages across 13 documents
Forecasting Methodology
26 passages across 11 documents
Innovation Research
26 passages across 12 documents
Energy Management Information Systems
20 passages across 3 documents
Rate Smoothing Adjustment
20 passages across 10 documents
Residential Demand Response Program
20 passages across 5 documents
Cost To Customer
19 passages across 9 documents
Equity Access
19 passages across 12 documents
Rental Properties And Condos
19 passages across 4 documents
Efficient Product Installation Epi
17 passages across 8 documents
Financial Instruments
17 passages across 12 documents
Capital Expenditures
16 passages across 11 documents
Small Business Energy Solutions
16 passages across 3 documents
Complaint Resolution
15 passages across 9 documents
Billing Procedures
14 passages across 9 documents
Harmonized Sales Tax
14 passages across 8 documents
Lighting Technology
14 passages across 5 documents
Load Management
14 passages across 10 documents
Property Assessed Clean Energy
14 passages across 7 documents
Rate Rider
14 passages across 8 documents
Residential Behaviour
13 passages across 5 documents
Standardized Filing
13 passages across 8 documents
Renewable Electricity Regulations
12 passages across 9 documents
Affordable Multifamily Housing And Non Profit Organizations Amf
11 passages across 7 documents
BNI Custom Incentive Program
11 passages across 6 documents
Enabling Strategies Es
11 passages across 6 documents
Operating Expenses
11 passages across 6 documents
Bca
10 passages across 4 documents
Efficiency Nova Scotia Corporation Act
10 passages across 5 documents
Technical Reference Manual
10 passages across 2 documents
Best Interests Of Customers
9 passages across 4 documents
Comfit
9 passages across 8 documents
Emergency Response
9 passages across 6 documents
Financing Alternatives
9 passages across 2 documents
Home Energy Assessment
9 passages across 3 documents
Cost Deferral
8 passages across 8 documents
Disconnection Procedures
8 passages across 6 documents
Distribution Planning
8 passages across 4 documents
Residential Energy Affordability Program
8 passages across 2 documents
Appliance Retirement
7 passages across 3 documents
Contract Terms
7 passages across 6 documents
Efficiency Maine
7 passages across 6 documents
Energy Efficiency Resource Standards
7 passages across 4 documents
Innovative Financing
7 passages across 4 documents
New Residential Program
7 passages across 4 documents
Residential Solar Pv Program
7 passages across 3 documents
Resource Costs
7 passages across 4 documents
Appeal Processes
6 passages across 5 documents
Compliance Legislation
6 passages across 4 documents
Cybersecurity
6 passages across 6 documents
Programs And Customers
6 passages across 4 documents
Prudency Reviews
6 passages across 4 documents
Return On Equity
6 passages across 5 documents
Accounting Policies
5 passages across 5 documents
BNI
5 passages across 2 documents
Capacity Costs
5 passages across 4 documents
Capacity Market Participation
5 passages across 2 documents
Building Regulations
4 passages across 1 documents
Business Energy Rebates
4 passages across 2 documents
Climate Adaptation
4 passages across 3 documents
Dcrr
4 passages across 4 documents
Demand Side Management Advisory Group
4 passages across 3 documents
Demand Side Management Purchase Agreement
4 passages across 3 documents
Direct Installation
4 passages across 2 documents
Efficiency Preferred Partner
4 passages across 2 documents
Homewarming
4 passages across 2 documents
Incentive Costs
4 passages across 4 documents
Income Tax Act
4 passages across 4 documents
Performance Plus
4 passages across 2 documents
Power Purchase Agreement
4 passages across 3 documents
Public Interest
4 passages across 3 documents
Strategic Energy Management
4 passages across 2 documents
Surplus Return
4 passages across 4 documents
2025 Ace Plan
3 passages across 2 documents
BNI Efficient Product Rebates Program
3 passages across 3 documents
Debt Service Coverage Ratio
3 passages across 3 documents
Energy Efficiency Portfolio Standard Eeps
3 passages across 1 documents
Green Heat
3 passages across 3 documents
Legal Procedures
3 passages across 3 documents
Multi Year Planning Cycle
3 passages across 3 documents
National Energy Code For Buildings
3 passages across 2 documents
Non Energy Impacts
3 passages across 1 documents
Policy And Legislation
3 passages across 3 documents
System Reliability
3 passages across 3 documents
Utility Governance
3 passages across 3 documents
Depreciation Amortization
2 passages across 2 documents
Education
2 passages across 2 documents
Electric Resource Assessment Model
2 passages across 1 documents
Electricity Generation
2 passages across 2 documents
Energy Usage Patterns
2 passages across 2 documents
Grid Modernization
2 passages across 2 documents
Solarhomes
2 passages across 2 documents
Transmission Planning
2 passages across 1 documents
Accounting Standards
1 passages across 1 documents
Asset Management
1 passages across 1 documents
Asset Retirement Obligation
1 passages across 1 documents
Boards Regulatory Rules
1 passages across 1 documents
Budgets And Targets
1 passages across 1 documents
Building Optimization Service
1 passages across 1 documents
Distribution
1 passages across 1 documents
Efficiency Trade Network
1 passages across 1 documents
Energyforward New Homes
1 passages across 1 documents
Environmental Goals And Climate Change Reduction Act
1 passages across 1 documents
Generation Grid Resources
1 passages across 1 documents
Legal Costs
1 passages across 1 documents
Legal Standards
1 passages across 1 documents
Market Penetration
1 passages across 1 documents
Securitization
1 passages across 1 documents
Smart Synergy
1 passages across 1 documents
System Benefits Charge
1 passages across 1 documents
Tariff Design
1 passages across 1 documents
Upfront Costs
1 passages across 1 documents