E-1EfficiencyOne Application - Revised Application see Exhibit E-43
3 passages
lting in lower unit costs than found in prior approved DSM Plans. Navigant, 2015 Investing in Demand-side Resources: Considering Affordability, February 26, 2015, page 4 ENS has addressed short-term affordability considerations in multiple...
AI summary The document discusses ENS's approach to affordability in its DSM Plan, noting that the proposed Plan requires less investment than initially modeled, resulting in lower unit costs and addressing short-term affordability concerns. It also references the 2014 IRP and the impact of DSM-related rate increases on the Fuel Adjustment Mechanism.
Assumptions used in ENS's 2016-2018 Rate and Bill Impact Analysis Stakeholder Stakeholder Comment ENSC's Response Inclusion in the model expressed as $/kW, rather than $/MWh. The value of avoided capacity is usually assessed by determining...
AI summary The stakeholder comments highlight concerns with the assumptions used in ENS's 2016-2018 Rate and Bill Impact Analysis, particularly regarding the outdated avoided capacity cost and the exclusion of fuel cost benefits from DSM in the model. ENS acknowledges the concerns and is open to refining the analysis.
Societal NEBs While we have discussed participant and utility NEBs, DSM is also known to generate non-energy benefits for society as a whole, primarily through (1) environmental benefits (to the extent they are not already internalized in...
AI summary The text discusses societal non-energy benefits (NEBs) from demand-side management (DSM), including environmental and macroeconomic benefits. Environmental benefits include reduced emissions, while macroeconomic benefits involve increased GDP and job creation. It critiques the Total Resource Cost (TRC) method for being biased against energy efficiency and not fully capturing societal benefits. The document notes that in Nova Scotia, carbon emissions are already partially internalized due to legislation.
E-11NSPI (CA) RIRs to IR-1 to IR-41 - Redacted
6 passages
NON-CONFIDENTIAL 1 Request IR-5: 2 3 Reference: 2016-2018 DSM Plan NS Power Evidence Appendix B 4 - 5 Please provide residential increases in rates and Fuel Adjustment Mechanism charges in - 6 both absolute and percentage terms since 2011?...
AI summary The document includes a request (IR-5) asking for residential rate increases and Fuel Adjustment Mechanism charges since 2011, in both absolute and percentage terms, along with a reference to the 2016-2018 DSM Plan evidence appendix.
9 Year Revenue increase due to GRA ($) % increase due to GRA Revenue increase due to FAM (all components combined including: BCF, AA, BA) ($) % increase to FAM (all components combined including: BCF, AA, BA) Composite revenue increase ($)...
AI summary The table shows revenue increases from the GRA and FAM mechanisms from 2011 to 2015, including dollar amounts and percentage changes. The data highlights fluctuations in revenue contributions from these mechanisms over the years.
NON-CONFIDENTIAL 1 Request IR-12: 2 3 Reference: 2016-2018 DSM Plan NS Power Evidence 4 - 5 Please provide annual spending by the largest categories of expenditures by NSPI since - 6 2011 and the absolute and percentage increase in them si...
AI summary The document contains a request (IR-12) for NSPI to provide annual spending data by category (fuel, salaries, capital expenditures, etc.) since 2011, with details on absolute and percentage increases.
NON-CONFIDENTIAL 1 Request IR-14: 2 3 Reference: 2016-2018 DSM Plan NS Power Evidence Appendix B 4 5 Please provide the fuel costs as percentage of expenditures for Canadian jurisdictions. 6 7 Response IR-14: 8 9 NS Power does not have thi...
AI summary The document contains a request for fuel costs as a percentage of expenditures for Canadian jurisdictions under the 2016-2018 DSM Plan. NS Power responded that it does not have this information.
CONFIDENTIAL (Attachments Only) 1 (d) For each of the five plans, please provide the annual capacity factor for each coal- or 2 gas-fired plant. 3 4 (e) For each of the five plans, please provide the annual projected variable cost of each...
AI summary The document contains a series of information requests from the Consumer Advocate (CA) to Nova Scotia Power Inc. (NSPI) regarding the 2016-2018 DSM Plan (NSUARB M06733). Requests include capacity factors, variable costs, renewable energy supply comparisons, and analyses of the Port Hawkesbury biomass plant and Lingan FGDs' cost impacts under different scenarios.
Fuel and Purchased Power, Thermal and Hydro O&M, Capital for new resources in the plan, DSM program administrator costs, sustaining capital (k$) Half Low Base CRP Mid/FGD cents/kWh CRP1-1-FGD CRP2-17-FGD No DSM Plan CRP Mid/FGD Low DSM Pla...
AI summary The text presents a table of fuel and purchased power costs, capital expenditures, and DSM program administrator costs over multiple years, showing variations between different scenarios such as 'No DSM Plan' and 'Low DSM Plan'. The data includes cents per kWh and percent changes compared to the 'No DSM Plan' scenario, highlighting the impact of demand-side management on costs.
E-17NSPI (Peach) RIRs to IR-1 to IR-24
5 passages
Request IR-11: Utilities, whether traditional for-profit generating utilities or the new not-for-profit energy conservation/energy efficiency utilities operate under regulatory oversight and using planning processes. In their nature, plann...
AI summary The text contrasts NSPI's use of the Fuel Adjustment Mechanism (FAM) for financial risk buffering with E1's use of a reserve fund, questioning whether these approaches equitably address utility financial responsibility. It highlights differences in regulatory mechanisms for managing cost overruns and operational uncertainties between traditional and energy efficiency utilities.
NON-CONFIDENTIAL (c) Is the FAM essentially a balancing account such that if NSPI has a cost overrun in this area in a particular year, NSPI can be eventually made whole by a rate adjustment to collect additional revenue from customers tha...
AI summary The Fuel Adjustment Mechanism (FAM) ensures customers pay actual fuel costs, not acting as a reserve fund. NSPI emphasizes FAM's audit process and distinction from non-fuel cost mechanisms. E1's reserve request is contrasted with FAM's design, which manages rate adjustments based on prudently incurred fuel costs, not operational reserves.
NON-CONFIDENTIAL 2 (c) Please refer to parts (a) and (b). 4 (d) The table below provides the 2015 FAM AA/BA Riders by class as approved by the
AI summary The text references a table providing 2015 FAM AA/BA Riders by class as approved by the regulatory body, with a note to refer to previous parts for more details.
5 UARB, in absolute and percentage terms. FAM Amounts as a percentage of Base Cost Rate Revenues in 2015 Rate Class Revenues at base cost rates FAM Amounts FAM Amounts as a percentage of Revenue FAM AA FAM BA Total FAM AA FAM BA Total Resi...
AI summary The table presents the Fuel Adjustment Mechanism (FAM) amounts as a percentage of base cost rate revenues across various rate classes in 2015. It highlights the distribution of FAM AA, FAM BA, and total FAM amounts relative to revenue for different customer segments.
NON-CONFIDENTIAL Project Year Application Matter No. Date Filed Exhibit No. Fuel Adjustment Mechanism (FAM) – Base Cost of Fuel 2011 2011 FAM Base Cost of Fuel M03285 August 16, 2010 N-10 2010 P-887(1) – Nova Scotia Power Inc. (NSPI) – Ann...
AI summary This table lists various Fuel Adjustment Mechanism (FAM) proceedings related to Nova Scotia Power Inc. (NSPI) from 2010 to 2015, including matter numbers, dates filed, and exhibit numbers associated with each proceeding.