19. DISPUTE RESOLUTION - 19.1 In the event of a dispute in connection with this Agreement, a senior representative of EfficiencyOne and a senior representative of NSPI shall promptly meet to discuss and resolve the dispute and the Parties...
AI summary The section outlines dispute resolution procedures between EfficiencyOne and NSPI, including initial meetings, timeframes for resolution, referral to the UARB if unresolved, and EfficiencyOne's obligation to perform EECA unless authorized by UARB.
24. SHARING OF DATA AND INFORMATION - 24.1 EfficiencyOne shall work co-operatively with NSPI to provide NSPI with information and data from time to time in order to assist NSPI with planning and load forecasting as may be reasonably requir...
AI summary EfficiencyOne must share data with NSPI for planning and load forecasting, adhering to past practices. Disputes over data requests may be resolved by applying to the UARB. Key entities involved are EfficiencyOne, NSPI, and UARB.
7) Resolution Process a) if consensus is not achieved on any of the above items to be addressed within the DSM Advisory Group, such items will be presented to the UARB for determination not later than June 30th, 2016.
AI summary If the DSM Advisory Group fails to reach consensus on items by June 30, 2016, those items will be submitted to the UARB for determination.