E-1EfficiencyOne Application - Revised Application see Exhibit E-43
153 passages
NOTICE OF APPLICATION TO: The Nova Scotia Utility and Review Board ("UARB" or "the Board") - 1. The Electricity Efficiency and Conservation Restructuring (201 4) Act, S.N.S. 2014, c. 5 effected a new regime for the delivery of electricity...
AI summary EfficiencyOne seeks a Board decision to finalize a three-year Supply Agreement with NSPI under the Public Utilities Act, following failed negotiations. The application references a prior franchise granted in 2014 under the Electricity Efficiency and Conservation Restructuring Act, and cites Board Order M06247. EfficiencyOne asserts the agreement serves the public interest.
Revisions to The Public Utilities Act , proposed through the Electricity Efficiency and Conservation Restructuring (2014) Act , were proclaimed on May 1, 2014. Highlights of the legislation affecting this DSM Resource Plan include the foll...
AI summary This text discusses legislative changes to the Public Utilities Act through the Electricity Efficiency and Conservation Restructuring (2014) Act, effective from May 1, 2014. Key changes include the requirement for NS Power to implement cost-effective energy efficiency and conservation activities, the establishment of an ENS franchise, and the UARB's role in approving contracts and setting performance requirements.
1 2. 2014 DSM RESULTS 2
AI summary This section discusses the 2014 Demand Side Management (DSM) results, involving Nova Scotia Power Inc. (NSPI) and Efficiency Nova Scotia (ENS), under regulatory oversight by the Utility and Ratepayer Board (UARB). Key entities include KPMG and references to the Integrated Resource Plan (IRP).
3 2.1 2014 DSM Expenditures and Energy Savings Results 4 On June 4, 2012, the UARB approved years 2013 and 2014 of ENSC's 2013-2015 DSM Plan application. The approved DSM Plan identified an overall 2014 energy-savings target of 137.8 GWh f...
AI summary The UARB approved ENSC's 2013-2015 DSM Plan in 2012, setting a 2014 energy-savings target of 137.8 GWh. The text provides unaudited expenditures and energy savings results for 2014, as outlined in Figure 2.1.
9 10 Figure 2.1 - 2014 DSM Plan Actual Expenditures and Evaluated Energy Savings 2014 Plan Targets as Filed Mid-Course Adjustment Actual Expenditures1 $M Energy Savings GWh Expenditures1 $M Energy Savings GWh Expenditures1 $M Energy Saving...
AI summary Figure 2.1 presents a comparison of the 2014 DSM Plan's expenditures and energy savings targets versus actual outcomes. It shows that actual energy savings exceeded the original plan targets, with total energy savings reaching 151.9 GWh compared to the 137.8 GWh target. Expenditures were also lower than initially planned.
2.2 2014 DSM Programs ENSC exceeded target in 2014, achieving 151.9 GWh of energy savings compared to the UARB-approved target of 137.8 GWh. These savings include results from both the Residential and Business, Non-profit, and Institutiona...
AI summary ENSC exceeded 2014 DSM energy savings targets by 14.1 GWh, driven by the Home Energy Report program. Customer satisfaction remained stable at 91.2, and results aligned with the UARB-approved 137.8 GWh target. The NSUARB (2012) DSM Settlement Agreement is referenced.
Existing Residential The Existing Residential program, comprised of the Residential Direct Install, Rental Properties and Condos, Home Energy Assessment, Green Heat, Residential Solar components, and Low Income Homeowner services, achieved...
AI summary The Existing Residential program exceeded its 2014 energy savings target (37.0 GWh vs. 34.2 GWh), with ENSC agreeing to separately report low-income program results under the 2015 DSM Settlement Agreement. The RDI component increased installations by switching from CFLs to LEDs, reducing free ridership and boosting participation.
Education and Outreach In 2014, ENSC connected with Nova Scotians in a number of ways to continue its work in energy efficiency education and outreach. Such activities are critical in raising awareness of energy and the measures Nova Scoti...
AI summary In 2014, ENSC conducted energy efficiency education through initiatives like the LED Holiday Light Exchange, which collected 12,600 incandescent light sets and distributed 6,343 LED sets across 117 communities. The program aimed to raise awareness rather than focus solely on energy savings, contributing 0.2 GWh savings to the Efficient Product Rebates (Residential) program.
3. 2016-2018 DSM RESOURCE PLAN
AI summary The 2016-2018 DSM Resource Plan outlines Nova Scotia Power Inc.'s (NSPI) demand-side management initiatives, including Efficiency Nova Scotia (ENS) programs. The plan is subject to regulatory oversight by the Nova Scotia Utility and Ratepayer Board (UARB) and involves stakeholder input from entities like KPMG and the Canadian Advisory Council on Energy Efficiency (CACEE).
3.1 Summary The 2016-2018 DSM Resource Plan, as presented in Appendix A, is a three-year plan in accordance with the requirements of the Public Utilities Act. The Plan proposes a three- year energy savings target and a three-year system pe...
AI summary The 2016-2018 DSM Resource Plan aligns with the Public Utilities Act, setting energy and peak demand savings targets. ENS will adapt programs based on research, improve customer engagement, and implement Enabling Strategies like education, research, and market transformation initiatives to drive energy efficiency in Nova Scotia.
3.2 Energy Savings and Investment 9 Figure 3.1 provides a summary of the energy and demand savings and investment for the 2016-2018 DSM Plan. 1213 11
AI summary The section discusses energy savings and investment under the 2016-2018 DSM Plan, referencing a summary provided in Figure 3.1. It outlines the context and scope of energy savings initiatives during this period.
Annual avoided costs, calculated using ENSC's DSM Potential Study at the Base Level, were provided by NS Power. They include the cost of energy and capacity. Figures 3.2, 3.3, and 3.4 provide the program-level savings and investment for 20...
AI summary The text discusses annual avoided costs calculated by ENSC's DSM Potential Study, including energy and capacity costs. It references program-level savings and investment figures from 2016 to 2018 and explains terms like TRC and PAC, which are benefit/cost ratios used to evaluate the efficiency of demand-side management programs.
Figure 3.2 - 2016 DSM Resource Plan Investment and Savings 2016 Investment ($ million) Lifetime Benefits ($ million) a Incremental Annual Net Energy Savings at Generator (GWh) Incremental Annual Net Demand Savings at Generator (MW) Total R...
AI summary Figure 3.2 presents the 2016 DSM Resource Plan investment and savings, detailing program investments, benefits, and energy and demand savings across residential, business, nonprofit, and institutional sectors, along with associated cost tests.
Figure 3.3- 2017 DSM Resource Plan Investment and Savings 2017 Investment ($ million) Lifetime Benefits ($ million) a Incremental Annual Net Energy Savings at Generator (GWh) Incremental Annual Net Demand Savings at Generator (MW) Total Re...
AI summary The 2017 DSM Resource Plan outlines investments and savings across various demand-side management programs in Nova Scotia, including residential and business initiatives, with figures detailing investment amounts, lifetime benefits, and energy and demand savings.
Figure 3.4 - 2018 DSM Resource Plan Investment and Savings 2018 Investment ($ million) Lifetime Benefits ($ million) a Incremental Annual Net Energy Savings at Generator (GWh) Incremental Annual Net Demand Savings at Generator (MW) Total R...
AI summary Figure 3.4 presents the 2018 DSM Resource Plan investment and savings, detailing program investments, lifetime benefits, and energy and demand savings across residential, business, nonprofit, and institutional programs, along with enabling strategies.
4. DEVELOPMENT OF THE 2016-2018 DSM RESOURCE PLAN To aid in the preparation of the 2016-2018 DSM Resource Plan, ENS engaged Navigant and Dunsky Energy Consulting (Dunsky). ENS and NS Power also held ongoing discussions from fall 2014 until...
AI summary ENS engaged Navigant and Dunsky to develop the 2016-2018 DSM Resource Plan, adjusting costs after discussions with NS Power. The plan aimed to minimize program impacts while reducing expenses, with a preliminary overview presented to the DSM Advisory Group in February 2015.
4.1 Development of 2016-2018 DSM Program Targets and Investment The 2016-2018 DSM Resource Plan has been developed based on ENS's growing experience and history in delivering successful DSM programs and services to Nova Scotians. As part o...
AI summary ENS developed the 2016-2018 DSM Resource Plan using Navigant Consulting's EL-RAM model, aligning with cost-effective targets and investment levels. The Plan's 405.9 GWh energy savings and 62.5 MW demand savings aim to balance affordability with long-term energy needs, referencing NS Power's 2014 IRP and updated assumptions. ENS emphasizes reduced rate pressures and capacity additions compared to prior scenarios.
4.1.1 Results of NS Power's 2014 Integrated Resource Plan (IRP) Process The Preferred Resource Plan from NS Power's 2014 IRP specified that the Candidate Resource Plan modelled by Synapse Engineering Economics included a level of DSM consi...
AI summary NS Power's 2014 IRP identified a Candidate Resource Plan (CRP) with Mid-DSM levels from ENSC's study as yielding the lowest revenue requirement. High-DSM scenarios, when end-effects were considered, provided long-term benefits with lower ongoing costs. ENS opted against Mid-DSM due to legislative and structural changes, aligning instead with government policy and the Public Utilities Act's deferral/amortization provisions.
Additional Analysis by NS Power Throughout the fall of 2014 and into 2015, ENS worked with NS Power to incorporate additional NS Power-provided data into Navigant's model. Specifically, NS Power requested that ENS incorporate system load-s...
AI summary NS Power collaborated with ENS to integrate load-shape data into Navigant's model, resulting in lower demand savings than the Base-DSM Scenario. NS Power's analysis of the Low-DSM Scenario showed similar capacity additions avoided as the Mid-DSM Scenario until 2032, with results shared in February 2015.
2014 IRP No DSM Plan CRP01-01-FGD-R01 CRP2-17 FGD CRP Mid DSM/FGD Half-Low DSM Low DSM Base DSM (Synapse Model) 2015 2016 2017 ML Oct 2017 ML Oct 2017 ML Oct 2017 ML Oct 2017 ML Oct 2017 Lin 2 retire Lin 2 retire Lin 2 retire Lin 2 retire...
AI summary The document outlines a timeline of energy projects and capacity additions up to 2039, along with net present value (NPV) figures and planning study values. It discusses how ENS can build a DSM Plan that balances long-term DSM requirements with avoiding short- to mid-term capacity additions, based on the 2014 IRP analysis.
rm rate impacts, particularly with a legislated $100 million cap on amortization of DSM. ENS agrees the impacts would be inappropriate when considering the additional analysis undertaken by NS Power. While short-term rate impacts are impor...
AI summary The document discusses the importance of balancing short-term and long-term considerations in the development of a Demand Side Management (DSM) Resource Plan, emphasizing the negative impacts of pausing or reducing DSM investments. It highlights the long-term benefits of maintaining consistent DSM investment levels to avoid increased fuel costs and start-up expenses.
4.1.3 Affordability The Province of Nova Scotia issued an Electricity Review Report on February 18, 2015, which states that a "large part of Nova Scotia's electricity future relates to increasing energy efficiency. One of the best ways to...
AI summary The Province of Nova Scotia's 2015 Electricity Review Report emphasizes energy efficiency and affordability. ENS's 2016-2018 DSM plan reduces short-term costs compared to the Mid-DSM Scenario while preserving long-term benefits, balancing affordability and efficiency.
4.1.4 Cost Efficiency Opportunities The 2016-2018 DSM Resource Plan is cost effective, per legislative and UARB requirements for DSM. Results from Navigant's EL-RAM show that all programs are cost-effective in each year of the Plan, using...
AI summary The 2016-2018 DSM Resource Plan is deemed cost-effective using TRC and PAC tests. ENS aims to reduce unit costs through program adjustments like removing the Home Energy Report and reducing Enabling Strategies investment. Navigant's 2015 report is cited for affordability considerations.
4.1.5 Balanced Portfolio The overall DSM Resource Plan portfolio, as in past DSM Plans, has been based on a balanced portfolio approach. A balance has been sought between short- and long-term cost considerations, an ability to ensure acces...
AI summary The DSM Resource Plan employs a balanced portfolio approach, balancing short- and long-term costs, ensuring service access for Nova Scotians, and meeting ENS's energy savings targets within UARB-approved investment levels, with detailed explanations in Appendix F and recommendations from Dunsky Energy Consulting.
Consistent with the DSM Settlement Agreement for 2013-2014, approved by the UARB on June 4, 2012, ENS proposes to undertake the following regular reporting to the UARB 1 and DSM Advisory Group for the 2016-2018 DSM Resource Plan: 2 • Annua...
AI summary ENS proposes to submit regular reports to the UARB in accordance with the DSM Settlement Agreement for 2013-2014. These reports include an Annual Progress Report (APR), which will cover activities, performance indicators, cost and savings summaries, and corrective actions if energy savings targets are not met. ENS also plans to notify the UARB of significant changes to the DSM Resource Plan.
4.3.2 Quarterly Meetings and Reports ENS proposes to continue filing quarterly reports with the UARB for quarters one through three of each year, and meet with the DSM Advisory Group no less than three times per year. The meetings and repo...
AI summary ENS proposes quarterly reporting to UARB and three annual meetings with the DSM Advisory Group to update the 2016-2018 DSM Resource Plan.
4.4 Performance Requirements Efficiency Nova Scotia retained Dunsky Energy Consulting to provide advice on a set of performance requirements that ENS should propose for the UARB's consideration in this Application. Dunsky was asked to cond...
AI summary Efficiency Nova Scotia (ENS) engaged Dunsky Energy Consulting to advise on performance requirements for Demand Side Management (DSM) programs, with a focus on metrics and targets for the Nova Scotia Utility and Ratepayer Board (UARB). Dunsky's report, attached as Appendix G, includes a jurisdictional scan showing over 80% of North American regions use energy savings and peak demand savings as primary performance metrics. Definitions for performance-related terms are provided.
1 The figure below provides ENS's proposed Performance Indicators and Targets: 2 Figure 4.2 - Proposed Performance Indicators and Targets Performance Metrics Units (Portfolio Level) Annual Reporting Performance Indicators Approved 2016-201...
AI summary The text presents ENS's proposed Performance Indicators and Targets, including metrics for energy savings, peak demand savings, and other indicators such as total ratepayer benefits, total spending, and customer satisfaction.
ENS Performance Thresholds: Dunsky's paper points out that, in almost all of these regions, the achievement of Performance Targets is the basis for awarding a financial bonus to the DSM Administrator. As an example, in its response to NSPI...
AI summary ENS seeks approval from the UARB to define success as achieving minimum Performance Thresholds of 90% of UARB-approved Performance Targets, rather than requiring precise achievement of targets. This is due to the challenges of aligning a three-year DSM plan with a four-year development cycle, and the recognition that hitting targets exactly may not be realistic.
4.5.2 HST ENSC filed a ruling request with the Canada Revenue Agency (CRA) in October 2010 on the following two issues: 1) is the corporation making a taxable supply to NS Power and, as a result, whether the corporation is required to char...
AI summary ENSC requested CRA rulings on HST applicability for DSM programs and ITC eligibility, both denied in 2012. A 2015 CRA Appeals Division confirmation upheld the denial, but ENSTC may appeal to Canada's Tax Court. The 2014 Electricity Efficiency and Conservation Restructuring Act allows ENS to claim ITCs starting in 2015.
4.5.3 Establishment of an ENS Reserve Fund for DSM Expenses As a result of the recent legislative changes, EfficiencyOne, as the ENS franchise holder, assumes all financial risk associated with the delivery of DSM in Nova Scotia. As a stan...
AI summary EfficiencyOne, as the ENS franchise holder, assumes financial risk for DSM in Nova Scotia. A reserve fund is proposed to ensure financial stability, using operating surplus balances and governed by a reserve fund policy, without shifting responsibility for monitoring UARB-approved investment levels.
Grant Thornton, Maintaining sufficient reserves to protect your not-for-profit organization, Spring 2010 p. 7. 1 ENS has identified the following risk factors: 2 • Termination or expiration of the franchise; 3 • Reduction in other funding...
AI summary Efficiency Nova Scotia (ENS) identifies risks related to the termination of its franchise, changes in funding sources, and external factors. These risks include financial liabilities from franchise wind-up, potential absorption of non-discretionary costs if provincial funding is reduced, and external impacts on program delivery.
Calculation of the Reserve Fund: The reserve fund balance has been calculated using assumptions regarding the three risks identified which include DSM portion only of wind up costs, loss of cost synergies and the impact of external factors...
AI summary The reserve fund balance is calculated based on assumptions regarding three identified risks, including DSM portion of wind-up costs, loss of cost synergies, and external factors. Collins Barrow was engaged to review these assumptions and the reasonableness of the reserve calculation.
5.1 Cost-Effectiveness Testing The Total Resource Cost (TRC) test has been the primary cost-effectiveness test for demand-side management in Nova Scotia since the commencement of DSM-related activities in the province. In the early years,...
AI summary Nova Scotia's DSM program shifted from measure-level TRC testing to program-level screening in 2011, allowing strategic measures with TRC ratios below one. ENS now seeks UARB approval to replace TRC with PAC as the primary cost-effectiveness test for future DSM plans, citing the 2012 plan and Dunsky analysis.
5.2 Rate and Bill As part of the 2016-2018 DSM Resource Plan, ENS is filing a forward-looking Rate and Bill analysis. This is in accordance with requests from Synapse Energy Economics. This is the first time ENS has filed a forward-looking...
AI summary ENS is filing a forward-looking Rate and Bill Impact Analysis as part of the 2016-2018 DSM Resource Plan, the first without historical data. Stakeholder feedback from meetings and submissions was incorporated, with the analysis detailed in Appendix D.
5.3 Cost Allocation Method The new legislative structure, under which NS Power is required to purchase cost- effective, reasonably available DSM, NS Power is able to recover UARB-approved DSM investments from ratepayers. For this reason, i...
AI summary NS Power must recover DSM costs from ratepayers under UARB approval. ENS and NS Power agree on NS Power's responsibility for cost allocation, but ENS awaits NS Power's proposal. ENSC monitors rate class expenditures to inform UARB and stakeholders, with 2014 data referenced in Figure 5.1.
ENSC did not require the level of investment forecast in each rate class except for the Municipal and Large Industrial rate classes. In the Q1 Demand Side Management Report submitted to the UARB on May 14, 2014, ENSC anticipated overspendi...
AI summary ENSC did not require the level of investment forecast in each rate class except for the Municipal and Large Industrial rate classes. In the Q1 Demand Side Management Report submitted to the UARB on May 14, 2014, ENSC anticipated overspending in the Municipal rate class and brought this to the attention of the class's DSM representative. During 2014 ENSC managed participation, to the extent possible, in the Municipal rate class to limit additional expenditures where possible. Approximately 38 percent of the investment in the Large Industrial rate class occurred in the last month of the year.
ming from. If customers in a particular rate class are willing to participate in ENS's programs, ENS should be able to allow those willing customers to contribute to its achievement of energy savings. If an individual rate class is close t...
AI summary The text discusses challenges faced by Efficiency Nova Scotia (ENS) in managing program participation across different rate classes. It highlights the difficulty in limiting participation in certain programs when forecasted investment is exceeded, particularly for programs like Efficient Product Rebates (BNI) and Green Heat. It also notes internal reporting delays and the challenges of meeting energy-savings targets at year-end.
2 As described above, ENS will be pleased to provide input into NS Power's proposed cost 3 allocation methodology once available. Mitigation Strategy Potential Impact and/or Uncertainty Cancelling programs once the full • ENSC's ability to...
AI summary The text discusses the potential impact of cancelling demand-side management (DSM) programs once the full investment amount has been reached. Concerns include ENSC's ability to meet 2014 targets and confusion among customers, delivery agents, and consultants familiar with current program terms.
6. CONCLUSION The 2016-2018 DSM Resource Plan provides an evidence-based approach that enables Nova Scotians to achieve reasonably-available, cost-effective electricity energy and demand savings. The plan was developed with emphasis on aff...
AI summary The 2016-2018 DSM Resource Plan aims to achieve cost-effective electricity savings in Nova Scotia through affordability-focused strategies. ENS seeks UARB approval for the plan, supply agreements, performance metrics, a shift from TRC to PAC cost-effectiveness testing, and a reserve fund establishment.
Appendix A 2016-2018 DSM Resource Plan
AI summary Appendix A outlines the 2016-2018 Demand Side Management (DSM) Resource Plan, a component of Nova Scotia Power Inc.'s (NSPI) Integrated Resource Plan (IRP). The plan focuses on energy efficiency initiatives and programs managed by Efficiency Nova Scotia (ENS).
1. INTRODUCTION The 2016-2018 DSM Resource Plan has been developed based on ENS's growing experience and history in delivering successful DSM programs and services to Nova Scotians. As part of the process, ENS engaged Navigant Consulting a...
AI summary The 2016-2018 DSM Resource Plan by Efficiency Nova Scotia (ENS) outlines energy efficiency programs, emphasizing flexibility for mid-course adjustments based on market conditions and evaluations. It balances affordability, avoids electrical system capacity additions, and includes residential, business, and enabling strategy programs. The Plan is for planning and cost-effectiveness testing, not direct implementation.
Currency is expressed in 2016 dollars. Columns may not add correctly, due to rounding. Annual avoided costs, calculated using ENSC's DSM Potential Study at the Base Level, were provided by NS Power. They include the cost of energy and capa...
AI summary The text discusses annual avoided costs calculated using ENSC's DSM Potential Study, including energy and capacity costs. It also introduces TRC and PAC as benefit/cost ratios comparing lifetime benefits to program costs. Figures 1.2, 1.3, and 1.4 provide investment and savings data for 2016, 2017, and 2018, respectively.
Figure 1.2 - 2016 DSM Resource Plan Investment and Savings 2016 Investment ($ million) Lifetime Benefits ($ million) a Incremental Annual Net Energy Savings at Generator (GWh) Incremental Annual Net Demand Savings at Generator (MW) Total R...
AI summary Figure 1.2 presents the 2016 DSM Resource Plan Investment and Savings, detailing the investment amounts, lifetime benefits, and energy and demand savings for various residential and business programs. It includes data on program administrator costs and total resource costs.
Annual avoided costs, calculated using ENSC's DSM Potential Study at the Base Level, were provided by NS Power. They include the cost of energy and capacity. & lt;sup>a Lifetime benefits are expressed as the net present value of the avoide...
AI summary The text discusses annual avoided costs calculated by NS Power using ENSC's DSM Potential Study, including energy and capacity costs. It also defines lifetime benefits as the net present value of these avoided costs and introduces TRC and PAC as benefit/cost ratios used to evaluate program measures.
& lt;sup>d Reflects ENS's planned participation by low income customers, per the 2015 DSM Resource Settlement Agreement. Figure 1.3 - 2017 DSM Resource Plan Investment and Savings 2017 Investment (S Lifetime Benefits ($ million) a Incremen...
AI summary The 2017 DSM Resource Plan outlines investments and savings for residential and non-residential programs, including efficient product rebates, custom incentives, and education initiatives, with a focus on low-income participation and overall energy savings metrics.
Annual avoided costs, calculated using ENSC's DSM Potential Study at the Base Level, were provided by NS Power. They include the cost of energy and capacity. DATE FILED: February 27, 2015 & lt;sup>a Lifetime benefits are expressed as the n...
AI summary The text discusses annual avoided costs calculated by NS Power using ENSC's DSM Potential Study, including energy and capacity costs. It also references lifetime benefits, TRC, PAC, and ENS's planned participation by low-income customers as outlined in the 2015 DSM Resource Settlement Agreement.
Figure 1.4 - 2018 DSM Resource Plan Savings and Investment 2018 Investment (S million) Lifetime Benefits ($ million) a Incremental Annual Net Energy Savings at Generator (GWh) Incremental Annual Net Demand Savings at Generator (MW) Total R...
AI summary Figure 1.4 presents the 2018 DSM Resource Plan Savings and Investment, detailing the investment amounts, lifetime benefits, energy and demand savings, and cost tests for various residential and non-residential DSM programs in Nova Scotia.
2. RESIDENTIAL PROGRAMS AND SERVICES Efficiency Nova Scotia's Residential sector offerings include a variety of initiatives to help homeowners, renters and landlords become more efficient in their use of electricity. Educating potential pa...
AI summary Efficiency Nova Scotia (ENS) offers residential energy efficiency programs, including rebates, education, and home assessments. Programs are categorized into Efficient Product Rebates, Existing Residential, and New Residential. ENS aims to maximize energy savings through multiple participant actions and will adapt services based on market and client needs.
2.4 Update on Energy Saving Actions Efficiency Nova Scotia's 2016-2018 DSM Resource Plan does not include a target or investment for Energy Saving Actions. ENS piloted the Home Energy Report in 2013, and it will continue until early 2016....
AI summary Efficiency Nova Scotia (ENS) discontinued the Home Energy Report pilot due to affordability concerns, opting for a lower DSM Plan level. ENS will continue exploring behavior-based energy efficiency incentives and conduct R&D through Enabling Strategies. Future DSM plans may revisit the Home Energy Report if higher energy savings are required.
3.2 Custom Incentives The Custom Incentives program provides financial incentives to help commercial, industrial, not-for-profit and institutional customers reduce their electrical energy consumption and peak demand. Incentives are provide...
AI summary The Custom Incentives program offers financial support to commercial, industrial, and institutional customers in Nova Scotia to reduce energy consumption and peak demand through energy audits, technical upgrades, and tailored measures. It accommodates diverse project phases and supports engineering studies, energy-efficient retrofits, and cogeneration projects outside the COMFIT program.
3.3 Direct Installation The Direct Installation program is designed to assist small to medium-sized businesses reduce their energy consumption with turnkey solutions identified through a no-charge assessment. Direct Installation is deliver...
AI summary The Direct Installation program, managed by Efficiency Nova Scotia (ENS), helps small to medium businesses reduce energy use via turnkey solutions. Delivery agents handle procurement and installation, with shared costs and interest-free financing. Target customers include retail shops, restaurants, and non-profits. From 2016-2018, ENS plans to expand contractor participation and product offerings to meet evolving market needs.
4. ENABLING STRATEGIES Enabling Strategies are essential to ensure that ENS is able to increase awareness about energy efficiency, evolve services, and provide information and tools needed by Nova Scotians to make informed energy choices....
AI summary Enabling Strategies are critical for ENS to enhance energy efficiency awareness, evolve services, and drive participation. Key objectives include education, innovation, and market transformation. Examples include PACE financing support, research for incentive optimization, and initiatives like the LED Holiday Light Exchange. ENS advocates for increased funding to achieve long-term DSM goals despite short-term affordability challenges.
4.1 Education and Outreach The complexity of the electricity system means that many concepts and terms are not familiar or accessible to most Nova Scotians. The concept of energy efficiency is equally challenging to communicate effectively...
AI summary Education and outreach are critical for promoting energy efficiency in Nova Scotia, as complex concepts require clear communication to engage residents. Efficiency Nova Scotia (ENS) has increased public awareness, but challenges remain in communicating intangible benefits and adapting to new technologies. The Electricity Efficiency and Conservation Restructuring (2014) Act underscores energy efficiency's role in the electricity supply, emphasizing the need for ongoing outreach efforts.
• Educating customers on ways to conserve energy, reduce peak demand, achieve cost-effective energy savings and lower their electric utility bills; 1 • Increasing public awareness of the value of participating in DSM 2 programs; 3 • Enabli...
AI summary The text outlines a strategy focused on educating customers on energy conservation, reducing peak demand, and achieving cost-effective energy savings. It emphasizes increasing public awareness of demand-side management (DSM) programs, promoting energy efficiency as a social norm, and engaging Nova Scotians through various outreach methods such as social media, electronic newsletters, and educational initiatives like the Green Schools program.
4.2 Development and Research - Efficiency Nova Scotia uses evidence-based decision-making to improve program design and delivery and to guide business strategy. This approach ensures ENS is making the best possible decisions for evolving b...
AI summary Efficiency Nova Scotia (ENS) employs evidence-based decision-making to enhance program design and business strategy. ENS will invest in two areas: research and development for Demand Side Management (DSM) Resource Plans and programs, and activities to improve service delivery to Nova Scotians, ensuring alignment with evolving business needs and reducing risks.
4.2.1 Primary and Secondary Research - Innovation is critical to ensure ENS programs reflect current technologies and consumer behaviour patterns. As such, an important focus of research will be to explore new opportunities for DSM program...
AI summary Efficiency Nova Scotia (ENS) emphasizes innovation in Demand Side Management (DSM) programs through primary and secondary research, focusing on new technologies, consumer behavior, and barriers to participation. Initiatives include developing the 2019-2021 DSM Resource Plan, exploring demand-response measures, piloting programs, and testing marketing strategies to enhance DSM effectiveness.
4.2.2 Development of DSM Information Management and Program Execution Systems - Changes to enhance the customer experience through Programs 2.0 will require an information management system that can easily track and provide insight into al...
AI summary The development of DSM Information Management and Program Execution Systems aims to enhance customer experience, streamline reporting, and improve data tracking for ENS. The system will reduce processing time, minimize external consulting, and boost program uptake via database marketing, with investments continuing through 2016-2018.
4.3.4 Regulatory Affairs As approved in the 2015 DSM Resource Plan, Regulatory Affairs initiatives outside of specific research conducted for DSM Resource Plans or Potential Studies are categorized as Enabling Strategies. As with other Ena...
AI summary Regulatory Affairs initiatives, categorized as Enabling Strategies, are essential for future energy savings. These include UARB costs, DSM Advisory Group activities, stakeholder consultations, and legal work. Approvals for these activities are necessary to achieve ongoing and future energy savings.
2. Contracted Deliverables ENS is proposing a three-year contracted deliverable of cumulative energy and peak demand savings. A three-year deliverable is consistent with previous multi-year DSM Plans, other jurisdictions and the Public Uti...
AI summary ENS proposes a three-year contracted deliverable for cumulative energy and peak demand savings, aligning with previous multi-year DSM plans, other jurisdictions, and the Public Utilities Act.
Multi-Year Plans A Dunsky report, Regulatory Oversight – A Balanced Approach for Efficiency Nova Scotia, January 24, 2012, included in ENSC's 2013-2015 DSM Plan Application as Appendix B, points out that ENS operates in an extremely comple...
AI summary The Dunsky report (2012) highlights ENS's challenges in a competitive market, emphasizing the discretionary nature of energy efficiency and the need for flexibility. The 2016-2018 DSM Plan aims to ensure program accessibility through a balanced portfolio, adapting to market conditions and stakeholder needs.
Other Jurisdictions ENS retained Dunsky Energy Consulting to provide advice on a set of performance requirements that ENS should propose for the UARB's consideration in this Application. The Dunsky report, DSM Performance Indicators, is at...
AI summary Efficiency Nova Scotia (ENS) retained Dunsky Energy Consulting to advise on performance requirements for the Nova Scotia Utility and Ratepayer Board (UARB). The Dunsky report, 'DSM Performance Indicators' (Appendix G), recommends ENS propose UARB-approved performance targets including cumulative annual energy and peak demand savings over three years at the portfolio level.
3. Contract Price In the Supply Agreement, Section 4.2 states the Contract Price shall constitute full compensation for the Electricity Efficiency and Conservation Activities, and no additional compensation shall be payable to, arising out...
AI summary The Contract Price in the Supply Agreement covers full compensation for Electricity Efficiency and Conservation Activities without additional payments for losses or costs. ENS accepts cost risk and proposes a three-year term for deliverables. Surplus funds may be split between a reserve fund and NS Power. Flexibility in adjusting strategies is emphasized.
Update on Implementation of 2013 Verification and Evaluation Recommendations B C E F G K 1 As Shared with DSM Advisory Group November 2015 Updated February 2015
AI summary This document provides an update on the implementation of 2013 verification and evaluation recommendations, shared with the DSM Advisory Group in November 2015 and updated in February 2015.
1. EXECUTIVE SUMMARY The rate and bill impact analysis completed by Efficiency Nova Scotia (ENS) provides an overall trend-based picture of the rate and bill impacts of DSM at a rate-class level to help inform stakeholders and the UARB of...
AI summary Efficiency Nova Scotia (ENS) conducted a rate and bill impact analysis for its 2016-2018 DSM Resource Plan, showing rate increases but overall bill savings across all rate classes. While residential rates rose 3.5%, average bills decreased by 4% due to DSM measures, highlighting affordability considerations for stakeholders and the UARB.
2. INTRODUCTION Efficiency Nova Scotia's rate and bill impact analysis is intended to be a high-level estimate of the impacts of demand-side management (DSM) activities on rate classes' rates and bills. The analysis model, initially filed...
AI summary Efficiency Nova Scotia's rate impact analysis model for demand-side management (DSM) provides high-level estimates of rate and bill impacts, developed by ENS and Elenchus Research Associates with Synapse Energy Economics' framework. The model was reviewed by Synapse and the DSM Advisory Group, with revisions made based on their feedback. Results are not literal but illustrate DSM options' impacts.
Rates versus Bills (Affordability) ENS has taken an in-depth and focused view of affordability in its 2016-2018 DSM Resource Plan Application. This analysis provides information on which to analyze the impacts of DSM, providing additional...
AI summary ENS's 2016-2018 DSM Resource Plan analysis shows that while short-term rates increase with 100% expensing, long-term rates decrease due to avoided capacity costs. Residential customers see bill reductions despite higher rates, but model discrepancies from removing the Home Energy Report affect savings estimates. ENS plans to address these issues in future models.
Rate and Bill Impact Trends With NS Power's release of non-confidential annual avoided costs, annual, rather than levelized, avoided costs have been used in the 2016-2018 analysis. This change in inputs has affected the presentation of res...
AI summary NS Power's shift from levelized to annual avoided costs in 2016-2018 analysis altered rate impact timing, showing greater near-term increases and long-term decreases while maintaining overall DSM benefits. This methodological change affects presentation but not total benefits over the DSM timeframe.
Incorporation of Point-of-Sale Discount Programs ENS provided the following explanation in its 2014 rate and bill impact analysis report. However, stakeholders may have similar questions regarding participation rates, so the explanation of...
AI summary ENS explains its upstream point-of-sale discount programs (e.g., Instant Savings) and their impact on participation rates, noting alignment with Oregon's Energy Trust practices. Saturation in some rate classes does not preclude future DSM participation, as programs may adjust measures to influence purchases.
Balanced Portfolio Approach ENS's Evidence highlights the importance of a balanced portfolio approach. A balanced approach is also supported in Appendix E, which consists of Dunsky Energy Consulting's Balanced Plan Principles memo. The bil...
AI summary ENS's Evidence emphasizes a balanced portfolio approach, supported by Dunsky Energy Consulting's memo in Appendix E. DSM activities across rate classes provide benefits to Nova Scotians, outweighing rate impacts. The broad DSM program offerings demonstrate value to customers.
Overall Assumptions Differing from previous years, this rate and bill impact analysis is forward-looking and does not present historical results from 2011-2014. There are some instances however, that historical data were utilized; their sp...
AI summary The analysis is forward-looking, using ENS's 2016-2018 DSM Resource Plan and Navigant Consulting's EL-RAM model. It incorporates the 2014 IRP's energy forecasts up to 2040 provided by NS Power, with benefits extending 16 years beyond the plan's timeframe. Historical data is selectively used where relevant.
Rate Impact Assumptions In addition to an illustrative assumption of potential amortization impact on rates and bills, as described in the results section of this report, rate impacts are presented as year- over-year impacts (i.e., how rat...
AI summary The analysis presents rate impacts as year-over-year changes rather than comparing to a no-DSM baseline, following Synapse's recommendation that a no-DSM scenario was not considered during 2016-2018. This approach focuses on incremental changes rather than absolute comparisons.
Alternative DSM Scenarios Alternative Scenarios explore the effect of varying levels of DSM investment. DSM Potential Study data ($M and GWh) for the Low, Base, and Mid-DSM Scenarios over 2016-2018 were used to inform the model with respec...
AI summary The analysis evaluates alternative DSM investment scenarios (Low, Base, Mid, and NS Power's 50% Low IRP) to assess energy savings impacts. ENS's proposed Plan is compared against these scenarios, with the Base scenario omitted due to similarity. NS Power's 50% Low Scenario, not vetted by ENS, uses conservative avoided costs. The model assumes 75% of energy savings changes stem from participant numbers, with 25% from adoption depth, capped at 100% participation.
Output Potential Summary sheets for rate, bill, participation and alternative DSM scenario impacts for each applicable rate class are included in Attachment 3. Inclusions on the summary sheet have been selected based on representative outp...
AI summary Attachment 3 contains summary sheets analyzing rate, bill, participation, and alternative DSM scenario impacts for each applicable rate class. The inclusions are based on representative model outputs from the analysis.
6. ENS'S USE OF THE RESULTS - There are several ways in which ENS expects to use the results of this analysis: - ENS expects the analysis to help to inform ongoing discussions with NS Power and stakeholders in regards to the 2016-2018 DSM...
AI summary ENS plans to use analysis results for discussions with NS Power and stakeholders on the 2016-2018 DSM Resource Plan. It will focus recruitment efforts in specific rate classes while maintaining support for high-participation classes. ENS seeks input on integrating rate/bill impact analysis into other studies.
8. CONCLUSION ENS's rate and bill impact analysis provides an overview of general trends in relation to a specific snapshot in time of DSM in Nova Scotia. It captures the rate, bill and participation impact trends of particular DSM scenari...
AI summary ENS's rate and bill impact analysis outlines general trends in DSM impacts for Nova Scotia, providing a trend-based view rather than exact yearly values. This informs discussions for the 2016-2018 DSM Resource Plan by highlighting overall rate class impacts.
Assumptions used in ENS's 2016-2018 Rate and Bill Impact Analysis Stakeholder Stakeholder Comment ENSC's Response Inclusion in the model Consumer Advocate The data did attempt to model changes in savings resulting from changes in investmen...
AI summary The Consumer Advocate challenges ENSC's assumption that a 50% reduction in DSM spending would result in a 50% reduction in savings, as this was not modeled. ENSC acknowledges that the 50% Low Case from the IRP was not tested and agrees that the assumption is not supported by modeling. However, ENSC included the scenario for comparison purposes in the rate and bill impact analysis.
These assumptions are for rate and bill impact analysis purposes only and do not impact ENS's calculation of energy savings. Category Item Assumption Overall Assumption General approach ENS has used the "snapshot" approach recommended by S...
AI summary The analysis uses a 'snapshot' approach to assess the impacts of specific DSM plans over three years (2016-2018) and the benefits of energy savings from measures installed during that period. This method isolates the impacts of proposed or approved DSM Plans and does not incorporate long-term assessments of DSM.
Appendix D, Attachment 3 Line# Rate and Bill Impacts of DSM on the Small General Class 1 Impacts of DSM on the Small General Rate Class 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Units 2 Incremental DSM Savi...
AI summary This table outlines the rate and bill impacts of Demand Side Management (DSM) on the Small General Class from 2016 to 2030. It includes incremental and cumulative DSM savings, costs, and average savings per participant, highlighting a decline in savings and costs after 2018.
Appendix D, Attachment 3 Rate and d Bill Impa acts of DS M on the General C lass Impacts of DSM on the General Rate Class 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Units Incremental DSM Savings 33.1 32.4 31...
AI summary This table outlines the impacts of Demand Side Management (DSM) on the General Rate Class from 2016 to 2030, including incremental and cumulative DSM savings, DSM costs, number of participants, and cost per kWh saved. The data shows a decline in DSM savings after 2018 and a steady increase in cost efficiency over time.
Line# Rate and Bill Impacts of DSM on the Medium Industrial Class 1 Impacts of DSM on the Medium Industrial Rate Class 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Units 2 Incremental DSM Savings 3.4 3.4 3.3 0...
AI summary The table presents the rate and bill impacts of Demand Side Management (DSM) on the Medium Industrial Class from 2016 to 2030. It includes incremental and cumulative DSM savings, DSM costs, and cost per kWh saved, showing a decline in savings and costs after 2018.
Investing in Demand-side Resources: Considering Affordability
AI summary The document examines the integration of demand-side resources in Nova Scotia's energy strategy, emphasizing affordability. It discusses balancing cost-effective energy efficiency programs with consumer affordability, involving entities like Efficiency Nova Scotia (ENS) and Nova Scotia Power Inc. (NSPI), while considering regulatory frameworks and stakeholder input.
1.1 Report Purpose This report contextualizes the proposed level of investment in demand-side resources for 2016 to 2018 in Efficiency Nova Scotia's (ENS) three-year Demand-Side Resource Plan. We consider levels of demandside resource inve...
AI summary This report evaluates the proposed investment in demand-side resources for 2016–2018 under Efficiency Nova Scotia's (ENS) three-year plan, assessing their value to Nova Scotians and compliance with the Public Utilities Act .
1.2 Summary of Findings - 1. Since 2011, excluding 2015, Nova Scotia has invested in demand-side resources at or above the level (in real terms) proposed by ENS in the 2016-2018 Demand-Side Resource Plan. - 2. Demand-side resource investme...
AI summary Nova Scotia's demand-side resource investments since 2011 (excluding 2015) meet or exceed ENS's 2016-2018 plan. These investments yield over $200M in net benefits, enhance affordability, and reduce Nova Scotia Power's revenue requirements. DSM is highlighted as cost-effective, with the Province's plan emphasizing its role in improving electricity affordability and economic competitiveness.
2. Benefits of Demand-Side Resource Investments in Nova Scotia
AI summary The section discusses the benefits of demand-side resource investments in Nova Scotia but lacks specific details due to the absence of substantive text beyond the heading.
2.1 Investments in Demand-side Resources Demand-side management (DSM) is recognized as a highly cost-effective electricity supply resource.[10](#page-193-3) For Nova Scotians, DSM has reduced customer electricity costs, provided substantia...
AI summary Demand-side management (DSM) is highlighted as a cost-effective electricity resource, reducing customer costs and providing economic and system benefits since 2008. ENS's proposed investments are projected to yield over $200 million in ratepayer benefits. Jurisdictions in Canada and the U.S. recognize DSM's value, with some requiring utilities to procure all cost-effective demand-side resources.
2.2 Demand-Side Management is an Investment, Not a Cost Since 2008, demand-side resource investments have provided significant benefits to Nova Scotian households and businesses. On behalf of Efficiency Nova Scotia, Navigant's Electricity...
AI summary Since 2008, demand-side management (DSM) investments in Nova Scotia have delivered benefits to households and businesses. Efficiency Nova Scotia, using Navigant's EL-RAM model, assessed cost-effectiveness. The 2016-2018 plan optimized DSM investment for cost-effectiveness and broad participation, with program participants benefiting from lower bills and improved affordability.
2.3 Relative Size of Demand-side Resource Investments in Nova Scotia [Figure 1](#page-194-1) includes the investment level proposed by ENS over the 2016-2018 period and approved for 2015, and presents a comparison of both historical demand...
AI summary This section discusses the relative size of demand-side resource investments in Nova Scotia, comparing proposed and approved investment levels over specific periods and showing their proportion of residential revenue requirements. The data indicates that demand-side investments account for 2.4% of average household electricity costs, with a gross monthly cost share of less than $3.45.
Figure 1. Residential Sector Demand-side Investment vs. All Other Sector Electricity Spending – 2011 to 2018 Year Residential Revenue Requirement (includes Customer Charge) ($ million) [ a ] Demand-side Plan Residential Investment with 50%...
AI summary Figure 1 compares residential sector demand-side investment with all other sector electricity spending from 2011 to 2018. It shows that demand-side investment constitutes a small percentage of residential revenue requirement, with the average cost share per customer remaining relatively stable over time.
2.3.1 Relative Size of Household Demand-side Resource Investments as Compared with Total Energy Costs When compared with total stationary household energy expenditures (excluding transportation), demand-side resource investments are a very...
AI summary Demand-side resource investments constitute a minor portion of Nova Scotia households' energy expenditures. Reducing these investments, as proposed by ENS, would minimally affect short-term affordability but could compromise mid- and long-term affordability.
2.4 Macroeconomic Benefits The current investment level proposed by ENS is estimated to yield more than $200 million in net total resource benefit to ratepayers over the period of 2016 to 2018.[18](#page-196-3) In addition to these benefit...
AI summary ENS's proposed investment is projected to generate over $200 million in net total resource benefits for Nova Scotia ratepayers (2016-2018). Energy efficiency benefits extend beyond traditional DSM cost-effectiveness tests. The analysis uses Navigant's EL-RAM model, with a note that NSUARB M06475 suggests potential underestimation of benefits if NSPI ratepayers have lower capital costs than the utility.
2.4.2 Economic Benefit of Demand-side Resource Investments for Nova Scotians Total economic impact analysis examines the direct, indirect, and induced impacts of a particular activity. The energy efficiency sector provides benefits to the...
AI summary The analysis highlights that demand-side resource investments in Nova Scotia generate economic benefits across direct, indirect, and induced impacts. The energy efficiency sector contributes to the provincial economy through these three categories, emphasizing broader economic advantages.
2.4.3 Electricity System Benefits Investments in demand-side resources also yield system benefits that support long and short-run cost savings and are included in benefit/cost calculations. - Reducing and delaying energy supply requirement...
AI summary Demand-side investments reduce energy supply needs, lower line losses, and decrease capacity reserves, enhancing long-term affordability. These benefits include delaying infrastructure costs, reducing transmission congestion, and improving efficiency during peak and off-peak periods. Generation and capacity savings are amplified by demand reduction multipliers during peak times.
2.5 Further Benefits of Demand-side Resource Investments
AI summary This section discusses additional benefits of demand-side resource investments, emphasizing efficiency programs and regulatory considerations in Nova Scotia. Key entities include Nova Scotia Power Inc. (NSPI), Efficiency Nova Scotia (ENS), and the Nova Scotia Utility and Review Board (UARB), with a focus on cost savings, environmental impact, and program administration.
2.5.1 Overview Demand-side resource investments provide additional benefits above and beyond the direct system benefits available to all customers and the electricity bill savings that accrue to Nova Scotian households and businesses that...
AI summary Demand-side investments provide non-energy benefits (NEBs) to participants, utilities, and society, enhancing affordability despite low costs. These benefits, beyond direct savings, are highlighted in Lazar and Colburn's 2013 report on energy efficiency's full value.
2.5.2 Emissions Reductions Notwithstanding existing emissions caps and the expectation that the generation portfolio in Nova Scotia will be less reliant on coal and fossil fuels in the future, in 2014, Nova Scotia Power generated 61 percen...
AI summary In 2014, Nova Scotia Power generated 61% of its electricity from coal and 75% from fossil fuels, contributing to public health risks and greenhouse gas emissions. Demand-side resources can reduce these emissions, benefiting health and society.
2.5.3 Participant Non-energy Benefits In addition to electricity energy savings that produce bill reductions, demand-side program participants may experience non-energy benefits, such as improved comfort, increased property values, improve...
AI summary Demand-side program participants in Nova Scotia may experience non-energy benefits such as improved comfort, increased property values, and enhanced productivity, in addition to energy savings and bill reductions. These indirect benefits are recognized alongside direct energy efficiency outcomes.
2.5.4 Utility Non-energy Benefits In addition to avoided energy and capacity costs, demand-side resources often are considered a lower risk option compared with many supply-side alternatives. By contrast with major supply infrastructure, d...
AI summary Demand-side resources are highlighted as lower-risk investments compared to supply-side alternatives due to their dispersed nature and reliability. They reduce fuel supply needs for fossil generators, mitigating market price volatility. These benefits are not typically addressed in traditional cost-effectiveness analyses of demand-side resources.
2.5.6 Summary of Non-energy Benefits Issues Increasingly, non-energy benefits – especially those that accrue to participants – are viewed as significant benefit streams that the current demand-side resource benefit-cost analysis effectivel...
AI summary Non-energy benefits, particularly those to participants, are overlooked in the current demand-side resource benefit-cost analysis. This neglect is critical as the analysis should reflect total benefits and costs to both participants and non-participants, justifying affordable investments with net financial benefits for ratepayers.
2.6 Affordability of Demand-side Resource Investments in Nova Scotia Utility resource planning efforts face a long-term responsibility to deliver reliable service at least cost for ratepayers. In the context of this guiding principle, the...
AI summary The text argues that under-investing in demand-side resources (DSM) in Nova Scotia could lead to higher long-term costs and reduced benefits for ratepayers. While ENS reduced short-term DSM investments compared to Nova Scotia Power's Preferred Resource Plan, the analysis suggests that long-term benefits are still significant. Alternative rate mitigation strategies, like rate smoothing, are recommended over reducing DSM investments.
MEMO To: EFFICIENCY NOVA SCOTIA From: Philippe Dunsky Date: February 26th, 2015 Re.: DSM Portfolio Design DSM Portfolio Principles and Principles Considerations Considerations
AI summary Memo from Philippe Dunsky to Efficiency Nova Scotia discussing DSM portfolio design principles and considerations for a regulatory proceeding in Nova Scotia.
Approach Few regions have adopted a formal and publically available set of principles to guide their DSM plans. This is partly the result of the complexity of DSM itself which, for reasons we will explain below, does not lend itself well t...
AI summary The document outlines the complexity of Demand Side Management (DSM) and identifies four guiding principles for DSM plans: maximizing energy savings, optimizing net benefits, minimizing risk, and ensuring equitable access. It emphasizes balancing these goals with trade-offs and the need for diverse portfolios and sustained market presence.
Consideration #1: MAXIMIZE SAVINGS SAVINGS A DSM Program Administrator exists first and foremost to produce DSM savings. Yet even this goal is not entirely straightforward, as it involves a tension between two related goals: short-term sav...
AI summary The text discusses the balance between short-term and long-term savings in DSM programs, emphasizing that short-term initiatives (like immediate energy-saving measures) are essential for building market familiarity and enabling long-term efficiency gains through education, training, and market transformation.
IMPLICATION: In building its three IMPLICATION MPLICATION: In its : three-year DSM plan, we encourage ENS to seek a balance year encourage ENS to seek a between short short-and long and longand long-term savings goals. term goals. To this...
AI summary The text advises ENS to balance short-term and long-term savings goals in its three-year DSM plan by investing in high-risk, long-term market transformation efforts, valuing full measure lifespans, and considering long-term impacts of short-term initiatives. It warns against focusing solely on quantifiable savings, which may neglect cost and variable benefits.
Consideration #2: MAXIMIZE NET BENEFITS ET NBENEFITS One of the key drivers for DSM is its cost-effectiveness – the extent to which benefits exceed costs – when compared against supply-side energy resources. As such, most DSM PAs focus sig...
AI summary The document emphasizes that Demand Side Management (DSM) should prioritize maximizing net benefits over minimizing costs alone. It argues that energy savings from different measures (e.g., efficient heating vs. fridges) vary in value due to usage patterns and longevity. For example, savings from building envelopes outlast those from T8 lamps, affecting NSPI's avoided costs.
Consideration #3: MINIMIZE RISK As with any business designed for the long haul, minimizing risk is an important consideration. For DSM, we note at least two ways in which risk ought to be considered: (a) portfolio diversification, and (b)...
AI summary The text emphasizes minimizing risk in Demand Side Management (DSM) through portfolio diversification and market presence. Diversification adds value not captured by cost-benefit estimates, achievable via multiple methods, though the text is cut off mid-example.
Consideration #4: MAXIMIZE EQUITY ( QUITY E(SOCIAL LICENSE SOCIAL LICENSE LICENSE) Businesses must generally obtain a "social license" – general acceptance of, and support from, the communities in which they operate. In the case of DSM, to...
AI summary Maximizing equity in DSM programs requires ensuring broad access, particularly for low-income customers, multifamily buildings, and small businesses facing barriers like split incentives. Special programs and higher Program Administrator costs may be needed, though this can reduce net benefits. Equity-focused design should balance access with rate impacts.
SUMMARY SUMMARY& CONCLUSION & CONCLUSION The business of "selling" Demand-Side Management is not fundamentally different from most business ventures: when taking a long-term perspective, strategic planning involves balancing multiple objec...
AI summary Efficiency Nova Scotia (ENS) must balance multiple objectives in its Demand-Side Management (DSM) strategy, including maximizing short-term and long-term savings, minimizing costs, ensuring value, managing risks, preserving relationships, and ensuring broad access. A balanced approach is emphasized to achieve long-term success in DSM portfolio development.
DSM PERFORMANCE INDICATORS
AI summary The document outlines performance indicators for Demand Side Management (DSM) programs, likely related to regulatory proceedings in Nova Scotia. It may involve entities like Nova Scotia Power Inc. (NSPI) and Efficiency Nova Scotia (ENS), with focus on energy efficiency, program evaluation, and compliance with regulatory standards.
JURISDICTIONAL REVIEW & RECOMMENDATIONS FOR EFFICIENCY NOVA SCOTIA PREPARED BY
AI summary This document outlines a jurisdictional review and efficiency recommendations for Efficiency Nova Scotia (ENS), focusing on regulatory oversight and program effectiveness. Key entities include Nova Scotia Power Inc. (NSPI) and the Nova Scotia Utility and Ratepayer Board (NSUARB). The review addresses DSM programs, HST implications, and TRC methodologies.
link to specific targets – on a set of additional indicators of success. Specifically: RECOMMENDATION #1: ENS adopt two Target Performance Indicators applied to the 2016-2018 Plan, namely: • Cumulative annual energy savings; and • Cumulati...
AI summary The recommendations focus on enhancing ENS's performance indicators by introducing cumulative annual energy and peak demand savings, developing a methodology for lifetime energy savings, and considering additional indicators such as total ratepayer benefits and customer satisfaction for annual reporting.
The table below summarizes our recommendations: Performance Indicator Target (TPI) Other (OPI) Note on metrics Cumulative Annual Electricity Savings GWh/yr (last year of plan) Cumulative Annual Peak Demand Savings MW (last year of plan) Cu...
AI summary The table outlines performance indicators and targets for energy efficiency programs, including cumulative electricity and peak demand savings, as well as considerations for value and other factors. The focus is on transitioning certain metrics from optional performance indicators to target performance indicators in the next three-year plan.
2. TARGET PERFORMANCE INDICATORS
AI summary Section 2 outlines Target Performance Indicators (TPIs) for Nova Scotia's energy efficiency and demand-side management programs. It references regulatory bodies like the NSUARB, organizations such as NSPI and ENS, and programs including DSM and BER. Key themes involve performance metrics, program administration, and compliance with energy efficiency standards.
3.1. CHOICE OF CASE STUDIES For purposes of this study, we conducted a scan of target performance indicators used in ten jurisdictions across the U.S. and Canada. The selected regions were chosen using the following criteria: - Third-Party...
AI summary The study selected ten jurisdictions in the U.S. and Canada for case studies, focusing on regions with third-party DSM administrators and recognized DSM leaders. The criteria included regions using third-party PAs and those with performance incentive mechanisms, such as California and Ontario.
VERMONT Efficiency Vermont, the program administrator currently operated by Vermont Energy Investment Corporation (VEIC), is eligible to receive a performance incentive of up to $3.9M over the current 3-year Plan period. This represents ap...
AI summary Efficiency Vermont, administered by VEIC, can earn a performance incentive of up to $3.9M over three years if it meets 7 performance targets and 8 minimum requirements. Failure to meet minimum requirements may significantly reduce incentives, and annual verification of savings is required.
Table 3: Target performance indicators and Minimum Requirements in Vermont Target performance indicators Metric Unit Electricity savings (Net annual cumulative) MWh Total Resource Benefits (electric, fossil, water) $ NPV Summer Peak Demand...
AI summary Table 3 outlines target performance indicators and minimum requirements in Vermont, including metrics like electricity savings, Total Resource Benefits (TRB), and participation thresholds. TRB is calculated based on avoided cost forecasts and adjusted for changes over time.
DISTRICT OF COLUMBIA Following the same structure as Vermont, the performance of the DC Sustainable Energy Utility (SEU), also operated by VEIC, is evaluated using six performance targets and three minimum requirements (Table 4). An annual...
AI summary The performance of the DC Sustainable Energy Utility (SEU) is evaluated using six performance targets and three minimum requirements, similar to Vermont. An annual incentive of up to $600,000 is available, which is about 4% of the SEU's annual DSM budget, and savings are subject to annual verification.
MASSACHUSETTS In Massachusetts, utilities are responsible for delivering energy efficiency, and can earn performance incentives if they hit performance targets. In aggregate, Massachusetts's utilities can receive performance incentives of...
AI summary In Massachusetts, utilities are responsible for delivering energy efficiency and can earn performance incentives if they meet targets. The total possible incentives are up to $63M over three years, capped at 5% of the total DSM budget. Performance is measured using three indicators: savings, value, and 'performance', with the latter based on ten metrics focused on market transformation and depth of savings.
Table 6: Target performance indicators in Hawaii Target performance indicators Metric Unit Energy Savings kWh/yr (cumul.ann.) Peak Demand Savings kW (cumul.ann.) Total Resource Benefit (TRB) $ NPV Market Transformation - Behavior Modificat...
AI summary Table 6 outlines target performance indicators in Hawaii, focusing on energy and peak demand savings, Total Resource Benefit (TRB), and market transformation metrics. TRB is defined as the net present value of savings, adjusted retroactively for changes in avoided cost forecasts, similar to practices in Massachusetts and Vermont. Lifetime savings are based on ex-ante estimates of energy measures' useful lives.
OREGON Oregon does not have a performance incentive mechanism in place. Nevertheless, the Oregon Public Utilities Commission (OPUC) has set target performance indicators by which the program administrator, Energy Trust of Oregon, is to be...
AI summary Oregon lacks a performance incentive mechanism, but the Oregon Public Utilities Commission (OPUC) has established target performance indicators (TPIs) for the Energy Trust of Oregon (ETO). Failure to meet these TPIs could result in a review by OPUC and potentially the termination of ETO's contract.
4.2. DISCUSSION & RECOMMENDATIONS Two target performance indicators meet all of the above-noted five criteria, namely: Cumulative annual energy savings, and Cumulative annual peak demand savings. These indicators are clearly within the sco...
AI summary Two Target Performance Indicators (cumulative annual energy and peak demand savings) are recommended for ENS due to their alignment with its mandate, measurability, and controllability. A third indicator (cumulative lifetime energy savings) is noted as important but lacks reporting history in Nova Scotia. The UARB would set specific targets for the first two indicators to assess ENS performance and inform franchise renewal decisions.
DSM SCREENING IN NOVA SCOTIA TOWARD A BALANCED COST-EFFECTIVENESS FRAMEWORK PREPARED BY DUNSKY ENERGY CONSULTING Philippe Dunsky, President François Boulanger, Senior Consultant SUBMITTED TO EFFICIENCY NOVA SCOTIA February 23rd, 2015
AI summary A document prepared by Dunsky Energy Consulting and submitted to Efficiency Nova Scotia on February 23, 2015, discusses DSM screening in Nova Scotia toward a balanced cost-effectiveness framework. The report outlines the need for a structured approach to evaluating demand-side management programs, emphasizing cost-effectiveness and regulatory considerations.
EXECUTIVE SUMMARY The Total Resource Cost (TRC) test was first defined, along with a series of other "standard" tests, in 1983, in the context of California's initial, utility-driven energy efficiency and demand-side management (DSM) progr...
AI summary The Total Resource Cost (TRC) test, introduced in 1983, has been widely used since the 1990s to evaluate demand-side management (DSM) cost-effectiveness. However, recent concerns question its continued use, citing four unresolved issues affecting decision-making in DSM programs.
RECOMMENDATIONS - 1. Nova Scotia adopts the Program Administrator Cost (PAC) as the primary test for purposes of screening DSM cost-effectiveness; - 2. The PAC test be applied for information purposes at the program and portfolio levels, a...
AI summary The recommendations focus on adopting the Program Administrator Cost (PAC) as the primary test for DSM cost-effectiveness, applying it at different levels, re-examining discount rates for consistency, and developing a transparent reporting template based on NESP's framework.
INTRODUCTION TO DSM SCREENING
AI summary An introduction to Demand Side Management (DSM) screening in Nova Scotia, involving key organizations like Efficiency Nova Scotia (ENS) and Nova Scotia Power Inc. (NSPI), with references to regulatory frameworks and energy efficiency programs.
BRIEF HISTORY In the early 1980s, following on the heels of the second energy crisis, California's utilities moved to encourage improved customer energy efficiency. In order to provide a framework for judging the appropriateness of utility...
AI summary In the early 1980s, California's utilities developed standardized tests for DSM spending following the second energy crisis, leading to the creation of the Standard Practice Manual (SPM) by the California Energy Commission and California Public Utilities Commission in 1983. Subsequent revisions have been largely cosmetic.
ration as a type of DSM, and expanding on the nature of externalities that should be included in the Societal Cost Test (California Public Utilities Commission and California Energy Commission, 2001). In addition to the three perspective p...
AI summary The text discusses the Societal Cost Test (SCT) and Program Administrator Cost (PAC) test within cost-effectiveness frameworks. The SCT includes broader societal benefits, particularly environmental factors, while the PAC test compares utility savings from DSM to supply costs. The Standard Practice Manual outlines these tests as guidance for judgment, not strict criteria.
CHOICE OF TESTS: THE RISE OF THE TRC AND MORE RECENT TRENDS Through the vagaries of time and the shifting importance given to DSM, most states and provinces that gave it consideration have, in the end, landed on the use of the TRC test as...
AI summary The document discusses the evolution of cost-effectiveness testing in demand-side management (DSM), noting the initial dominance of the Total Resource Cost (TRC) test due to abundant low-cost opportunities. However, with diminishing low-hanging fruit and the recognition of non-energy benefits (NEBs), there's a growing shift towards alternative tests. Program administrators are reevaluating TRC's limitations, and many DSM leaders now use other methods.
REGULATORY DRIVERS While the current effort at DSM in Nova Scotia is relatively new, the province's consideration of DSM dates back over fifteen years. Indeed, in the mid-1990s, in the context of an Integrated Resource Planning (IRP) proce...
AI summary Nova Scotia's DSM evolution spans 15+ years, with UARB using TRC thresholds (0.8 in 1990s, 1.0 in 2006) for DSM evaluation. The 2014 IRP prioritized cumulative revenue requirements over customer costs, while the 2014 Act linked energy efficiency to NSPI cost reduction via PAC. Synapse's analysis excluded customer costs in revenue assessments.
POLICY DRIVERS Nova Scotia's DSM is arguably driven by imperatives outside of the strict regulatory arena as well. We note that in 2012, an equivalency agreement between the Province and the federal government was reached on climate change...
AI summary Nova Scotia's DSM is influenced by 2012 climate change agreements with the federal government, allowing carbon exemptions for power plants in exchange for sectoral reductions. The 2014 Electricity Efficiency and Conservation Plan formalized ENS's role in competing energy savings with supply options, aligning with PAC cost-effectiveness tests. Nova Scotia's approach reflects broader trends in reevaluating DSM strategies.
ISSUE #1: ACCURACY: IS THE TRC CALCULATED CORRECTLY? The TRC is the most common test currently in use, and compares all direct benefits, expressed through avoided energy and capacity supply costs, to all direct costs, both for the DSM prog...
AI summary The TRC (Total Resource Cost) ratio compares avoided energy and capacity costs to program and participant costs. While the simplified formula is clear, the detailed algorithm in the Standard Practice Manual lacks clarity on key inputs and assumptions. Six components of the TRC calculation may use different methodological approaches, raising concerns about accuracy.
pically focus on the capital savings and reduced staff time associated with much longer equipment lives (i.e. reduced frequency of equipment replacement). Meanwhile, incorporating daylighting into new commercial office buildings is sold fa...
AI summary The text highlights that non-energy benefits (NEBs) are often undervalued by TRC despite their significance in demand-side management (DSM) programs. Literature from Massachusetts shows NEBs can account for up to 70% of total program benefits, emphasizing their impact on benefit-cost ratios. Studies demonstrate NEBs' value in residential and commercial sectors, though TRC currently assigns them zero value.
OTHER NON-ENERGY BENEFITS AND ISSUES Beyond Participant NEBs, DSM may offer additional non-energy benefits that accrue to the utility, and/or to society as a whole.
AI summary The text highlights that Demand Side Management (DSM) may provide additional non-energy benefits beyond Participant Non-Energy Benefits (NEBs), benefiting both the utility and society. These benefits are considered in the regulatory proceeding.
Utility NEBs Other than avoided energy and capacity costs, DSM is often considered a lower risk option than many of its supply-side alternatives. This lower risk is primarily related to four aspects of the DSM profile: - 1. Hedge against f...
AI summary Demand Side Management (DSM) is presented as a lower-risk alternative to supply-side energy options due to its fuel price hedging, reliability, and planning flexibility. DSM mitigates fuel price volatility, avoids construction risks, and offers load-matching reliability. Regions like the U.S. Northwest attribute risk benefits to DSM in cost-effectiveness analyses.
Societal NEBs While we have discussed participant and utility NEBs, DSM is also known to generate non-energy benefits for society as a whole, primarily through (1) environmental benefits (to the extent they are not already internalized in...
AI summary The text discusses societal non-energy benefits (NEBs) from demand-side management (DSM), including environmental and macroeconomic benefits. Environmental benefits include reduced emissions, while macroeconomic benefits involve increased GDP and job creation. It critiques the Total Resource Cost (TRC) method for being biased against energy efficiency and not fully capturing societal benefits. The document notes that in Nova Scotia, carbon emissions are already partially internalized due to legislation.
SUMMARY OF NEB ISSUES Increasingly, non-energy benefits – especially those that accrue to participants – are viewed as significant benefit streams that the current TRC effectively neglects. This is critical to the extent that the TRC's pur...
AI summary The document critiques the Total Resource Cost (TRC) methodology for neglecting non-energy benefits (NEB), particularly for participants. It notes that some regions modify TRC to include NEB or adopt alternative tests. A study evaluated DSM scenarios with 1.0%-2.5% annual savings, referencing Nova Scotia's 2012 DSM achievement of 1.52% annual sales. The text also mentions deliberate low-rate choices to avoid discounting future generations' interests.
IMPLICATIONS FOR NOVA SCOTIA Nova Scotia's current TRC does not account for non-energy benefits, whether they accrue to participants, the utility, or society at large. By failing to account for these benefits, while fully accounting for pa...
AI summary Nova Scotia's current Total Resource Cost (TRC) methodology excludes non-energy benefits (NEB), creating a bias against Demand Side Management (DSM) by fully accounting for participant costs while ignoring societal and utility-level NEB.
ISSUE #4: POLICY: WHAT IF THE TRC IS INCONSISTENT WITH PUBLIC POLICY? Throughout the 1990s, when the TRC first took on prominence as the pre-eminent DSM screen, most program administrators were working against growing but still modest DSM...
AI summary The text discusses the evolution of DSM goals from the 1990s to today, noting increased targets (1.5-3% annual savings) and improved baselines due to factors like consumer awareness and new codes. This combination is increasing costs for DSM administrators, requiring more expensive measures like deep retrofits and solar hot water to meet targets.
RECENT CHANGES TO STANDARD PRACTICES
AI summary The document outlines recent updates to standard practices in Nova Scotia's regulatory proceedings, involving entities like NSPI, ENS, and UARB. Key topics include energy efficiency programs, demand-side management, and regulatory frameworks. No specific arguments or cross-references are detailed in the provided text.
TRENDS IN LEADING REGIONS The concerns noted previously – errors in applying the TRC, unintentional bias in TRC results, conflict with official energy policies, and neglect of bottom-line concerns – are increasingly shared across the energ...
AI summary The report discusses concerns with the Total Resource Cost (TRC) test, including errors, bias, and conflicts with energy policies, leading to its modification or replacement in several regions. Six regions use a Modified Total Resource Cost (MTRC) test, four use the Program Administrator Cost (PAC) test in combination with TRC or the Societal Cost Test (SCT), and one region uses PAC or SCT alone.
Figure 6. Case Studies: Select Regions that Use Alternatives to the Standard TRC STATE PRIMARY TEST COMPONENTS SCREENING (2014 SCORECARD POSITION) TEST Non-Energy Benefits (NEBs) Participant Utility Societal Disc. Rate (Societal) LEVEL Not...
AI summary Figure 6 presents case studies of various regions using alternatives to the Standard Total Resource Cost (TRC) method, including modified TRC (mTRC), Societal Cost Test (SCT), and Program Administrator Cost (PAC). These regions implement different approaches, such as incorporating non-energy benefits (NEBs) and using hybrid delivery models, to evaluate energy efficiency programs.
OPTIONS FOR NOVA SCOTIA
AI summary Nova Scotia's regulatory proceeding discusses energy options involving Demand Side Management (DSM), Harmonized Sales Tax (HST), and Integrated Resource Plan (IRP). Key entities include Nova Scotia Power Inc. (NSPI), Efficiency Nova Scotia (ENS), and the Nova Scotia Utility and Review Board (UARB), with KPMG involved in analysis. The proceeding evaluates programs, legislation, and utility regulations.
Fig. 7. Overview of Concerns & Implications for Nova Scotia OUR CONCERNS NESP & NEEP GUIDELINES CONSIDERATIONS FOR NOVA SCOTIA ACCURACY Key assumptions may not reflect deliberate or appropriate choices. Both guidelines insist on need for t...
AI summary The document discusses concerns with the Total Resource Cost (TRC) methodology, including potential bias, lack of transparency, and misalignment with policy goals. It suggests that Nova Scotia should consider alternative frameworks like the Program Administrator Cost (PAC) test for better alignment with best practices and ratepayer value.
OPTION A. FIX THE TRC (ASSESS NON-ENERGY BENEFITS + OTHER CHANGES) One solution to the above concerns is to directly address each – or as many as possible, within reason – of the missing benefits or other algorithmic concerns, namely: acco...
AI summary Option A proposes addressing missing benefits and algorithmic issues in the Total Resource Cost (TRC) by incorporating non-energy benefits (NEBs) and reevaluating the discount rate for Demand Side Management (DSM) future benefits. This aims to improve the accuracy of TRC calculations and ensure comprehensive consideration of all relevant factors.
1. ACCOUNT FOR PARTICIPANT NON-ENERGY BENEFITS (NEBS) The exclusion of participant NEBs is arguably the most important factor in generating bias against DSM. On the other hand, the reason that NEBs have historically been excluded is that t...
AI summary The exclusion of participant non-energy benefits (NEBs) may bias against demand-side management (DSM). NEBs are hard to quantify, leading to varied valuation methods: specific valuations via market research, inferred valuations using cost-saving algorithms, or approximate adders. Each approach has trade-offs, balancing accuracy against over-conservatism or false precision.
2. ACCOUNT FOR UTILITY NEBS As discussed previously, DSM arguably brings additional non-energy benefits to the utility (and hence ratepayers), primarily through risk mitigation. While risk benefits are important, they are even more difficu...
AI summary The document discusses the challenges of quantifying non-energy benefits (NEBs) from Demand Side Management (DSM), noting that regions like Vermont and the U.S. northwest use proxy adjustment factors in their cost-effectiveness algorithms. Risk mitigation is highlighted as a key non-energy benefit, though it remains difficult to measure.
Figure 8. Participant NEBs: The Case of B.C. In British Columbia, the ambitious DSM goals of BC Hydro and Fortis BC recently began to hit up against the limitations of the TRC. As a result, in December 2011, the province chose to redefine...
AI summary British Columbia redefined its Total Resource Cost (TRC) test to include non-energy benefits (NEBs) from demand-side management (DSM) programs. Three methods were introduced for NEB inclusion, with a 15% cap on portfolio-level impacts. Nova Scotia Power may benefit from reduced utility costs due to lower consumer electricity bills, though these are not quantified as utility NEBs.
3. ACCOUNT FOR ENVIRONMENTAL EXTERNALITIES? Environmental externalities are the most common DSM non-energy benefit included in costeffectiveness screening. A recent ACEEE study (Kushler, Nowak, & Witte, 2012) reports that 35% of the survey...
AI summary The text discusses the inclusion of environmental externalities in demand-side management (DSM) cost-effectiveness screening, citing a 2012 ACEEE study showing 35% of U.S. jurisdictions include such benefits. It notes that Nova Scotia's regulations may already internalize emissions through existing compliance measures, questioning the need for additional externalities accounting beyond societal perspectives.
4. REVISIT DISCOUNTING PRACTICE One last component that can be addressed relates to the treatment of future streams of energy savings. In the past, when utilities were by and large the sole administrators of DSM programs, the TRC typically...
AI summary The text argues that Nova Scotia should reconsider using the utility's weighted average cost of capital (WACC) as the discount rate for demand-side management (DSM) programs, given the shift to non-profit administration by Efficiency Nova Scotia (ENS) and societal policy influences. It highlights that DSM's risk profile is more favorable than supply options, and suggests adopting a societal discount rate, as seen in Efficiency Vermont's model.
OPTION B. MOVE FOCUS TO PAC TEST The other primary option for Nova Scotia is to focus instead on the narrower but more straightforward PAC test. Using the PAC test provides a clear measure of a program's (past or anticipated) performance,...
AI summary Option B advocates shifting to the PAC test for evaluating DSM programs, emphasizing its clarity, symmetry in cost-benefit analysis, and alignment with other jurisdictions like Connecticut and Michigan. It addresses concerns about equity and non-electric energy impacts through policy exceptions and dedicated funding. The PAC test is seen as more accurate and straightforward compared to TRC, with existing familiarity among stakeholders.
PRIMARY RECOMMENDATION Our review of the issues and options for Nova Scotia concludes with the need to change the current cost-effectiveness framework, to ensure internal consistency and best practices. In the absence of significant change...
AI summary The analysis recommends shifting from the Total Resource Cost (TRC) to the Program Administrator Cost (PAC) test for evaluating Demand Side Management (DSM) in Nova Scotia. This change is advocated for its simplicity, accuracy, relevance to ratepayer interests, and alignment with the 2014 Electricity Efficiency and Conservation Restructuring Act and Nova Scotia Power Inc.'s Integrated Resource Plan (IRP).
RECOMMENDATIONS - 1. Nova Scotia adopts the Program Administrator Cost (PAC) as the primary test for purposes of screening DSM cost-effectiveness; - 2. The PAC test be applied for information purposes at the program and portfolio levels, a...
AI summary The recommendations focus on adopting the Program Administrator Cost (PAC) as the primary test for DSM cost-effectiveness, applying it at different levels, re-examining discount rates for consistency, and developing a transparent reporting template based on NESP's framework.
Figure 9: Resource Value Framework - NS Qualitative Assessment Program Name: Electric DSM Date: December 2014 1. Key Assumptions, Parameters and S ummary of Resu its Analysis Level ✓ Program Alialysis Level □ Portfolio Measure Life n/a Dis...
AI summary Figure 9 presents a qualitative assessment of the Resource Value Framework for the Electric DSM program in Nova Scotia as of December 2014. It outlines key assumptions, monetized program administrator costs and benefits, participant costs and benefits, public costs and benefits, and non-monetized public benefits.
E-22014 Electricity Demand Side Management Plan Evaluation Reports
250 passages
2014 DSM EVALUATION REPORTS
AI summary The document titled '2014 DSM EVALUATION REPORTS' appears to reference an assessment of demand-side management (DSM) programs from 2014. However, no substantive content or analysis is provided in the text, leaving the scope, findings, or conclusions of the evaluation unspecified.
INTRODUCTION This document provides a summary of the 2014 evaluations conducted for the Efficiency Nova Scotia Corporation (ENSC) demand-side management (DSM) programs. Established in 2010, ENSC is an organization in charge of helping Nova...
AI summary This document summarizes the 2014 evaluations of Efficiency Nova Scotia Corporation's (ENSC) demand-side management (DSM) programs. The evaluations were conducted by Econoler, in collaboration with CRA and Equilibrium Engineering, and revealed significant energy and peak demand savings. The report also discusses the evaluation methods used for different program components.
Table 1: Types of Evaluation Conducted by Program Component or Initiative Type of Evaluation Program Component or Initiative Impact Process Market Full-scale Tracked Savings Validation Appliance Retirement - - - x Instant Savings x x x - H...
AI summary This report evaluates 17 program components and initiatives offered in 2014 by ENSC, summarizing evaluation methodology, DSM portfolio performance in terms of savings, and recommendations for improvement. It includes an in-depth analysis of individual program component performance.
1 EVALUATION OBJECTIVES AND METHODOLOGY This section presents the objectives of the 2014 evaluation as well as the methodology used and the activities carried out to evaluate ENSC's DSM program components.
AI summary This section outlines the 2014 evaluation of ENSC's Demand-side Management (DSM) program components, detailing the objectives and methodologies employed to assess their effectiveness.
1.1 Evaluation Objectives The objectives of the 2014 evaluation of ENSC's DSM program components were to: - › Assess the effectiveness of program component design and delivery - › Determine the extent to which program component implementat...
AI summary The 2014 evaluation of ENSC's DSM program aimed to assess design effectiveness, implementation progress, energy savings, NTGR, and net savings. Key objectives included verifying technology performance, calculating gross and net energy savings, and analyzing the net-to-gross ratio.
2 DSM PORTFOLIO PERFORMANCE This section presents an analysis of the impact evaluation results for all the program components. Those results were also used for making a comparison to the targets, as well as to analyze the evolution of savi...
AI summary This section evaluates the impact of DSM program components, comparing results to targets and analyzing savings trends over recent years. It focuses on assessing portfolio performance through quantitative analysis of program outcomes.
2.1 Overall Targets and Results ENSC programs encompass many components, which all share the same market. For instance, the Existing Residential program includes the Home Energy Assessment, Green Heat, Low Income Homeowner, Residential Dir...
AI summary ENSC programs, including the Existing Residential program, are evaluated against overall targets set by ENSC. The mid-course targets for program components were reviewed by the DSM Advisory Group, with overall energy and demand savings targets remaining consistent with those approved by the Nova Scotia Utility and Review Board (UARB) in 2014.
Table 5: 2014 Savings Targets and Evaluated Results DSM Program "As-Filed" Targets Mid-course Targets Evaluated Results GWh MW GWh MW GWh MW Residential Residential Efficient Products Rebatesa 19.3 3.1 17.5 2.8 13.493 2.520 Existing Reside...
AI summary Table 5 presents the 2014 savings targets and evaluated results for various demand-side management (DSM) programs in Nova Scotia, including residential and business, non-profit, and institutional programs. The table compares as-filed targets, mid-course targets, and actual evaluated results in terms of gigawatt-hours (GWh) and megawatts (MW).
The ENSC's portfolio of DSM program components achieved 151.888 GWh in total energy savings at the generator, which were 10 percent higher than the 2014 UARB-approved target. The total portfolio peak demand savings of 27.077 MW were howeve...
AI summary The ENSC's DSM program achieved 151.888 GWh in energy savings, exceeding the 2014 UARB target by 10 percent, but peak demand savings were slightly below the target. Custom Incentives and Energy Savings Actions compensated for shortfalls in other programs. Codes and Standards also contributed additional savings.
2.2 Individual Impact Evaluation Results [Table 6](#page-18-0) and 7 summarize the evaluated savings, the net savings targets revised in June 2014 and the savings tracked internally by ENSC for each program component offered in 2014. Speci...
AI summary Table 6 and 7 summarize evaluated savings, revised net savings targets from June 2014, and internal savings tracking by ENSC for each program component offered in 2014. Observations regarding each program component and initiative are also provided.
Table 7: 2014 Evaluated Results, Targets and Tracked Demand Savings at the Generator 2014 Demand Savings (MW) ENSC DSM Program DSM Component Initial Gross Savings Installed/ Adjusted Gross Savings Installed/Adjusted Gross Savings with Inte...
AI summary Table 7 presents the 2014 evaluated results, targets, and tracked demand savings at the generator for various DSM programs and components, including residential and business initiatives. It includes metrics such as initial gross savings, net savings, and targets for each program, with some notes on evaluation methods.
Residential Direct Install Residential Direct Install had a total of 13,945 participants in 2014, and achieved net energy and peak demand savings of 24.552 GWh and 5.721 MW respectively. In addition to the regular Residential Direct Instal...
AI summary The Residential Direct Install program achieved significant energy and peak demand savings in 2014, with additional savings from a CBSM Pilot. Evaluated savings were slightly lower than tracked values due to adjustments in unitary savings, installation rates, and free-ridership levels, which were offset by increased internal spillover effects.
LED Holiday Light Exchange In 2014, a total of 117 events were held for LED Holiday Light Exchange. The evaluation demonstrated net energy savings of 0.192 GWh and net peak demand savings of 0.414 MW resulting from the distribution of 6,34...
AI summary The LED Holiday Light Exchange in 2014 resulted in energy and peak demand savings, but the evaluated savings were lower than those tracked by ENSC due to revised assumptions on unitary savings and the inclusion of an interactive effect factor. These changes reduced the estimated net demand savings by 66%.
2.5 Portfolio Analysis In addition to the performance of individual program components, it is worth taking a look at individual program components' contributions to the portfolio's overall savings over the years. [Table 10](#page-29-0) bel...
AI summary This section discusses the evaluation of individual demand-side management (DSM) program components' contributions to total portfolio savings since 2011, as presented in Table 10.
Table 10: Individual Program Components' Contributions to Total Portfolio Savings in % Percentage of Portfolio Savings DSM Program 2011 2012 2013 2014 Energy Demand Energy Demand Energy Demand Energy Demand Residential Appliance Retirement...
AI summary The table highlights the contributions of various program components to total portfolio savings in the DSM program for residential and BNI categories from 2011 to 2014. Residential components contributed 53% of energy savings and 57% of peak demand savings in 2014, while BNI components accounted for the remaining percentages.
2.6 Overall Performance In 2014, ENSC's program component portfolio achieved a total of 151.888 GWh in net energy savings and 27.077 MW in net peak demand savings at the generator. In addition to the savings generated by ENSC's DSM program...
AI summary In 2014, ENSC achieved its overall energy savings targets through a combination of successful program components and new initiatives. While some program components did not meet their individual goals, others like Custom Incentives and Energy Savings Actions made up for the shortfalls. ENSC has made significant improvements in program tracking, partner relationships, and education efforts. However, some savings calculation parameters were not updated as recommended.
us years. This was found to be due in part to higher product removal rates by the participants, but also to entry errors made by the DAs. The Evaluator recommended that this situation be investigated. Survey results showed that word of mou...
AI summary The evaluation of the Residential Direct Install program found high participant satisfaction and effectiveness in promoting energy efficiency. Word of mouth was the main source of awareness, and participants reported positive changes in behavior, such as turning off lights and reducing water consumption. DAs noted the program's educational value but recommended improvements in marketing.
Table 14: Recommendations for Residential Direct Install No. Recommendations RDI-R3. Under the logic model, the Evaluator recommended that activities meant to address each of the barriers in the program theory column be clearly identified....
AI summary The table provides recommendations for the Residential Direct Install program, emphasizing the need to clearly identify activities addressing barriers and ensuring all fields in the tracking system are systematically filled out, including specifying the absence of secondary heating sources.
No. Recommendations BER-R4. Collect additional information on the measures sold through BER Instant Rebate and continue improving the tracking system. BER Instant Rebate tracking report has seen some significant improvements since last yea...
AI summary The recommendation emphasizes improving the tracking system for BER Instant Rebate by enhancing the Masterlist tab and validating unitary savings equations to improve accuracy in calculating energy and demand savings from lighting products sold through the program.
thoroughly and properly conducted. One element that explains why adjustments to peak demand savings were more significant is that the Evaluator changed some of the diversity factors estimated by ENSC. Moreover, when calculating the net ene...
AI summary The document discusses adjustments to peak demand savings, noting that changes in diversity factors by the Evaluator impacted the results. In 2014, Custom Retrofit achieved significant energy and peak demand savings, while EBC and EMIS contributed additional energy savings. Participant satisfaction with Custom Retrofit remained high, with most recommending it to others and expressing interest in future ENSC programs.
Table 18: Recommendations for Custom Retrofit No. Recommendations Custom-R2. Improve the information presented in the DSMDS reports. The Evaluator found that most of the important information for evaluation purposes could be obtained from...
AI summary The Evaluator recommends improving the DSMDS reports by adding details such as line loss factor, rate code, verified savings at the meter, and free-ridership screening results. It also suggests including both total and current-year savings for better sample selection and adding unique identifiers to distinguish between new and ongoing projects.
Table 19: Recommendations for Custom New Construction No. Recommendations NC-R4. Adding the Nova Scotia Power's rate code to the DSMDS report: While the Nova Scotia Power's rate code is entered into the DSMDS, it does not appear in the Eva...
AI summary The document recommends adding Nova Scotia Power's rate code to the DSMDS report to facilitate the application of the correct line loss factor when evaluating energy and demand savings at the meter level. This would help in accurately comparing values from the DSMDS report with project feasibility studies and M&V reports.
4.2.5 Codes and Standards Based on international experience and our own, evaluating the energy impact of regulations or policies is usually more difficult than calculating the impact of a DSM program, which has a list of participants and a...
AI summary Evaluating the energy impact of codes and standards is more complex than assessing DSM programs due to the difficulty in characterizing the entire market of targeted products. Econoler recommends strategies to ensure successful impact evaluations of future codes and standards.
Evaluation of 2014 DSM Programs Efficiency Nova Scotia Corporation Overall Executive Summary Overall free-ridership level (%) for the program component $$FR_{total} = \frac{\sum_{i=1}^{n} (FR_i \times Gross_Savings_i)}{\sum_{i=1}^{n} Gross...
AI summary The document evaluates the free-ridership level of the 2014 DSM programs managed by the Energy Efficiency Nova Scotia Corporation. A formula is provided to calculate the overall free-ridership percentage based on participant data and gross savings.
Overall Executive Summary Residential Direct Install l a fu ridorchi- Ujah fu ridorchi- Augrage for oo ridorshir Free-ridership algorithm -ridership cipant • -ridership cipant _ ee-ridership icipant Questions Calculation Algorithm Answer C...
AI summary The text presents a table analyzing free-ridership in a residential direct install program, including questions and calculations related to participant behavior, such as likelihood of installing energy-efficient products without the program and willingness to pay for them. It evaluates responses on a scale from 0 to 10 and calculates percentages based on answers.
2014 DSM Evaluation Report 手 ECONOLER Random sampling error The error in measurement due to the fact that measures are taken from a subset of the population and not the entire population. Sample size The number of observations or replicate...
AI summary The 2014 DSM Evaluation Report defines key terms related to demand-side management (DSM) evaluation, including random sampling error, sample size, secondary market impacts, tracked savings, and unitary savings. These concepts are essential for accurately measuring program effectiveness and energy savings.
5 From the ARet 2013 DSM Evaluation Report. The 2014 participant survey was used to establish which types of refrigerators were used to replace retired ones (new or used, high or standard efficiency). Answers from participants were used to...
AI summary The 2014 participant survey was used to determine the types of refrigerators used to replace retired ones, which helped establish the average annual energy consumption of replacement refrigerators at 450 kWh per year.
3.4 Demand-to-Energy Ratio Peak demand savings are calculated using an on-peak demand-to-energy ratio of 0.159 MW/GWh. This ratio was established based on a weighted-average ratio of modelled system-coincident peak demand savings and energ...
AI summary The demand-to-energy ratio of 0.159 MW/GWh is used to calculate peak demand savings in Nova Scotia. This ratio was developed by Navigant using a weighted average of modelled system-coincident peak demand and energy savings for measures supported by ARET in 2014, based on local data and technical literature.
3.10 Overall Net Savings The net energy savings are estimated by multiplying the gross savings by the NTGR and the interactive effects, based on the equation below. Net Energy Savings = Gross Energy Savings × NTGRequiv × (1 - Interactive E...
AI summary The net energy savings are calculated by multiplying gross savings by NTGR and interactive effects. The overall net energy and peak demand savings for ARET are 3.492 GWh and 0.555 MW at the meter, increasing to 3.585 GWh and 0.570 MW at the meter when including appliance replacement pilot projects.
Table 30: Validated Net Energy and Peak Demand Savings Refrigerators Freezers Room AC Units Appliance Replacement Pilot Total Energy Savings Total Gross Energy Savings – at meter (GWh) 3.739 2.093 0.034 0.094 5.960 NTGR 0.60 0.58 0.55 1.00...
AI summary Table 30 presents validated net energy and peak demand savings across various appliance categories, including refrigerators, freezers, and room air conditioners. It includes data on gross and net energy savings, interactive effects factors, line loss factors, and peak demand savings at both the meter and generator levels.
3. 4. 5. During certain months of the year only. Never plugged in or running. [SKIP TO U6] (DO NOT READ) Other (Please Specify): 98. 99. (Don't know) [SKIP TO U6] (Refused) [SKIP TO U6] U5. During the last year, how many total months do yo...
AI summary The text contains a series of survey questions related to energy usage, specifically focusing on the usage patterns of refrigerators and air conditioners. Questions ask about the frequency of use, location of appliances, and decision-making factors for turning on air conditioners.
Program Component Overview In 2014, Instant Savings worked in collaboration with nine major retail chains and 34 independent retailers across Nova Scotia to offer customers in-store discounts on different energy-efficient products. Discoun...
AI summary In 2014, Instant Savings collaborated with retailers in Nova Scotia to provide in-store discounts on energy-efficient products. Discounts were offered on a range of products, including ENERGY STAR® CFLs, LED lamps, and CEE Tier III appliances. Advertising included in-store promotions, online platforms, and events aimed at educating customers about the program and other ENSC services. The goal was to achieve electricity savings of 13.4 GWh and peak demand savings of 2.1 MW.
Key Findings In 2014, Instant Savings generated 9.360 GWh in net electricity savings at the generator in comparison with 26.524 GWh in 2013 and 10.767 GWh in 2012. It also generated peak demand savings of 1.479 MW at the generator in 2014....
AI summary In 2014, the Instant Savings program achieved 9.360 GWh in net electricity savings and 1.479 MW in peak demand savings at the generator, showing a decrease from 2013 and 2012 figures. Key findings are detailed in subsequent subsections.
Partner Satisfaction and Barriers The DA was asked to share its feedback about Instant Savings and ENSC in 2014. For the most part, the DA was pleased with the program's success, program marketing, outreach activities and the relationship...
AI summary The DA expressed overall satisfaction with Instant Savings and ENSC, though noted varying retailer engagement as a barrier. Retailers praised relationships and communication but were dissatisfied with delays in product approvals and rebate processing.
RECOMMENDATIONS Overall, the Econoler team is of the opinion that though Instant Savings contributed to the market transformation in Nova Scotia, its net impact decreased significantly this year. In addition to the general recommendations...
AI summary The Econoler team acknowledges the contribution of Instant Savings to market transformation in Nova Scotia but notes a significant decrease in its net impact this year. Specific recommendations are made to optimize the program, alongside general recommendations for all ENSC program components from the 2014 evaluation report.
2014 Instant-R1. Continue monitoring the retailers' commitment to meeting POP requirements. The DA mentioned that though its interactions with retailers improved over time, challenges remain in engaging some of the retailers. The DA pointe...
AI summary The DA noted ongoing challenges with retailer engagement and POP installation, recommending continued monitoring. There is a need for improved training for in-store event representatives, as they are not adequately informing customers about ENSC programs. Customer engagement events have been successful but require better training to enhance their effectiveness.
1 PROGRAM DESCRIPTION Efficiency Nova Scotia Corporation's (ENSC) Instant Savings offers customers instant cash discounts at participating retailers across Nova Scotia when they purchase eligible energy-efficient products. Instant Savings...
AI summary Efficiency Nova Scotia Corporation's (ENSC) Instant Savings program provides cash discounts on energy-efficient products through participating retailers. The program ran in 2014 with various campaigns and product discounts, with some products removed due to market saturation and regulatory changes.
2.2.2 Interview with Delivery Agent In October 2014, one interview was conducted with the DA in order to understand their involvement in the program, their participation process, as well as their perception of and satisfaction with the pro...
AI summary An interview was conducted in October 2014 with the Delivery Agent (DA) to understand their involvement in the program, their participation process, and their perception of and satisfaction with the program. The interview guide is referenced in Appendix II.
2.2.3 Interviews with Retailers In the fall of 2014, CRA conducted a total of 14 in-depth interviews with retailers (also known as "partners"). These interviews focused on two specific products: ENERGY STAR® CFLs and ENERGY STAR® LED lamps...
AI summary In the fall of 2014, CRA conducted 14 in-depth interviews with retailers to assess their experiences with ENERGY STAR® CFLs and LED lamps, focusing on market spillover effects and satisfaction with the Instant Savings program.
2.2.4 In-store Visits In the spring (April) and fall (October) of 2014, a total of 20 visits and observations were conducted by Econoler in various stores to gather qualitative information to describe the in-store client experience. Nine m...
AI summary In 2014, Econoler conducted 20 in-store visits in April and October across nine major chain retailers to assess the efficiency of instant rebates, product displays, and employees' knowledge of energy efficiency programs.
Table 5: Implementation Status of Recommendations in the 2012 and 2013 Executive Summaries Recommendation Status 2012 Recommendations 2012 Instant-R1. Document the AIR MILES® approach No longer applicable 2012 Instant-R2. Generate greater...
AI summary This table outlines the implementation status of recommendations from the 2012 and 2013 Executive Summaries, focusing on energy efficiency programs such as the promotion of LED products, retailer involvement, and adjustments to tracking sheets and savings calculations for lighting products.
2012 Executive Summary Recommendations The Evaluator noticed that four of the five recommendations were implemented by ENSC and allowed for overall program improvement. The only recommendation that was not implemented is the one requesting...
AI summary The Evaluator noted that four of five recommendations were implemented by ENSC, leading to program improvements. The unimplemented recommendation involved documenting the AIR MILES approach. The removal of CFLs and changes to refrigerator and washer eligibility were made based on recommendations to improve energy efficiency and market penetration.
2013 Executive Summary Recommendations Four of the five recommendations were implemented by ENSC. Acting on these recommendations, ENSC increased promotion of products other than CFLs and LED lamps, and continued conducting general populat...
AI summary In 2013, ENSC implemented four recommendations to promote energy-efficient products beyond CFLs and LED lamps. Findings from surveys showed low awareness and purchase intent for other discounted products. ENSC conducted a price study, held in-store events, and developed a new POP system to promote these products. Additionally, they launched the Instant Savings application to highlight savings from eligible products.
3.2 Program Documentation and Design As part of the evaluation, the Evaluator analyzed the program documentation and worked together with the PM to improve and revise the content of the program manual, the evaluation plan and the logic mod...
AI summary The Evaluator analyzed program documentation and worked with the Program Manager to revise the program manual, evaluation plan, and logic model. Key issues included the need to document changes to eligible products and the lack of participant identification in the Instant Savings program, which complicates evaluation efforts.
3.3 Tracking System For 2014, the tracking information for Instant Savings is presented in the form of an Excel spreadsheet, which is subsequently uploaded into the demand-side management data system (DSMDS). Each participating retailer co...
AI summary The tracking system for Instant Savings in 2014 uses an Excel spreadsheet uploaded into the DSMDS. Retailers collect detailed product data, including measure codes, SKUs, pricing, and rebates, which are compiled by Summerhill and submitted to ENSC. The tracking sheet includes store identifiers, which help in error resolution and data collection planning. ENSC has improved the percentage of records with store identifiers by 9 percentage points since 2013.
Product Promotional Displays The majority of the stores visited used the point-of-purchase (POP) displays provided by ENSC and displayed them in each section where eligible products were found. Most of the proposed promotional tools were u...
AI summary The majority of stores used ENSC's POP displays for eligible products, though clotheslines were less visible. One retailer used in-house displays effectively. Two stores had successful in-store events promoting ENSC programs.
Employees' Knowledge of the Products and Program Overall, the salespeople were aware of the Instant Savings campaign, though they were not always aware of the terms and conditions of the program, such as the end date of the campaign. Sales...
AI summary Salespeople had general awareness of the Instant Savings campaign but were unclear about its terms and conditions. Their knowledge of energy-efficient product characteristics was limited, and reliance on POP displays for discount information was noted.
3.4.3 In-store Visits Summary In summary, the mystery shopper observed an improvement in the awarding of rebates at the cash between the spring and fall campaigns. Not only was there less confusion, but there were also fewer problems with...
AI summary The mystery shopper observed improvements in rebate processing and POP display variety during the fall campaign compared to spring. However, there were concerns about the proper installation of POP displays and the level of preparedness among fall representatives. Spring representatives were better at informing customers about ENSC programs.
4.1.1 Interview with Delivery Agent The DA described its involvement in Instant Savings as complex, given its participation in multiple aspects of program delivery, including communication with all the retail partners, assigning and superv...
AI summary The Delivery Agent (DA) discussed challenges in delivering the Instant Savings program, including varying retailer engagement, difficulties with rebate processing, and delays in receiving rebated product lists from Efficiency Nova Scotia Corporation (ENSC). Minor adjustments were made to the DA's workflow to accommodate program changes.
4.1.2 Interviews with Retailers As part of the Instant Savings evaluation, eight interviews were conducted with nationwide retailers and six interviews were conducted with independent retailers. It should be noted that the nationwide retai...
AI summary Eight interviews with nationwide retailers and six with independent retailers were conducted as part of the Instant Savings evaluation. Satisfaction with the program was moderately high, with independent retailers generally more satisfied than nationwide retailers. Support and communication were highly rated, though some concerns were raised regarding DA representatives and timely updates to rebated appliance lists.
Table 11: Importance of Discount in Influencing Installation Importance of 2012 2013 2014 Discount in Influencing Decision to Install Energy efficient Products CFL Purchasers LED Lamp Purchasers CFL Purchasers LED Lamp Purchasers CFL Purch...
AI summary Table 11 presents data on the importance of discounts in influencing the purchase of energy-efficient products, specifically CFLs and LED lamps, across years 2012 to 2014. The mean scores indicate that discounts were perceived as somewhat influential, with higher scores for LED lamp purchasers compared to CFL purchasers in most years.
Revised Savings The Econoler team reviewed the content of the tracking sheet to validate the types of heavy duty timers that were sold in 2014. Online information about the four most popular models (more than 20 units sold during the sprin...
AI summary The Econoler team reviewed heavy duty timer sales in 2014, finding 60% were used for outdoor lighting control and 40% for water ponds or pool pumping systems. These findings align with the OPA's 2012 evaluation, which reported similar usage patterns and an average unitary savings of 122 kWh for such timers.
5.1.15 Demand-to-Energy Ratio Peak demand savings are calculated using an on-peak demand-to-energy ratio of 0.158 MW/GWh. This ratio was established based on a weighted-average ratio of modelled system-coincident peak demand savings and en...
AI summary The demand-to-energy ratio of 0.158 MW/GWh is used to calculate peak demand savings. This ratio was established by Navigant using a weighted average of modelled system-coincident peak demand and energy savings for measures supported by Instant Savings in 2014.
5.1.16 Revised Gross Savings The annual energy and peak demand gross savings for each category of products installed through Instant Savings are presented in Table 27. They were calculated using the revised unitary savings values and the d...
AI summary The document presents revised gross savings for energy and peak demand from Instant Savings programs, calculated using updated unitary savings values and a demand-to-energy ratio. Total savings at the meter are 9.776 GWh and 1.545 MW, while generator-level savings are 10.754 GWh and 1.699 MW, factoring in a line loss of 1.100.
Table 27: Evaluation Results – Gross Energy and Peak Demand Savings by Product – Lighting Products Product Category Regular CFL Specialty CFL LED Lamp LED Recessed Downlight Dimmer Switch Indoor Motion Sensor Motion Sensor with Dimmer Swit...
AI summary Table 27 presents evaluation results for gross energy and peak demand savings by product category for lighting products, including CFLs, LEDs, and motion sensors. The table includes data on the number of units installed, energy savings in kWh and GWh, and peak demand savings in MW across different seasons and product types.
Table 28: Evaluation Results – Gross Energy and Peak Demand Savings by Product – Other Products Product Category Power Bar with Timer Smart Power Bar Heavy Duty Timer Clothes lines Program mable Ther mostat CEE Tier III Refrige rator CEE T...
AI summary Table 28 presents evaluation results of energy and peak demand savings by product category for other products, including power bars, timers, clothes lines, and refrigerators. The data includes units installed during Spring and Fall, energy savings in GWh, and peak demand savings in MW, with line loss factors applied for both meter and generator levels.
5.3.2 Spillover Instant Savings discounts were offered during two distinct periods: in the spring and in the fall. During and between these two periods, eligible product sales may have occurred due to program influence, even if participant...
AI summary The text discusses spillover effects from the Instant Savings program, analyzing how energy-efficient product sales (CFLs and LED lamps) were influenced by the program even when participants were unaware of the discount. Retailer interviews and market effects were used to estimate program attribution, which decreased for CFLs but remained stable for LED lamps.
CONCLUSION The 2014 evaluation of Instant Savings demonstrated that most of the recommendations made specifically for Instant Savings in the previous evaluations were implemented. The Evaluator commends ENSC on the efforts it made to impro...
AI summary The 2014 evaluation of Instant Savings highlights improvements in the program, including the removal of CFLs and the promotion of LED lamps. However, challenges remain, such as retailer engagement and communication delays. Energy savings declined compared to previous years, partly due to budget cuts and lower unitary savings for certain products.
This Appendix summarizes all the recommendations made by the Evaluator throughout this report as well as the sections from which the recommendations originated. Sections Recommendations Executive Summary 1 Continue monitoring the retailers...
AI summary This section highlights the need to continue monitoring retailers' compliance with POP requirements. The DA noted that while interactions with retailers have improved, challenges remain. The Evaluator observed shortcomings in in-store signage, which could mislead salespeople and customers about discounted products.
C2a. By what percentage do you estimate the number of regular Energy Star CFL bulbs sold in your store would have been lower during the April-May campaign if the discount had not been available? RECORD PERCENTAGE ___% - C6. What influence...
AI summary The text asks about the impact of the Instant Savings program on CFL sales, including the percentage of sales outside the spring campaign that can be attributed to the program. It also inquires about the program's influence on salespeople's knowledge, product variety, and customer awareness.
Table 36: In-Store Promotional Material - In the table below, please indicate by using Yes/No for each product category whether the promotional material was displayed in store as well as the quantity of each type of promotional material (s...
AI summary The text provides a table titled 'In-Store Promotional Material' asking retailers to indicate whether promotional materials were displayed in-store for each product category and the quantity used. Retailers may choose not to use POP (Point of Purchase) materials provided by ENSC. Additional comments can be added in the Comments section.
2014 DSM Evaluation Report
AI summary The 2014 DSM Evaluation Report provides an assessment of demand-side management initiatives undertaken in 2014, focusing on their performance, impact, and effectiveness in promoting energy efficiency.
Knowledge of Products 5. Could you tell me how these products (products eligible for the instant rebate) differ from other products sold in your store? 2014 DSM Evaluation Report
AI summary The question asks about the differences between eligible products for instant rebates and other products sold in the store, referencing a 2014 DSM Evaluation Report.
Table 39: In-Store Promotional Material - In the table below, please indicate by using Yes/No for each product category whether the promotional material was displayed in store as well as the quantity of each type of promotional material (s...
AI summary The document outlines requirements for in-store promotional material, specifying that stores must indicate with Yes/No whether promotional materials were displayed for each product category and the quantity used. Stores may not use all POP provided by ENSC, but products on rebate must be clearly marked with sticker talkers and hang tabs.
Do not ask the following questions directly to the representative. Simply show interest in the product/event. In-Store Event Section of the Store where the Event Takes Place Location of the event (which section in the store). Is it a high...
AI summary This table outlines an in-store event related to energy efficiency programs, focusing on the location of the event, the information provided by representatives, and the visibility of the event through promotional materials. It includes questions about product rebates, rebate amounts, and other programs promoted by ENSC.
CFL SEQUENCE [SKIP IF I1=2] FR0a. You bought CFLs today. Efficiency Nova Scotia offered a discount on packages of CFLs. Before paying at the cash register, were you aware that a discount was offered on the purchase of CFLs? [CODE ONE ONLY]...
AI summary The document outlines a survey process related to the purchase of Compact Fluorescent Lamps (CFLs) and includes a reference to the 2014 DSM Evaluation Report. It asks respondents about their awareness of discounts offered on CFL packages and how they learned about them.
- FR4. If the discount had NOT been offered, when would you have purchased the CFLs that you purchased today? Would it have been…? [CODE ONE ONLY] - 1. Definitely today - 2. Probably today - 3. Probably at a later date - 4. Definitely at a...
AI summary The text contains survey questions related to consumer behavior regarding the purchase of energy-efficient lighting products, specifically CFLs and L-E-Ds, and the influence of discounts offered by Efficiency Nova Scotia on these purchases.
f L-E-Ds. Did knowing this play a part in your decision to buy L-E-Ds today? [CODE ONE ONLY] - 1. Yes - 2. No - 98. (Don't know) - 99. (Refused) [ASK IF AWARE OF THE DISCOUNT (FR0aa=1) OR (FR0bb=1)] FR31. How likely would you have been to...
AI summary The text includes survey questions about consumer behavior regarding LED purchases, specifically asking whether knowledge of discounts influenced the decision to buy LEDs and assessing the likelihood of purchase without the discount.
FR41. If the discount had NOT been offered, when would you have purchased the L-E-Ds that you purchased today? Would it have been…? [CODE ONE ONLY] - 1. Definitely today - 2. Probably today - 3. Probably at a later date - 4. Definitely at...
AI summary The text contains survey questions aimed at assessing the impact of a discount offered by Efficiency Nova Scotia on customers' decisions to purchase L-E-Ds. Respondents are asked about their purchase timing and quantity without the discount, as well as the level of influence the discount had on their decision.
[ASK ALL RESPONDENTS] - D1. What type of residence do you live in? [READ FIRST SEVEN RESPONSES; SELECT ONE RESPONSE] - 1. Detached single-family house - 2. Semi-detached house - 3. Mobile home or house trailer 2014 DSM Evaluation Report
AI summary The text includes a survey question about residence type and references a 2014 DSM Evaluation Report. It does not provide detailed information about the report's content or any specific arguments or entities involved.
Free-Ridership (FR Series) FR0aa. You bought L-E-Ds today. Efficiency Nova Scotia offered a discount on packages of L-E-Ds. Before paying at the cash register, were you aware that a discount was offered on the purchase of L-E-Ds? [CODE ONE...
AI summary This section of the Free-Ridership (FR Series) survey asks respondents about their awareness of a discount on LED purchases and how that awareness influenced their purchasing decisions. It explores the channels through which they learned about the discount and whether they would have made the purchase without it.
[ASK ALL RESPONDENTS] - D1. What type of residence do you live in? [READ FIRST SEVEN RESPONSES; SELECT ONE RESPONSE] - 1. Detached single-family house - 2. Semi-detached house - 3. Mobile home or house trailer - 4. Townhouse or duplex whic...
AI summary The document contains a survey question asking respondents about their type of residence and references a 2014 DSM Evaluation Report. It is part of a regulatory proceeding in Nova Scotia.
APPENDIX VIII INTERNAL SPILLOVER METHODOLOGY The retailer interviews were used to estimate the level of spillover by measuring the market effects attributable to the program for two eligible products: CFLs and LED lamps. Instant Savings di...
AI summary This appendix discusses the methodology used to estimate internal spillover effects from the Instant Savings program by analyzing retailer interviews and market effects on sales of energy-efficient products like CFLs and LED lamps, even outside of campaign periods.
HOME ENERGY ASSESSMENT 2014 DSM EVALUATION 2014 DSM Evaluation Report
AI summary This document is the 2014 DSM Evaluation Report, focusing on the Home Energy Assessment program as part of the Demand Side Management (DSM) evaluation. It provides an analysis of program performance and outcomes.
3.1.2 Peak Demand Savings Peak demand savings are calculated using an on-peak demand-to-energy ratio of 0.246 MW/GWh. This ratio was established based on a weighted-average ratio of modelled system-coincident peak 2 94 were from LIH and 32...
AI summary Peak demand savings are calculated using a 0.246 MW/GWh ratio, based on modelled system-coincident peak demand and energy savings from HEA-supported measures in 2014, as developed by Navigant in the 2013-2015 DSM Plan. The ratio was determined using local data and technical literature.
4 UNCONVERTED D STUDY SAVINGS In 2013, many participants did not complete the E assessment. The partner's interviews from the 2013 process evaluation showed that the main reason for this was the length of time to complete the E assessment...
AI summary The document discusses the 2013 Unconverted D Study Savings, focusing on participants who did not complete the E assessment. It outlines the methodology used to calculate energy savings from unconverted participants, including survey results, the influence of energy assessments, and the calculation of net energy and peak demand savings.
Table 6: Unconverted D Study Electrical Savings Unconverted D Study Electrical Savings Total Number of Unconverted D Study Participants 3,088 Ratio of Unconverted D Study Participants Who Implemented at Least One Measure 73% Total Number o...
AI summary Table 6 presents data on electrical savings from the Unconverted D Study, including participant numbers, implementation rates, average savings per participant, and energy and peak demand savings at both the meter and generator levels.
2014 DSM Evaluation Report
AI summary The 2014 DSM Evaluation Report provides an assessment of demand-side management initiatives, focusing on their effectiveness and impact on energy efficiency and customer participation.
D1. What type of residence do you live in? Type of Residence 2012 2013 2014 Sample Size 80 101 100 Single-family detached 88% 97% 91% Semi-detached 8% - 4% Townhouse or duplex - 3% 2% Mobile home or house trailer 3% - 1% Others - - 1% Don'...
AI summary The text presents data on residence types, bedroom counts, and home occupancy patterns across three years (2012-2014). It includes statistical breakdowns of single-family detached homes, semi-detached homes, and seasonal vs. year-round occupancy, along with sample sizes for each year.
Recommendations Overall, the Econoler team believes that Green Heat is operating in a satisfactory manner. In addition to the general recommendations presented for all the ENSC program components in the overall evaluation executive summary...
AI summary The Econoler team recommends optimizing Green Heat's performance by adjusting initial system efficiency assumptions and improving pre-screening processes to ensure accurate information about the initial heating system type. These changes aim to enhance eligibility criteria and improve energy savings calculations.
2.2.4 Unitary Savings Review To review the unitary savings values used in the tracking sheet, the Econoler team validated the parameters currently used in the tracked savings calculations by conducting a literature review of similar techni...
AI summary The Econoler team reviewed unitary savings values by validating parameters using technical references and public reports, and conducting engineering calculations when necessary. Due to a small population size, a census was used for the Green Heat survey rather than sampling.
3.3 Program Documentation and Design As part of the evaluation, the Evaluator analyzed the program documentation and worked together with the PM to improve and revise the program manual, the evaluation plan and the logic model, where appli...
AI summary The Evaluator worked with the Program Manager to revise program documentation, including the program manual, evaluation plan, and logic model for Green Heat. A project workflow checklist was developed and integrated into the Data Management System to ensure proper application processing and prevent missing information.
3.4 Tracking System In 2014, ENSC began to track Green Heat data using the demand-side management data system (DSMDS) and generate tracking reports (extracted directly from the DSMDS) for evaluation purposes. The DSMDS and the tracking rep...
AI summary In 2014, ENSC started using the DSMDS to track Green Heat data and generate tracking reports, replacing the 2013 Excel-based tracking sheet. The 2014 tracking report is an Excel workbook with four tabs containing different types of information.
Project Details The project details tab contains the most information, and is similar in scope to the 2013 tracking sheet used by Green Heat. Information contained in this tab includes project ID, utility account number, rate code, project...
AI summary The project details tab includes information such as project ID, utility account number, rate code, project status, participant contact details, and equipment details. This information was used by the Evaluator to calculate savings, develop sampling plans, and adjust on-site visit protocols for 2014.
Installed Systems The final tab in the tracking report contains a summary table of the equipment installed to date. The quantity of each equipment type was recorded and categorized in two groups, namely those that received financing and th...
AI summary The tracking report for installed systems provides a detailed summary of equipment installed, categorized by financing and rebate. The report is well-organized, but issues were identified, such as inaccuracies in unitary savings for heat pump projects and missing data like utility account numbers and backup heating sources. The Evaluator recommends improvements to data collection for future analysis.
5.1 Gross Savings The tracking report provided for 2014 shows a total of 235 participants (193 from the rebate option and 42 from the financing option), who had installed a total of 235 units. The following sections present the unitary sav...
AI summary The 2014 tracking report shows 235 participants who installed energy-efficient equipment through rebate and financing options. The report includes unitary savings values tracked by ENSC and a revision conducted by the Evaluator.
5.1.2 Revised Gross Savings The annual gross savings for each category of equipment installed through Green Heat are presented in [Table 16.](#page-145-1) These were calculated using the unitary savings values revised in this report. Overa...
AI summary The revised gross savings from Green Heat programs are detailed, showing 2.090 GWh in energy savings and 0.844 MW in peak demand savings at the meter. At the generator level, these figures increase to 2.299 GWh and 0.928 MW, factoring in Nova Scotia Power's residential line loss factor of 1.100.
Table 16: Evaluation Results – Revised Gross Energy and Peak Demand Savings Category of Product Wood Stove Pellet Stove Wood Furnace or Boiler Pellet Furnace or Boiler Central Ducted Heat Pump Geoth. Heat Pump Total Energy Savings Number o...
AI summary Table 16 presents evaluation results for revised gross energy and peak demand savings across various heating products, including wood and pellet stoves, furnaces, and heat pumps. It includes metrics such as number of units, unitary savings, adjustments for heat pump usage, and total energy and peak demand savings at both meter and generator levels.
Table 17: Evaluation Results – Revised Net Energy and Peak Demand Savings Category of Product Wood Stove Pellet Stove Wood Furnace or Boiler Pellet Furnace or Boiler Central Ducted Heat Pump Geoth. Heat Pump Total Energy Savings Total Gros...
AI summary Table 17 presents the evaluation results for revised net energy and peak demand savings across various heating products, including wood and pellet stoves, furnaces, and heat pumps. The table includes metrics such as total gross and net energy savings, line loss factors, and peak demand savings at both the meter and generator levels.
On-site Visit Protocol Similar to the other program evaluations, the Evaluator prepared a standardized site visit protocol to aid in collecting relevant information. Validation of unitary savings is limited primarily to confirming that ope...
AI summary The document outlines the On-site Visit Protocol used to evaluate program effectiveness, focusing on verifying unitary savings by confirming that new equipment has displaced electrical heating systems. Information such as building type, occupants, and equipment location is collected to validate data and identify process improvements.
2.1.4 Peak Demand Savings Peak demand savings are calculated using an on-peak demand-to-energy ratio of 0.233 MW/GWh. This ratio was established based on a weighted-average ratio of modelled system-coincident peak demand savings and energy...
AI summary Peak demand savings are calculated using an on-peak demand-to-energy ratio of 0.233 MW/GWh, based on a weighted-average ratio from modelled system-coincident peak demand savings and energy savings for measures supported by low-income homeowners in 2014, as developed by Navigant in the 2013-2015 DSM Plan.
ABBREVIATIONS CATI Computer-Assisted Telephone Interviewing CRA Corporate Research Associates DSM Demand-side Management ENSC Efficiency Nova Scotia Corporation HEA Home Energy Assessment LIH Low Income Homeowner NBC National Building Code...
AI summary This section provides a list of abbreviations used in the document, including terms related to research, energy efficiency, and regulatory processes. It includes definitions for terms like CRA, DSM, ENSC, and PRISM, which are relevant to the regulatory proceeding.
2014 DSM Evaluation Report
AI summary The 2014 DSM Evaluation Report provides an assessment of the demand-side management (DSM) initiatives implemented in 2014, focusing on their effectiveness and impact on energy efficiency and conservation efforts.
D11. What temperature do you normally set your thermostat to when you are at home? Thermostat Temperature 2014 Sample Size 48 20 or lower 44% 21-22 42% 23+ 15% Mean 20.5
AI summary The data shows that in 2014, 44% of respondents set their thermostat to 20 or lower, 42% set it to 21-22, and 15% set it to 23 or higher, with a mean temperature of 20.5.
APPENDIX VI INTERNAL SPILLOVER METHODOLOGY The marketing of New Home Construction is primarily conducted through builders who receive promotion and awareness documents on various energy efficiency measures. Consequently, market effects, wh...
AI summary The appendix discusses the methodology for calculating internal spillover effects in the context of energy efficiency programs. It focuses on how builders may have implemented energy efficiency measures without formally participating in the New Home Construction or Performance Plus programs, using data from 2014 to estimate market effects.
RESIDENTIAL DIRECT INSTALL 2014 DSM EVALUATION 2014 DSM Evaluation Report
AI summary This document is the 2014 DSM Evaluation Report for the Residential Direct Install program, which assesses the effectiveness and outcomes of the program in promoting energy efficiency in residential settings.
Table 1: Distortion Effects and Overall Net-to-Gross Ratio Calculation Group of Participants Non-Low-Income Low-Income Free-ridership Level 15% - Spillover Level 6% - NTGR 0.91 1.00 Proportion1 77% 23% Overall NTGR 0.93 The evaluation reve...
AI summary Table 1 presents distortion effects and the overall net-to-gross ratio (NTGR) for non-low-income and low-income participants. The evaluation shows that the Residential Direct Install (RDI) program achieved net energy savings of 24.552 GWh and peak demand savings of 5.721 MW in 2014.
2.2.3 On-site Visits In the fall of 2014, 50 on-site visits were conducted in households where energy-efficient products had been installed by the DAs. These visits were conducted by Equilibrium, Econoler's subcontractor. They aimed at val...
AI summary In 2014, 50 on-site visits were conducted by Equilibrium to validate the proper installation of energy-efficient products in Nova Scotia households. Additional visits were made during installation to ensure the process was correctly followed, including data verification and product selection.
Annual Participant Survey The annual survey conducted for RDI in July 2014 targeted three different groups of participants: 2013 participants, 2014 participants and participants who took part in the CBSM Pilot in late 2013. The interviews...
AI summary The annual participant survey for RDI in July 2014 targeted three groups: 2013 and 2014 participants, and CBSM Pilot participants. The survey aimed to gather feedback on program aspects like spillover, awareness, motivations, and satisfaction, and included questions about clothes washing habits to compare CBSM Pilot participants with a control group.
For the quarterly surveys, four series of interviews with a total of 110 participants were conducted using CATI technology during four periods in April, July, October and December 2014. Such surveys were conducted to shorten the time gap b...
AI summary Quarterly surveys using CATI technology were conducted in April, July, October, and December 2014 with 110 participants to evaluate the RDI program's free-ridership and participant satisfaction with Efficiency Nova Scotia. The surveys were 9.5 minutes on average, and results are detailed in Appendices VII and VIII.
3.1 Participation in RDI RDI totalled 13,945 participants for the year 2014, compared to 23,587 participants for 2013 and 28,397 participants for 2012. Even though the number of participants per se has decreased in 2014, RDI has reached it...
AI summary In 2014, the RDI program had 13,945 participants, a decrease from previous years, but still met its energy savings targets. The reduction in the number of participants was offset by increased savings per home due to the introduction of LEDs and smart power controllers.
Table 5: Implementation Status of Recommendations in 2012 Executive Summary Recommendation Status 2012 RDI-R1 Fine-tune the program marketing approach Implemented 2012 RDI-R2 Continue informing participants about energy-efficient products...
AI summary Table 5 outlines the implementation status of 2012 recommendations related to the Residential Direct Install (RDI) program. All recommendations were implemented by Efficiency Nova Scotia (ENSC), leading to program improvements, including a transition from CFL to LED installations due to market changes and free-ridership concerns.
3.3 Program Documentation and Design As part of the evaluation, the Evaluator analyzed the program documentation and worked together with the PM to improve and revise the content of the program manual, evaluation plan and logic model, wher...
AI summary The Evaluator worked with the Program Manager to revise program documentation, focusing on defining barriers to RDI and clarifying key aspects such as the transition from CFLs to LEDs, procedures for identifying low-income participants, and differences between RDI and MURB to avoid overlap.
3.4 Tracking System The Econoler team reviewed the 2014 RDI tracking sheet content. It was presented under the form of a spreadsheet, in which each of the DA's installations is compiled. At this point in time, ENSC does not use the DSMDS f...
AI summary The tracking system for the Residential Direct Install (RDI) program is reviewed, highlighting its use of spreadsheets to compile installation data. ENSC does not use the DSMDS for daily management, but the system tracks participant information, energy savings, and other relevant data for program evaluation. Some data collection challenges remain, such as missing rate codes.
3.5 On-site Visits during the Installation Process For the 2014 impact evaluation, three site visits with both RDI DAs were performed during the installation process. At the beginning of the appointment, the DA collected general informatio...
AI summary This section discusses the on-site visits conducted during the installation process for the 2014 impact evaluation. It details the procedures followed by DAs, including product replacement, quality checks, and participant interactions, as well as challenges encountered such as incompatible fixtures and existing tank wraps.
4.1 Partner Perspectives Interviews with two DAs were conducted as part of the RDI evaluation. Overall, RDI is viewed as valuable, efficiently administered, and effective in promoting energy efficiency. Changes made to RDI over the past ye...
AI summary The RDI program is viewed as effective and efficiently administered by DAs, though marketing limitations and product selection issues are noted. DAs highlight the importance of referrals and word of mouth in program participation, while expressing concerns about short-term contracts and limited product variety. Suggestions for improving educational outreach and streamlining promotional materials are made.
4.2.3 RDI Impact The majority of participants recalled receiving information about energy efficient products from the installer (70% in 2014). This information led to a change in behaviour for approximately one-half of those who received t...
AI summary Most participants remembered receiving information about energy-efficient products from installers in 2014, with about half reporting a change in behavior as a result. Table 9 details the behavioral changes mentioned by participants.
Table 11: Recommendations for Improvement Suggestions 2012 2013 2014 Sample Size 181 159 164 Offer more products/measures to be installed 6% 9% 10% Better advertising/program awareness 13% 5% 4% Offer more information on the products/measu...
AI summary Table 11 presents recommendations for improvement across three years (2012–2014), with the majority of respondents indicating no other recommendations. The most common suggestions include offering more products, better advertising, and providing more information on installed measures.
5 IMPACT EVALUATION FOR RDI The objective of the 2014 RDI impact evaluation is to determine the gross and net energy savings generated by the energy-efficient products installed in participating households. Both electrical energy and peak...
AI summary The 2014 RDI impact evaluation aims to assess the gross and net energy savings from energy-efficient product installations in participating households, considering factors like unitary savings values, installation rates, and free-ridership.
Tracked Savings Since the removal of CFLs, LED lamps are offered for free to the RDI participants. In the current tracking sheet, the amount of LED lamps installed is recorded under a different field for each combination of replaced lamp w...
AI summary The document discusses how LED lamps are tracked for installation by RDI participants, with different fields for each combination of replaced and new lamp wattages. ENSC uses a fixed daily usage value of 2.68 hours for LED lamps, derived from Hydro-Québec's metering study for indoor usage, unlike the approach used for CFLs.
5.1.10 Demand-to-Energy Ratio Peak demand savings are calculated using an on-peak demand-to-energy ratio of 0.233 MW/GWh. This ratio was established based on a weighted-average ratio of modelled system-coincident peak demand savings and en...
AI summary The demand-to-energy ratio of 0.233 MW/GWh is used to calculate peak demand savings, based on a weighted average from modelled data in the 2013-2015 DSM Plan. The ratio was determined using local data and technical literature, focusing on peak demand periods in Nova Scotia.
Table 22: Tracked Evaluation Results – Gross Energy and Peak Demand Savings by Product C F Ls Ca f Pr du te t g or y o o c 1 3 W Re la in p c g 4 0 W 1 3 W Re la in p c g 6 0 W 1 3 W Re la in p c g 1 0 0 W 2 3 W Re la in p c g 4 0 W 2 3 W...
AI summary Table 22 presents tracked evaluation results for energy and peak demand savings by product, including installation rates, total units, savings in kilowatt-hours, and peak demand savings in megawatts for various categories of products.
(Continued) LED L _amps Category of Product 8W Replacing 40W 8W Replacing 60W 8W Replacing 100W 10.5W Replacing 40W 10.5W Replacing 60W 10.5W Replacing 100W 11W Replacing 40W 11W Replacing 60W 11W Replacing 100W 12W Replacing 40W Energy Sa...
AI summary The text presents a detailed table outlining energy savings data for various LED light products, including installation rates, energy savings values, and peak demand savings. The table includes metrics such as total number of units, installation rates, and gross energy and peak demand savings at both the meter and generator levels.
5.2 Interactive Effects In a home, interactive effects occur when the implementation of energy efficiency measures has an impact on the energy consumption of other elements such as heating and cooling. In the case of RDI, replacement of in...
AI summary Interactive effects in energy efficiency measures, such as replacing incandescent lighting with CFLs or LEDs, can influence heating and cooling loads in homes. This is based on a 1992 study by ADS for Hydro-Québec using DOE-2 simulations, which considered three interactive-effects scenarios. The low-impact scenario was selected for calculations, reflecting home evolution since 1992.
5.3 Net-to-Gross Ratio The net-to-gross ratio (NTGR) evaluation is based on a self-report approach which relies on a series of questions designed to measure the impact of RDI on the participants' decision to implement eligible energy effic...
AI summary The net-to-gross ratio (NTGR) evaluation uses a self-report approach to assess the impact of the Residential Demand Response Initiative (RDI) on participants' decisions to implement energy efficiency upgrades. The methodology includes assessing distortion effects such as free-ridership and internal spillover.
Table 27: Evaluated Net Energy and Peak Demand Savings by Product C F Ls In ive E f fe Fa te t t to ra c c c r -2 0. 6 % -2 0. 6 % -2 0. 6 % -2 0. 6 % -2 0. 6 % -2 0. 6 % -2 0. 6 % N T G R 0. 9 3 0. 9 3 0. 9 3 0. 9 3 0. 9 3 0. 9 3 0. 9 3 T...
AI summary Table 27 presents evaluated net energy and peak demand savings by product, including metrics such as net-to-gross ratio (NTGR), total net peak demand savings, and line loss factors. The data indicates a consistent -20.6% efficiency factor and a constant NTGR of 0.93 across all product categories.
6.1 Unitary Savings Analysis To obtain an average annual savings value per pilot participant, the following method was used: - › Establishing the number of laundry loads done per week and the number of loads done in warm water for both the...
AI summary The Unitary Savings Analysis calculates average annual savings per participant by comparing laundry habits between control and treatment groups. The analysis uses data from an annual phone survey, which included questions on cold water washing habits. Outliers were removed to ensure more reliable averages.
6.1.1 Demand-to-Energy Ratio The same demand-to-energy ratio as the one used for all products installed under the regular RDI program component was used to establish peak demand savings, which amounts to 0.233 MW/GWh.
AI summary The demand-to-energy ratio of 0.233 MW/GWh, used in the RDI program, was applied to calculate peak demand savings for products installed under the regular RDI program component.
6.4 Net Savings In total, the CBSM Pilot generated net energy savings of 0.050 GWh at the meter and 0.055 GWh at the generator, and net demand savings of 0.012 MW at the meter and 0.013 MW at the generator, as shown in the table below.
AI summary The CBSM Pilot generated net energy savings of 0.050 GWh at the meter and 0.055 GWh at the generator, along with net demand savings of 0.012 MW at the meter and 0.013 MW at the generator.
Table 31: CBSM Pilot Net Evaluated Energy Savings Parameter Value Energy Savings Total Number of Participants 438 Net Unitary Savings Value (kWh) 114 Interactive Effect Factor 0% Total Net Energy Savings – at meter (GWh) 0.050 Line Loss Fa...
AI summary Table 31 presents the net evaluated energy savings from the CBSM Pilot, including total participants, unitary savings, and both energy and peak demand savings at the meter and generator levels, with adjustments for line loss factors.
QD1b. If you answered "No", what else can Efficiency Nova Scotia do to involve delivery agents? Very knowledgeable Somewhat knowledgeable Not very knowledgeable Not at all knowledgeable QD4a. How knowledgeable are you/your staff regarding...
AI summary This document contains survey questions related to program performance and stakeholder engagement, focusing on Efficiency Nova Scotia's Residential Direct Installation program and the involvement of delivery agents.
Sampling Methodology For the 2014 RDI impact evaluation, 50 on-site visits were conducted with participants. The sampling plan was developed in September 2014 on the basis of the most up-to-date tracking data available. The sample selected...
AI summary The 2014 RDI impact evaluation involved 50 on-site visits, with a sample split between participants with CFLs and LEDs. The sampling plan aimed to balance participants across Delivery Agents but faced challenges due to differing territory sizes. The evaluation also focused on participants with additional RDI measures installed, such as hot water and Embertec devices, due to prior complaints.
On-site Visit Protocol On-site visits were conducted to validate the quantity of installed products documented in the tracking system against the actual situations observed on site. This process served two main purposes: 1) to establish th...
AI summary On-site visits were conducted to verify the installation of energy efficiency products and assess their savings values. Evaluators collected data on lamp types, locations, hot water heating sources, and other parameters to determine installation rates and product removal reasons.
Residential Direct Install Efficiency Nova Scotia Corporation 2014 DSM Evaluation Report
AI summary This document refers to a 2014 DSM Evaluation Report related to the Residential Direct Install Efficiency Nova Scotia Corporation. It highlights the evaluation of demand-side management programs, focusing on efficiency initiatives in residential settings.
E3b. [ASK IF E3a = 1, 2 or 3] You indicated that you were not satisfied with the Embertec smart power controller that was installed under the program. What was the SINGLE most important reason you were not satisfied with this device? [PROB...
AI summary The respondent expressed dissatisfaction with the Embertec smart power controller installed under a program, citing that it did not function as expected as the primary reason for their dissatisfaction.
Behaviour Changes and Washing Habits [B Series] [ASK ALL PARTICIPANTS] - B1. Did your household receive information during the visit from the installer about energy-efficient products? DO NOT READ, CODE ONE ONLY - 1 Yes - 2 No - 98. (Don't...
AI summary The document includes survey questions about whether households received information on energy-efficient products during an installer visit and whether that information influenced their energy usage behavior.
[ASK ALL RESPONDENTS] 98 None These final questions are asked for statistical purposes only. The information collected is strictly confidential. - D1. What type of residence do you live in? [READ RESPONSES 1-7, THEN 96; SELECT ONE RESPONSE...
AI summary This section of the document includes a survey question asking respondents about the type of residence they live in, followed by a reference to the 2014 DSM Evaluation Report. The information collected is for statistical purposes and is strictly confidential.
- B2. Did the information your household received during the visit from the installer change your behavior in terms of how you use energy at home? Information Received 2012 2013 2014 Sample Size 181 159 164 Yes 75% 77% 70% No 18% 11% 21% D...
AI summary The data shows that a majority of households (ranging from 49% to 53%) reported that information received during an installer visit led to behavioral changes in energy use at home, with slight variations across the years 2012 to 2014.
APPENDIX VI CBSM PILOT PARTICIPANT SURVEY RESULTS E1a. You just mentioned that an Embertec smart power controller for audio-visual equipment was installed in your household as part of the program. Do you still have this device installed in...
AI summary The survey question asks whether a participant still has an Embertec smart power controller installed in their household as part of the CBSM pilot program.
B3. How did your behavior change? Behavioral Changes 2014 Pilot Participants Sample Size 85 I turn off my lights now 52% I use cold water to wash my clothes 35% Reduce water consumption/Not wasting water 18% I turn off appliances 12% More...
AI summary The text discusses behavioral changes among 2014 pilot participants, showing that 52% now turn off lights, 35% use cold water for laundry, and 18% reduce water consumption. Satisfaction with washing clothes in cold water is reported as 75% satisfied.
Satisfaction [S Series] S2. BUT DO NOT PROBE FOR MULTIPLE] How did you find out about this program? [DON'T READ; ALLOW MULTIPLE RESPONSE 1. 2. 3. 4. 5. 6. Media advertising Contacted directly by Efficiency Nova Scotia Through a third party...
AI summary This section of the document contains a survey related to customer satisfaction with Efficiency Nova Scotia's programs, focusing on how participants learned about the program, their experience with the Direct Install program, and their level of satisfaction with various factors related to Efficiency Nova Scotia's performance.
FR2a. If you had not participated in RDI, what is the likelihood that you would have installed the same energy-efficient products that you installed through RDI? (Scale 0 to 10) FR2a = Answer x 10% PA1 Score: FR2a FR1. Did you or anyone in...
AI summary This section of the document asks participants about their likelihood of installing energy-efficient products without the RDI program, their prior plans, and the influence of the program on their decisions. It also includes scoring mechanisms to assess free-ridership based on responses.
RENTAL PROPERTIES AND CONDOS SERVICE 2014 DSM EVALUATION EFFICIENCY NOVA SCOTIA CORPORATION 2014 DSM Evaluation Report Final Report February 26, 2015
AI summary This document presents the 2014 Demand Side Management (DSM) Evaluation Report by Efficiency Nova Scotia Corporation, submitted in February 2015. It provides an analysis of the DSM program's performance and outcomes.
Program Component Overview Formerly known as Multi-Unit Residential Buildings (MURB), RP&C offers landlords, tenants and condominium owners direct free-of-charge installation of energy-efficient products in both common-space areas and rent...
AI summary The RP&C program, formerly MURB, provides free installation of energy-efficient products in common areas and rental units. The program is managed by a delivery agent, the Summerhill Group, and is part of Business Energy Solutions.
Table 10: Validated Gross Energy and Peak Demand Savings by Product Ty f Pr du t p e o o c 1 3- W t C t a F L 1 3- W t C t a L O F do t u or 1 4- W t C t a F L 1 4- W t C t a L O F do t u or 2 3- W t C t a F L 2 3- W t C t a L O F do t u o...
AI summary Table 10 presents validated gross energy and peak demand savings by product type, including metrics such as number of units installed, unit savings, and total savings in kilowatt-hours. The table includes various products like CFLs, LEDs, and heat pumps, and provides data on energy efficiency programs.
3.2 Interactive Effects Interactive effects occur on a building's space conditioning systems after the implementation of energy efficiency measures, such as lighting upgrades. These upgrades impact the energy consumption of the heating and...
AI summary This section discusses interactive effects on building space conditioning systems following energy efficiency measures, such as lighting upgrades. The analysis focuses on how replacing incandescent lighting with CFLs or LEDs affects heating and cooling loads and references a 1992 study by ADS for Hydro-Québec using DOE-2 software to simulate scenarios of interactive effects.
[ASK ALL RESPONDENTS] - CS1. How did your company first learn of the programs offered by Efficiency Nova Scotia? [DON'T READ; ALLOW MULTIPLE RESPONSE BUT DO NOT PROBE FOR MULTIPLE] - 1 Media advertising - 2 Someone at Efficiency Nova Scoti...
AI summary The document includes a question about how companies learned of Efficiency Nova Scotia's programs and references a 2014 DSM Evaluation Report. It also contains a placeholder for a picture related to the report.
Factor (READ AND RANDOMIZE) Responses a. The free installation of energy-efficient products offered by the program Response 98 Don't Know 99 Refused b. Information or advice provided by program staff throughout the upgrade process Response...
AI summary The text presents responses to questions about customer experiences with energy efficiency programs, including free installation of products, information provided by program staff, and previous experience with similar programs. The data includes responses such as 'Don't Know' and 'Refused'.
SOLAR 2014 DSM EVALUATION
AI summary The document references a 2014 Demand Side Management (DSM) evaluation, indicating a review or assessment of energy efficiency programs or initiatives undertaken during that year.
Table 1: Validated Gross and Net Savings at the Generator Tracked Gross Savings Gross Savings with Adjustment Ratio NTGR Net Savings Energy Savings 0.0925 GWh 0.0950 GWh 0.65 0.0617 GWh 2014 DSM Evaluation Report
AI summary Table 1 presents validated gross and net savings at the generator, including energy savings of 0.0925 GWh and a net savings of 0.0617 GWh after applying an adjustment ratio of 0.65. The data is referenced from the 2014 DSM Evaluation Report.
LED HOLIDAY LIGHT EXCHANGE 2014 DSM EVALUATION 2014 DSM Evaluation Report
AI summary This document is the 2014 DSM Evaluation Report for the LED Holiday Light Exchange program. It assesses the effectiveness of the program in promoting energy efficiency and reducing electricity consumption.
2.1 Gross Savings The quantity of LED sets exchanged during LHLE events was captured in a tracking sheet. A total of 6,343 sets were distributed at 117 events in 2014. ENSC then used an average unitary savings value to estimate the total e...
AI summary The document discusses the distribution of LED sets during LHLE events in 2014, with a total of 6,343 sets distributed across 117 events. ENSC used an average unitary savings value to estimate the energy and peak demand savings from the program.
Number of Sets Replaced Through LHLE, ENSC offers one set of LED lights in exchange for two sets of traditional incandescent lights—there is a limit of one set of LED holiday lights per person. Consequently, ENSC calculates the unitary sav...
AI summary ENSC's LHLE program exchanges one set of LED lights for two sets of traditional incandescent lights, with a limit of one LED set per person. ENSC assumes customers will replace returned incandescent sets with new LED sets, but this assumption is considered conservative as customers often return more than two sets and may use only the new LED set provided.
2.2 Interactive Effects Interactive effects occur in a home when implemented energy efficiency measures have an impact on the energy consumption of other elements, such as heating and cooling. In the case of LHLE, replacement of old tradit...
AI summary Interactive effects occur when energy efficiency measures, such as LED holiday lights, impact other home energy consumption, like heating. LED lights used indoors during winter can increase heating loads. Hydro-Québec previously disregarded energy savings from indoor LED lights in electrically heated homes. Surveys and calculations show that only external LED lights contribute significantly to energy savings.
Influence of HER on Behavioural Changes Participants in the web-based component of HER were first asked a number of survey questions about energy efficiency behaviours to find out whether they had adopted one or more of them in the 12 mont...
AI summary Participants in the web-based HER program reported low influence ratings (1.6 to 4.3 on a 10-point scale) regarding energy efficiency behaviors. However, analysis showed that some behaviors, such as hanging laundry to dry and reducing shower time, increased after participation in the program, indicating some behavioral changes.
Recommendations Overall, the Econoler team finds that the paper-based component of HER has succeeded in achieving the expected results in terms of changing participants' electricity consumption behaviour. The impact of the web-based compon...
AI summary The Econoler team found that the paper-based component of the Home Energy Report (HER) successfully changed participants' electricity consumption behavior, while the web-based component's impact was harder to evaluate. Specific recommendations are made to optimize HER, in addition to general recommendations for ENSC program components from the 2014 DSM programs.
3.1 Program Design Participants in the paper-based component are provided with paper reports that illustrate their energy usage patterns, compare their energy usage to an anonymous group of similar neighbouring homes and offer tips on how...
AI summary The program provides participants with paper reports and a web portal to compare energy usage with similar homes and offer energy efficiency tips. The objective is to encourage behavioural changes and reduce energy consumption. While initial changes are common, they may erode over time, whereas actions like purchasing energy-efficient products lead to more sustainable savings.
The majority of respondents reported it would have been likely for them to adopt the specific energy-efficient behaviour without HER, as highlighted in the table below.
AI summary Most respondents indicated they would likely adopt energy-efficient behaviors even without the Home Energy Report, as shown in the provided table.
Selection of Participants First, Econoler reviewed the process used to build the two groups. A smaller group was selected by Opower to represent a random sample of the Nova Scotian population, while the other bigger group represented high...
AI summary The document describes the selection process for two participant groups in a program aimed at achieving energy savings. A random sample of 20,000 households was selected, with half in a treatment group and half in a control group. Additionally, 110,000 high electricity users were selected, with 88,000 in a treatment group and 23,000 in a control group. Both groups were analyzed to ensure similarity in attributes such as usage, demographics, and home characteristics.
The information provided by Opower's billing analysis did not allow calculating the peak demand savings associated with the paper-based participants. However, the paper-based component report's observations regarding the measures taken and...
AI summary The analysis of Opower's billing data could not determine peak demand savings for paper-based participants. However, secondary research identified a similar program in Ohio that estimated peak demand savings by dividing annual energy savings by 8,760. Using this method, net peak demand savings were calculated as 3.580 MW at the meter and 3.938 MW at the generator.
Gross Peak Demand Savings Some of the tips selected to calculate energy savings might have also achieved a certain level of peak demand savings. However, additional information is required to estimate the demand savings attributable to eac...
AI summary The document discusses the calculation of gross peak demand savings, noting that while some energy-saving tips may have reduced peak demand, specific data is lacking for the HER component. The Evaluator has decided not to attribute peak demand savings to the HER component for 2014 due to its minimal impact.
99. Refused [THANK AND TERMINATE] [IF REFUSED, ASK "Can we schedule a more convenient time for you to conduct this survey?" [SCHEDULED, IF NECESSARY, FOR:] Behaviour Changes (Series B)
AI summary This section of the document outlines a refusal to participate in a survey and provides an option to reschedule. It also introduces a section on Behaviour Changes (Series B), which likely relates to customer behavior in energy efficiency programs.
BV7. [ASK IF ANSWER TO BL6 OR BV5 ˃ 0] Thinking of the [ANSWER TO BL7 OR BV6] loads of clothes washing your household does in a typical week, approximately how many are washed in cold water, now that you have signed up online for your Home...
AI summary This section of the document includes survey questions related to household energy usage behaviors, focusing on the impact of the Home Energy Report on participants' decisions to turn off their computers at night and the frequency of such actions before and after signing up for the report.
Demographic Characteristics (Series D) [ASK ALL RESPONDENTS] These final questions are asked for statistical purposes only. The information collected is strictly confidential. - D1. What type of residence do you live in? [READ RESPONSES 1-...
AI summary This section of the document collects demographic information about respondents for statistical purposes. It asks about the type of residence and whether the home is owned or rented. A reference to the 2014 DSM Evaluation Report is included.
- B5. I am going to read you a list of energy-efficient behaviours that your household may have adopted. For each one, can you please tell me if your household has adopted it in the last 12 months? Taken Steps to Reduce Home Energy Use 201...
AI summary The survey indicates that 80% of respondents have adopted at least one energy-efficient behaviour in the past year, with common practices including turning off lights and washing clothes in cold water. A smaller percentage have taken more advanced steps, such as using a home power monitor or insulating windows.
Importance of HER in Decision to Wash Clothes in Cold Water 2014 Sample Size Mean Score Average rating: 10= "Extremely influential", 0= "No influence at all" HER influence on decision to wash in cold water 118 1.6 Base: Respondents who was...
AI summary The Home Energy Report (HER) had a modest influence on respondents' decision to wash clothes in cold water, with an average score of 1.6 on a scale from 0 to 10. Most respondents (70%) indicated they would have washed clothes in cold water regardless of the HER.
2014 DSM Evaluation Report
AI summary This document is the 2014 DSM Evaluation Report, which assesses the effectiveness of demand-side management programs in Nova Scotia. It provides an analysis of program performance, outcomes, and impacts on energy efficiency and customer participation.
Non-sampling error Errors arising during the course of all survey activities other than sampling. Non-sampling errors tend to lead to bias in measurements and are very difficult to quantify. Peak demand savings The demand savings that coin...
AI summary The text defines several key terms related to survey errors, energy savings, and statistical measurements. It outlines non-sampling errors, peak demand savings, precision, random sampling error, sample size, tracked savings, and unitary savings, providing context for their application in energy efficiency and demand-side management programs.
BER Instant Rebates Product Types - › CEE T8 lamps › LED troffer - › Wall pack induction lamp fixtures › LED strip lighting - › LED decorative walkways › T5 high bay fixtures - › CEE electronic ballasts › LED high bay fixtures - › High bay...
AI summary The BER Instant Rebates Product Types include various lighting products such as LED troffers, LED strip lighting, and T5 high bay fixtures. These products are now submitted under BER, which aimed for 27.0 GWh of electricity savings and 4.8 MW of peak demand savings in 2014. Energy savings are accounted for under the BNI Efficient Products Rebates.
Table 5: Implementation Status of Recommendations in 2012 and 2013 Executive Summaries Recommendation Status 2012 Recommendations 2012 BER-R1 Analyze product offering to reduce duplicate rebates and program overlapping in the market Implem...
AI summary This table outlines the implementation status of recommendations made in 2012 and 2013 executive summaries, focusing on energy efficiency programs. Most recommendations have been implemented, though some remain partially implemented or are yet to be addressed.
BER Mail-in The review of the BER Mail-in tracking system included both the Excel sheet containing data exported from the DSMDS and the documentation stored in the DSMDS. In 2014, ENSC used only the DSMDS to manage the application process...
AI summary The BER Mail-in tracking system was reviewed, highlighting improvements in the Excel report's structure, including consolidated project information and automated savings calculations. The DSMDS was used in 2014, with savings equations stored in the Screening Tool and copied into the Project Summary tab. The Evaluator recommends using formulas to link total savings to individual measure savings to prevent errors.
BER Instant Rebates BER Instant Rebates is currently not managed through the DSMDS on a day-to-day basis, which means the Evaluator reviewed the compilation of all the products sold at each participating distributor in the Excel sheet prov...
AI summary The BER Instant Rebates program is not managed through the DSMDS, leading to manual review of Excel data provided by ENSC. The Masterlist and Reporting tabs in the Excel sheet contain product details and savings equations, allowing accurate calculation of discrepancies in savings. However, manual verification remains necessary due to a lack of automated validation tools.
5 IMPACT EVALUATION FOR BER MAIL-IN The objective of the 2014 impact evaluation for BER Mail-in was to determine the gross and net energy savings. Both electrical energy and peak demand savings were estimated by analyzing the following par...
AI summary The 2014 impact evaluation for BER Mail-in aimed to assess gross and net energy savings by analyzing parameters such as installation rates, equipment features, and load factors. Interactive effects were considered for lighting measures but not for others. Adjustments and diversity factors were established based on documentation and on-site visits.
ated savings should be removed from the 2014 evaluation. A total of 22 projects were removed for this reason, including 7 projects from the sample and 15 other projects from the final tracking system. The algorithms in the BER – Measure Eq...
AI summary The document discusses the removal of 22 projects from the 2014 evaluation due to inaccurate savings calculations in the BER – Measure Equations Tool. Issues were identified in the algorithms for zero-energy doors, water heating measures, and HVAC hotel occupancy sensors, including incorrect parameter definitions and missing variables.
5.1.1 HVAC Measures A total of 15 on-site visits were conducted for the HVAC measure category this year, but only 13 projects were included in the final analysis because two incomplete projects were removed from the sample. All the complet...
AI summary The document discusses the evaluation of HVAC measures, specifically heat pump installations, based on 13 completed projects out of 15 on-site visits. Adjustments were made to energy and demand savings based on factors like full-load hours and heating capacity, referencing AHRI Standard 210/240.
llect the efficiency of the motor controlled; since this is a variable in the Massachusetts methodology, it will have to be added to the information required in the application package and worksheets. While the calculations presented in th...
AI summary The document discusses the need to collect motor efficiency data for the Massachusetts methodology, which is used for energy efficiency measures. It notes that the current methodologies are limited to HVAC applications and suggests using a tool developed by ENSC for calculating energy and demand savings for VSDs used in other applications. Adjustments were made to the savings calculations for five remaining projects.
5.1.7 Commercial Kitchen Measures Commercial kitchen measures were evaluated by conducting five on-site visits. Only one project validated had its tracked savings values matching the revised values. The most prevalent problem was errors in...
AI summary An evaluation of commercial kitchen measures found issues with tracked savings calculations, including incorrect equations and missing elements. Adjustments were made to the savings of visited projects, increasing energy and demand savings by 15.4% and 45.6%, respectively.
5.1.12 Revised Gross Savings The savings achieved by every category of BER Mail-in measure are presented in Table 13. Both the energy and demand savings were revised by incorporating the adjustments discussed in the previous sections. Usin...
AI summary This section presents revised gross energy and demand savings for the BER Mail-in program, incorporating adjustments from prior sections. The savings are calculated using a line loss factor of 1.068 and a diversity factor, resulting in 12.902 GWh of energy savings and 1.988 MW of peak demand savings at the meter, with higher values at the generator.
Table 13: Evaluation Results – Revised Gross Savings – BER Mail-in Category of Measure HVAC Lighting Refrige ration Motors and VSDs Compressed Air Agricultural Tracking System Savings Tracked Energy Savings (GWh) 2.837 4.588 0.097 1.269 0....
AI summary Table 13 presents evaluation results for revised gross savings from the BER Mail-in program, detailing energy and demand savings across various categories of measures such as HVAC, lighting, and compressed air. It includes metrics like tracked energy savings, adjustment ratios, and line loss factors for both energy and peak demand savings.
(Continued) Category of Measure Kitchen Water Heating Laundry Solar LED Promotion Total Energy Savings Total Gross Energy Savings – at Meter (GWh) 0.376 0.057 0.003 0.005 2.765 12.902 NTGR 0.75 0.75 0.75 0.75 1.00 - Total Net Energy Saving...
AI summary Table 15 compares energy and peak demand savings from the mail-in rebate approach with those calculated in the 2014 tracking system, presenting data across categories like kitchen, water heating, and solar, along with metrics such as gross and net energy savings and peak demand savings.
6.1.10 Revised Gross Savings Energy and demand savings associated with the instant rebate approach were calculated using the unitary savings values revised under this evaluation. Savings at the generator were also calculated using a line l...
AI summary The instant rebate approach's energy and demand savings were calculated using revised unitary savings values. Total energy savings were 18.002 GWh at the meter and 19.209 GWh at the generator, with peak demand savings of 4.260 MW and 4.545 MW respectively.
Table 20: Evaluation Results – Gross Energy and Peak Demand Savings for Instant Rebates Products with Unitary Savings Values Ca Pr du t te o c g or y H P- T 8- 3 2 W La m p s R W -T 8- 2 8 W La m p s R W -T 8- 2 5 W La m p s 1- La m p H P...
AI summary Table 20 presents evaluation results for gross energy and peak demand savings from instant rebate products with unitary savings values, including data on various lamp and ballast products and their associated energy savings.
Table 21: Evaluation Results – Gross Energy and Peak Demand Savings for All Other Instant Rebates Products Pr du Ca t te o c g or y T 5 d T 8 an H ig h Ba s y D Do L E l ig h ts n w O t he r In do D La L E or m p s O t do u or L D W E l lp...
AI summary Table 21 presents evaluation results for gross energy and peak demand savings from all other instant rebates products. It includes various categories and totals, such as the number of units in the program, with figures ranging from 3,087 to 23,115,7.
Table 25: Evaluation Results – Net Energy and Peak Demand Savings for Instant Rebates Products with Unitary Savings Values Ca f Pr du te t g or o o c y H P- T 8- 3 2 W la m p s R W -T 8- 2 8 W la m p s R W -T 8- 2 W 5 la m p s 1- La m p H...
AI summary Table 25 presents the evaluation results of net energy and peak demand savings for instant rebate products with unitary savings values, including various lamp and ballast products, lighting occupancy sensors, and motors. The table provides data on gross energy savings and efficiency factors for each product category.
Table 26: Evaluation Results – Net Energy and Peak Demand Savings for Other Instant Rebates Products Ca f te Pr du t g or y o o c T 5 d T 8 an H ig h Ba y s D Do L E l ig h ts w n O t he r In do D La L E or m p s O t do u or L D W E l lp k...
AI summary Table 26 presents evaluation results for net energy and peak demand savings from Other Instant Rebates Products. It includes metrics such as total gross energy savings, high bay savings, and other categories, with numerical values provided for each category.
› your staff's overall knowledge of these products? 2014 DSM Evaluation Report
AI summary The document references a 2014 DSM Evaluation Report and asks about the staff's knowledge of specific products. It appears to be related to the evaluation of demand-side management programs.
› the number of LED downlights sold in your store? › your staff's overall knowledge of these products? 2014 DSM Evaluation Report
AI summary The text references a 2014 DSM Evaluation Report and includes questions about the number of LED downlights sold and staff knowledge of products. It does not provide specific details or discussion on the themes of the proceeding.
Yes S4. Finally, do you have any suggestions to improve the program? No S2. The program support and communications S3. The rebate processing, tracking and reporting S1. The overall program Aspects of the program a. Score b. Reason Please s...
AI summary The text presents a series of questions related to the Business Energy Rebates (BER) program, focusing on customer satisfaction, program effectiveness, and the influence of incentives on product choices. Respondents are asked about their satisfaction with various aspects of the program, the adequacy of incentives, and the impact of the program on customer behavior.
Firmographics [F Series] These final questions are asked for statistical purposes only. The information collected is strictly confidential. - F1. What is the main activity of your company? [DO NOT READ—BUT CONFIRM WITH RESPONDENT THAT THE...
AI summary The text outlines a series of statistical questions for a regulatory proceeding in Nova Scotia, focusing on company activities, employment numbers, and organizational structure. It includes a reference to the 2014 DSM Evaluation Report and mentions some acronyms related to the process.
2014 DSM Evaluation Report Normal week/holidays lighting operation schedule (hours per day): Please fill the table below for each lighting schedule reported by the site contact as usage could vary for each section of the facility. Use addi...
AI summary The text provides a template for reporting lighting operation schedules in a 2014 DSM Evaluation Report, requesting detailed information on usage patterns across different sections of a facility.
2014 DSM Evaluation Report
AI summary The 2014 DSM Evaluation Report provides an assessment of demand-side management programs in Nova Scotia, focusing on their effectiveness, implementation, and impact on energy efficiency and customer participation.
Motors and Drives: Collect the information in the table below if motors and drives measures were installed. Use on-site observation and contact declaration. Use additional sheets if required. The information collected will then be compared...
AI summary The text provides instructions for collecting information on motors and drives measures, including the use of on-site observation and contact declaration. It mentions that this information will be compared with data in a tracking sheet by Econoler, and it requests the recording of manufacturer and model numbers along with technical details.
Refrigeration: Collect the information in the table below if refrigeration measures were installed. Use on-site observation and contact declaration. Use additional sheets if required. The information collected will then be compared with th...
AI summary The document provides instructions for collecting information on refrigeration measures installed, including manufacturer and model numbers, to be compared with tracking sheet data by Econoler.
Laundry: Collect the information in the table below if commercial laundry measures were installed. Use on-site observation and contact declaration. Use additional sheets if required. The information collected will then be compared with the...
AI summary The text provides instructions for collecting information on commercial laundry measures, including manufacturer and model numbers, technical data, and details to be compared with a tracking sheet by Econoler.
2.2.3 Project File Review, On-site Visits and Interviews By the end of 2014, 25 on-site visits and a full technical review of project documentation was carried out for a sample of the 2014 Custom Retrofit participants. However, since some...
AI summary By the end of 2014, 25 on-site visits were conducted for a sample of Custom Retrofit participants to validate technical specifications and assess spillover effects. Due to errors in the tracking sheet, only 22 visits were used. The visits were carried out by Equilibrium Engineering and included interviews and facility assessments.
3.1 Participation in Custom Retrofit In 2014, Custom Retrofit saw a total of 100 projects implemented, compared to 134 projects in 2013, 155 projects in 2012 and 159 projects in 2011. Figure 2 illustrates that the number of projects implem...
AI summary In 2014, Custom Retrofit implemented 100 projects, a decline from previous years. This decrease is partly due to the offloading of lighting-only projects to other programs like Business Energy Rebates (BER), and may also be attributed to lower targets set by ENSC.
Table 4: Implementation Status of Recommendations in 2012 and 2013 Executive Summaries Recommendation Status 2012 Recommendation 2012 Custom-R1 Consider diverting or assigning a proportion of the simple lighting retrofit projects to other...
AI summary Table 4 outlines the implementation status of recommendations from 2012 and 2013 executive summaries, focusing on improvements in energy efficiency programs, such as retrofit projects, diversity factor calculations, and the use of measurement and verification (M&V) procedures. Many recommendations have been fully or partially implemented, with ongoing efforts in some areas.
3.4.1 DSMDS Report In 2014, the DSMDS was used to generate the preliminary tracking report for sampling purposes, which contained three tabs: (1) Evaluation Report; (2) Measures by Project; and (3) Measures by Category. However, when gener...
AI summary In 2014, the DSMDS was used to generate a preliminary tracking report with three tabs, but encountered a technical issue when generating the final report. It is assumed that once resolved, the final report will resemble the 2014 version, which was reviewed by the Evaluator.
3.4.2 Online DSMDS In addition to the tracking report provided, the Evaluator reviewed the contents and structure of ENSC's DSMDS. Since all current Custom Retrofit projects are now being tracked online through this tool, the Evaluator fel...
AI summary The Evaluator reviewed ENSC's Demand-Side Management Data System (DSMDS), focusing on the Project Summary and Measures and Documents tabs, to assess accuracy and identify areas for improvement, as all current Custom Retrofit projects are now tracked online through this tool.
Project Summary The Project Summary tab of the DSMDS contains all the relevant information required for a quick overview of any Customer Retrofit project. Information within this tab includes the project information, notes, milestone dates...
AI summary The Project Summary tab in the DSMDS includes key information for Customer Retrofit projects, such as project details, budget, savings summaries, and client contact data. ENSC added a section to document free-ridership screening and facility details, improving data management and enabling future program adjustments.
4.1.1 Awareness and Participation The ENSC website or the Internet was the main means by which participants found out about Custom Retrofit. Other sources of awareness were energy managers, ENSC staff, word of mouth, trade magazines, Nova...
AI summary The ENSC website and the Internet were the primary sources of awareness for the Custom Retrofit program. Additional awareness came from energy managers, ENSC staff, word of mouth, trade magazines, Nova Scotia Power, and the provincial government.
Table 6: Factors Influencing Participants' Decisions Importance of Factors in Influencing Decision 20 12 2013 2014 to Implement Energy Efficiency Measures Sample Size Mean Sample Size Mean Sample Size Mean Mean (0=Not at all important, 10=...
AI summary Table 6 outlines the importance of various factors influencing participants' decisions to implement energy efficiency measures. Financial incentives and on-bill financing are highly valued, while previous experience with programs and technical assistance are also significant considerations.
4.1.3 Satisfaction with Custom Retrofit Nearly all participants were satisfied with Custom Retrofit overall. Several other program aspects generally received good ratings, with the majority of participants offering good ratings for the ini...
AI summary Nearly all participants were satisfied with the Custom Retrofit program, with positive feedback on eligibility confirmation, project implementation, incentive amounts, and savings verification. However, satisfaction was lower regarding rebate delays and the paperwork required, with an average of 11 weeks to receive the rebate or incentive.
5.1.1 Adjustment Methodology for Custom Retrofit The following sub-sections describe the verification procedure used by the Econoler team when evaluating the gross savings for each Custom Retrofit project. For the 2014 Evaluation, projects...
AI summary The document outlines the adjustment methodology used by the Econoler team to verify gross savings for Custom Retrofit projects, particularly during the 2014 Evaluation. Projects were split into lighting and others to create individual adjustment factors and minimize the impact of one measure type on total tracked savings.
Lighting Retrofit Projects In 2014, 36 of the 100 projects included lighting retrofit measures, which accounted for approximately 24 percent of the verified energy savings. In order to paint an accurate picture of Custom 2014, 11 of the 25...
AI summary This section discusses the verification process for lighting retrofit projects in 2014, highlighting factors such as unitary wattage, installation rates, hours of operation, diversity factors, and M&V procedures. These factors were used to calculate energy savings and ensure accuracy in the verification process.
Other Energy Efficiency Projects The remaining 2014 Custom projects were grouped into a second category simply named "Other Energy Efficiency Projects", and it included a variety of measures, such as HVAC upgrades, motor replacements, cont...
AI summary The 'Other Energy Efficiency Projects' category includes diverse energy conservation measures, such as HVAC upgrades and motor replacements. The weighted adjustment ratio was calculated based on a detailed review of project documentation and on-site verification of equipment installation and operation parameters.
5.1.2 Adjusted Gross Savings The final tracked gross energy and peak demand savings results for Custom 2014 were reviewed and adjusted by the Evaluator. All adjustments were made following a comparison of the claimed project savings with t...
AI summary The final tracked gross energy and peak demand savings results for Custom 2014 were reviewed and adjusted by the Evaluator based on a sample of 22 projects, following the exclusion of three projects from the original sampling plan.
Adjustments to Lighting Retrofit Projects The adjustment factors for lighting retrofits were determined through the analysis of the information obtained during the 10 on-site visits for lighting retrofit measures. The overall energy and pe...
AI summary Adjustments to lighting retrofit projects were determined based on 10 on-site visits, identifying discrepancies in operation hours, fixture counts, and interactive effects. Energy savings adjustment factor was set at 1.009, and peak demand ratio at 1.142. Recommendations include standardizing M&V plans and focusing verification on larger projects.
Adjustments to Other Custom Retrofit Projects The remaining Custom projects in the sample are classified as "other" Custom Retrofit projects for this report. The tracked savings for each project were adjusted using a similar methodology as...
AI summary The report discusses adjustments to energy and peak demand savings for 'other' Custom Retrofit projects, noting minor discrepancies in energy savings calculations and significant errors in documentation. An overall energy savings adjustment factor of 0.991 was applied, while a peak demand adjustment factor of 0.686 was used, influenced by differences in methods for estimating peak coincidence factors.
Continued success in the delivery of non-lighting Custom projects will require continued improvement to the application of M&V practices. In a number of cases, M&V activities were not summarized or documented in the DSMDS. More specificall...
AI summary The document highlights the need for improved M&V practices in non-lighting Custom projects, noting that only 13 out of 22 sampled projects included measurements. Savings for the 2014 Custom Retrofit are estimated at 21.279 GWh at the meter and 22.547 GWh at the generator, with peak demand savings of 1.619 MW and 1.716 MW respectively.
Table 11: Net Energy and Peak Demand Savings for Custom Retrofit Custom Retrofit Energy Savings Total Gross Energy Savings – at Meter (GWh) 21.279 NTGR 0.90 Total Net Energy Savings – at Meter (GWh) 19.151 Line Loss Factor 1.060 Total Net...
AI summary Table 11 presents the net energy and peak demand savings for a custom retrofit, including total gross and net energy savings at both the meter and generator levels, along with line loss factors and peak demand savings figures.
6.1 EMIS Review A newly introduced Custom Retrofit sub-component, EMIS was first undertaken in 2013 as a pilot. The main goal of EMIS is to assist industrial clients in making real-time decisions about their process using energy consumptio...
AI summary The EMIS program, introduced in 2013, helps industrial clients make real-time energy decisions using metered system data. A review found that only two of four 2014 projects were generating savings, while others were still in implementation. The program manual and supporting documentation are well-defined, providing clear guidance for participants and consultants.
6.2 Existing Building Commissioning Review As mentioned previously, EBC was one of the Custom Retrofit components newly introduced in 2014. The goal of this component is to achieve energy and peak demand savings through the appropriate and...
AI summary The Existing Building Commissioning (EBC) program, introduced in 2014, focuses on achieving energy and peak demand savings through low-cost and no-cost measures. An evaluator found that EBC is cost-effective, generating approximately 850 MWh in savings, though project documentation quality varied significantly.
6.4 Overall Savings for Custom Retrofit The following table presents the total tracked and evaluated savings for Custom Retrofit as well as its two sub-components, EBC and EMIS.
AI summary This section introduces a table that outlines the total tracked and evaluated savings for the Custom Retrofit program, along with its sub-components, EBC and EMIS.
This Appendix presents all recommendations made by the Evaluator throughout the report as well as the sections from which the recommendations originated. Sections Recommendations 5 Require EMIS service providers to track and present saving...
AI summary This section recommends that EMIS service providers use the IPVMP protocol to track and present savings, ensuring detailed M&V plans and verification by ENSC to address weaknesses in project implementation and ensure accurate savings tracking.
Free-Ridership [FR Series] According to our information, through its participation in the Custom Program, your business or organization received incentives to implement electrical energy-saving projects in one or several facilities or buil...
AI summary This section of the Free-Ridership survey asks participants whether they had plans to implement energy efficiency measures before joining the Custom Program and assesses the likelihood they would have taken those actions without the program's incentives.
FR2b. installed standard equipment instead of energy-efficient equipment? Response 98 Don't Know 99 Refused FR2c. implemented the energy efficiency measures that you implemented through the program, but at a later date? Response 98 Don't K...
AI summary The text discusses survey questions related to energy efficiency programs, specifically focusing on whether respondents would have implemented energy efficiency measures without the program and the timing of such implementation. It includes response options and follow-up questions for detailed answers.
Barriers to Actions and Recommendations [B Series] - B1. Did you face any challenges or barriers when implementing energy efficiency measures through the Custom Program? - 1. Yes - 2. No (SKIP TO B7) - 98. (Don't know) (SKIP TO B7) - 99. (...
AI summary This section of the proceeding asks respondents about challenges faced in implementing energy efficiency measures through the Custom Program, including approval delays, measurement and verification requirements, and payback time frames. It also seeks suggestions for improving the program's various components and processes.
- P4. What was the SINGLE most important reason your company or organization chose to participate in the Custom Program?
AI summary The question asks for the most important reason a company or organization chose to participate in the Custom Program, indicating a focus on motivations for program participation.
P6. Some companies work with a design professional, project architect, engineer, equipment contractor, or a utility account manager as part of the project design phase. Who do you feel was more responsible for specifying the measures to in...
AI summary The text inquires about responsibility for specifying measures to install through the Custom Program, involving various professionals such as design professionals, project architects, engineers, equipment contractors, or utility account managers.
MEAN VALUE OF: (FR2a ; FR2b) IF PRE-SCREENING: 0% FR1. Before participating in Custom, did your company have plans to implement the specific energy efficiency measures that were implemented through the program? IF 1. Yes: Use FR1a IF 2. No...
AI summary The text outlines a series of questions related to energy efficiency program participation, focusing on whether companies had pre-existing plans for energy efficiency measures and how financial incentives influenced their decision to implement them.
CUSTOM NEW CONSTRUCTION 2014 DSM EVALUATION 2014 DSM Evaluation Report
AI summary This document is titled 'CUSTOM NEW CONSTRUCTION 2014 DSM EVALUATION' and refers to a 2014 Demand Side Management (DSM) Evaluation Report. It appears to be a regulatory proceeding document related to energy efficiency programs.
3.2 Tracking System In 2014, ENSC tracked Custom NC projects through the demand-side management data system (DSMDS) and generated tracking reports in the form of an Excel workbook for evaluation purposes. The following two sections present...
AI summary In 2014, ENSC used the DSMDS to track Custom NC projects and generated Excel-based tracking reports for evaluation. The section discusses the Evaluator's review of these reports and the DSMDS system.
3.2.2 Demand-side Management Data System Beyond the review of the tracking report provided, the Evaluator reviewed the contents, and structure of ENSC's Demand-Side Management Data System. Since all current Custom NC projects are now being...
AI summary The Evaluator reviewed the Demand-Side Management Data System (DSMDS) used by ENSC to track Custom NC projects. The system contains eleven tabs, three of which were found to contain the necessary information for on-site evaluations and verifying tracked savings.
Project Summary The Project Summary tab of the DSMDS contains all of the relevant information required for a quick overview of any Customer NC project. Information within this tab includes the project information, notes, milestone dates, p...
AI summary The Project Summary tab in the DSMDS provides an overview of Customer NC projects, including budget, savings, and contact information. ENSC added sections for free-ridership screening and facility details to improve data collection and program offerings.
4.1 Gross Savings Under the 2014 impact evaluation, the Evaluator calculated the gross energy and peak demand savings for all the nine sampled projects in accordance with the specifics of each project. These results were then compared to t...
AI summary The 2014 impact evaluation calculated gross energy and peak demand savings for nine sampled projects, compared results with tracking sheets, and applied adjustment factors. Weighted averages were used to determine overall adjustment factors for Custom NC projects, which were then used to adjust gross savings.
4.1.1 Adjustment Methodology Nine on-site visits were conducted with the intent of confirming that the tracked savings recorded in the DSMDS were appropriate and accurate using a similar approach than the one used in 2013. The on-site visi...
AI summary The document outlines the adjustment methodology used to verify the accuracy of energy savings recorded in the DSMDS through on-site visits. Key factors considered include baseline assumptions, equipment specifications, installation rates, hours of operation, diversity factors, and M&V procedures for NCEM projects.
4.1.3 Adjusted Gross Savings The 2014 gross energy savings presented in the ENSC tracking sheet for each project visited were individually revised according to the adjustments identified by the Evaluator. Adjustment calculations were perfo...
AI summary The 2014 gross energy savings for the Custom NC program were adjusted based on on-site evaluations. Adjustments were made to nine of thirteen projects, including a significant adjustment for a LEED® NC certified building and another for incorrect lighting installation. Peak demand savings were difficult to evaluate due to limited information in simulation reports.
Calculation of Adjusted Gross Savings To calculate the adjustment ratio, the Evaluator used eight of the nine projects reviewed. The LEED project savings that had not been adjusted to take into account the LEED energy performance requireme...
AI summary The document discusses the calculation of an adjustment ratio for gross energy and peak demand savings, excluding a LEED project due to its unique certification requirements. The adjustment ratios calculated were 0.982 for energy savings and 0.976 for peak demand savings, based on eight projects. The savings at the meter and generator levels are also detailed, with specific values provided for Custom NC.
Sampling Methodology The Evaluator received the first Custom NC tracking sheet in October 2014. At that point in time the tracking sheet contained only six projects, and therefore comprised the entire available sample. In November a second...
AI summary The Evaluator received tracking sheets for Custom NC projects in October and November 2014. Initially containing six projects, the sample was expanded to nine projects by November. Since the mandated sample size of ten was not met, all nine projects were used as the sample population without applying decision criteria.
Table 5: Final Sample for Custom NC 5 Description Number of Projects Expected Gross Energy Savings at the Meter (GWh/yr) Expected Gross Demand Savings at the Meter (MW) Sample 9 3.977 1.343 Final Tracked Projects 13 6.696 2.462 On-site Vis...
AI summary Table 5 provides a comparison between a sample and final tracked projects under the Custom NC5 initiative, showing energy and demand savings. The On-site Visit Protocol section outlines procedures for site visits.
The Evaluator reviewed the protocol used in 2013 and deemed it appropriate for the 2014 impact evaluation, with the exception of minor adjustments. These adjustments included a space allocated for a list of the project's key variables, and...
AI summary The Evaluator reviewed and adjusted the 2013 protocol for the 2014 impact evaluation, incorporating a space for key variables and a free-ridership questionnaire checkbox. The protocol included tools like the on-site form, DSMDS files, and the free-ridership questionnaire to collect project details, building systems data, and utility bill information for evaluation.
On-Site Visit Protocol 1. General Information Site Visit Date: Project ID: Project Type: Project Status: Project Name: Address: Contact Name: Contact Title: Contact Phone: Email: List of people met during the visit: Type of building: Comme...
AI summary This document outlines the On-Site Visit Protocol, providing a structured format for gathering information during facility visits. It includes sections for general information, key project variables, and facility operation schedules, allowing for detailed data collection on building types, occupancy patterns, and operational schedules.
EXECUTIVE SUMMARY This report presents the results of the 2014 evaluation of Business Energy Solutions (BES), which is the sole component of the Direct Installation program. The 2014 evaluation was based on 55 on-site visits, including fiv...
AI summary The 2014 evaluation of Business Energy Solutions (BES), the sole component of the Direct Installation program, involved 55 on-site visits, surveys of participants, and a unitary savings review to assess program effectiveness.
2.2.1 On-site Visits In October and November 2014, Equilibrium Engineering conducted 50 on-site visits after project implementation. These visits were meant to verify the implementation status of the measures against the data found in the...
AI summary Equilibrium Engineering conducted 50 on-site visits in 2014 to verify the implementation of energy efficiency measures and calculate installation rates. Five additional visits were conducted with Delivery Agents to validate the turnkey implementation process, using a different protocol.
3.1 Participation in BES As Figure 2 illustrates, the participation in BES has declined since 2012, but has remained rather stable compared to 2013, all BES initiatives considered. This decrease after 2012 can be partially explained by the...
AI summary Participation in the Building Efficiency Program (BES) has declined since 2012, with a significant drop after the removal of the Commercial Direct Install (CDI) component. The number of participants remained relatively stable from 2012 to 2014, with varying numbers implementing lighting and non-lighting measures, MURB Common Area measures, and participating in the LED Blitz pilot.
Lighting Measures Tracking Report The lighting measures tracking report presents information regarding the participants and their calculated gross energy savings. It includes each participant's detailed contact information and the details...
AI summary The Lighting Measures Tracking Report details participant information, project tracking, and energy savings data. It includes contact details, measure identification numbers, and key parameters for validating energy savings. The report also highlights improvements in data collection, such as increased documentation of heating energy sources.
3.3 On-site Visit during the Installation Process Similar to 2013, five visits were conducted with DAs as part of the evaluation process. Two visits with two different DAs were conducted during the initial on-site assessment of a facility....
AI summary The document details on-site visits conducted by DAs during the installation process of energy efficiency measures. Initial assessments evaluated energy savings opportunities and lighting measures, while installation visits identified products used and encountered issues. Recommendations include adding a lighting analysis and providing clearer information on replacement lamps.
Table 7: Specific Barriers to Participation 2012 2013 2014 Specific Barrier Most Important Barrier (#) Second Most Important Barrier (#) Most Important Barrier (#) Second Most Important Barrier (#) Most Important Barrier (#) Second Most Im...
AI summary Table 7 outlines specific barriers to participation in the Building Efficiency Program (BES) from 2012 to 2014. Key barriers include problems with contractors, lack of financing, and delays in project approval, among others, with varying frequencies across years.
Unitary Savings for LED Lamp Replacements As for the relamping measures, the savings in the 2014 tracking system are solely based on the wattage differences between the existing and the new lamp types, which is similar to the procedure use...
AI summary The document discusses the calculation of unitary savings for LED lamp replacements, emphasizing the importance of considering the ballast factor and ballast efficacy factor (BEF) in determining system wattage. It notes that existing databases are not sufficient for LED systems and proposes an equation to estimate system wattage when LED tubes are used.
Custom Measures Implementing one of last year's recommendations made by the Evaluator, ENSC stopped approving projects involving custom measures. These measures are now claimed in a regular category which allows disclosing more information...
AI summary ENSC has stopped approving projects involving custom measures following a recommendation from the Evaluator. Previously approved custom measure projects from 2013 were implemented in 2014 and documented in the tracking system. Savings from this category are claimed without adjustment due to the small number of measures this year.
Hours of Operation No light metering study was conducted for the 2014 impact evaluation. Therefore, the self-declaration ratio of 0.98, established by the Evaluator in 2012 by conducting a metering study, is used to adjust the hours of ope...
AI summary No light metering study was conducted for the 2014 impact evaluation, so the 2012 self-declaration ratio of 0.98 is used to adjust hours of operation. This ratio remains valid as the methodology for reporting hours has not changed, except for exit signs, which are lit 24/7.
Diversity Factor Based on information provided by ENSC, the peak period for electricity demand in Nova Scotia occurs weekdays from 7 a.m. to 12 p.m. and 4 p.m. to 11 p.m. in December, January and February. Similar to evaluations completed...
AI summary The document discusses the determination of diversity factors for energy efficiency measures in Nova Scotia, including lighting and heat pump installations. It outlines how peak demand periods are identified and how diversity factors are calculated based on operational schedules and building types.
Peak Demand-to-Energy Ratio Peak demand savings are calculated using an on-peak demand-to-energy ratio of 0.177 MW/GWh. This ratio was established based on a weighted-average ratio of modelled system-coincident peak demand savings and ener...
AI summary Peak demand savings are calculated using a ratio of 0.177 MW/GWh, established by Navigant in the 2013-2015 DSM Plan. This ratio is based on a weighted average of modelled system-coincident peak demand and energy savings for measures supported by the Building Efficiency Program in 2014.
Table 16: Evaluation of Gross Energy and Peak Demand Savings Associated with BES Lighting Measures LEC )s Fluoresc ent T8 F N4 - 4 - 1 Category of Product Reballast (linear) Other Reballast Other CFLs Custom Т5 Exit Signs Metal Halide Othe...
AI summary Table 16 evaluates the gross energy and peak demand savings associated with BES lighting measures, including various product categories and their corresponding savings metrics. The table includes initial and calculated tracked savings, demand savings, and adjustments based on factors like ballast, installation rates, and line loss.
Table 18: Evaluation of Gross Energy and Peak Demand Savings Associated with RP&C Common Areas (CFLs) Category of Product 13-Watt CFL 14-Watt CFL 23-Watt CFL 14-Watt Dim. CFL 16-Watt Dim. CFL 3-Watt LED Chandelier 10-Watt LED A lamp 9-Watt...
AI summary Table 18 evaluates the gross energy and peak demand savings associated with the installation of various lighting products in RP&C common areas, including CFLs and LEDs. The table provides data on the number of units installed, energy savings, peak demand savings, and factors such as line loss and diversity.
5.3.4 Revised Gross Savings for LED Blitz The annual gross savings calculated for each category of product installed through LED Blitz are presented in [Table 20](#page-123-0) for lighting measures and in [Table 21](#page-124-0) for non-li...
AI summary The document discusses revised gross savings for the LED Blitz program, presenting energy and peak demand savings at both the meter and generator levels. Calculations were based on unitary savings values and a line loss factor provided by Nova Scotia Power.
Table 20: Evaluation of Gross Energy and Peak Demand Savings Associated with LED Blitz Lighting Measures Category of Product LED A Lamp 8W LED A Lamp 12W LED MR16 7W LED GU10 5W LED BR30 11W LED BR30 13W LED BR40 11W LED BR40 18W LED PAR20...
AI summary Table 20 evaluates the gross energy and peak demand savings from LED Blitz Lighting Measures across various product categories. It details the number of units installed, energy savings in GWh, line loss factors, and peak demand savings in MW for different LED lighting products.
Table 21: Evaluation of Gross Energy and Peak Demand Savings Associated with LED Blitz Non-lighting Measures Category of Product Vending Machine Misers Faucet Aerators Pre-Spray Valves Total for All LED Blitz Measures Number of Units 60 1...
AI summary Table 21 evaluates the energy and peak demand savings from non-lighting measures under the LED Blitz program. It details the number of units installed, energy savings, and peak demand savings across categories like vending machine misers, faucet aerators, and pre-spray valves. The total gross energy savings at the generator level is 0.653 GWh, with peak demand savings of 0.135 MW.
5.4.1 Interactive Effects for BES Lighting Measures Installing new efficient lighting products to replace old lighting fixtures inside a conditioned space brings out an increase in the heating load during winter, as less waste heat from li...
AI summary Replacing old lighting fixtures with efficient ones increases winter heating loads but decreases summer cooling loads. The weighted interactive effect coefficient of -5.4% was calculated based on an ADS study from 1992 and data from 44 on-site visits for the 2014 BES lighting evaluation.
The following table compares the energy and peak demand savings established by this evaluation and those calculated in the 2014 tracking system.
AI summary The text presents a table comparing energy and peak demand savings from this evaluation with those from the 2014 tracking system, indicating a focus on energy efficiency and demand-side management metrics.
The figure below illustrates the methodology used to calculate the internal spillover level. SO1. Since the time that you participated in BES, has your company purchased and installed any additional energy-efficient products on its own for...
AI summary The text outlines a methodology for calculating internal spillover levels by assessing whether companies installed additional energy-efficient products after participating in the BES program and whether their experience influenced these decisions.
Table 36: Number of On-Site Visits Performed for Lighting and Non-Lighting Measures Measure Type Tracked Gross Savings (MWh) % of Total Tracked Savings Square Root of Tracked Savings % of Total of Square Root of Tracked Savings Actual Samp...
AI summary Table 36 presents the number of on-site visits performed for lighting and non-lighting measures, highlighting that lighting measures account for the majority of tracked energy savings and sample size compared to non-lighting measures.
3.1.5 At-meter Peak Demand Savings Finally, the Evaluator estimated peak demand savings at the meter by using the data collected on demand savings, the market size of electric motors in Nova Scotia, the noncompliance rate and a diversity f...
AI summary The Evaluator estimated peak demand savings at the meter using data on demand savings, market size of electric motors, noncompliance rate, and a diversity factor of 85 percent. The average of 30 HP and 75 HP electric motors was used for calculations, leading to an estimated total peak demand savings of 0.145 MW.
3.3.5 At-meter Peak Demand Savings The Evaluator estimates that the introduced regulation on three-phase dry-type transformers generated 0.072 MW in peak demand savings in Nova Scotia in 2014.
AI summary The Evaluator estimates that the introduced regulation on three-phase dry-type transformers generated 0.072 MW in peak demand savings in Nova Scotia in 2014.
The Econoler team estimates that 0.160 MW was saved at the meter in Nova Scotia in 2014 as a result of introducing the regulation on large air conditioners and heat pumps. A diversity factor of 0 percent was applied to air conditioners sin...
AI summary The Econoler team estimates that 0.160 MW was saved in Nova Scotia in 2014 due to regulations on large air conditioners and heat pumps. Diversity factors of 0% and 98% were applied to air conditioners and heat pumps, respectively, based on evaluations and on-site visits.
3.9.6 At-meter Peak Demand Savings Peak demand savings are calculated using a demand-to-energy ratio of 0.158 MW/GWh. This ratio was established based on a weighted-average ratio of modelled system-coincident peak demand savings and energy...
AI summary Peak demand savings are calculated using a demand-to-energy ratio of 0.158 MW/GWh, established based on a weighted-average ratio from modelled system-coincident peak demand savings and energy savings for a projected deployment of measures supported by Instant Savings in 2014, as developed by Navigant in the 2013-2015 DSM Plan.
Table 49: Peak Demand Savings Associated with the Introduction of Incandescent Bulbs Standards in the Nova Scotia Market Product Class Demand-to Diversity Total Peak Demand Savings Energy Ratio Factor at Meter for 2014 (MW) (%) (MW) Incand...
AI summary Table 49 presents peak demand savings from incandescent bulb standards in Nova Scotia. The data shows a total peak demand savings of 2.611 MW for incandescent bulbs (75 - 100W). Section 3.10 discusses LED street lighting, indicating a shift towards more energy-efficient lighting solutions.
Table 53: Demand Savings Associated with the Introduction of the LED Street Lightings in the Nova Scotia Market Product Class Number of Lighting units Replaced in 2014 Demand Savings (W/unit) Diversity Factor (%) Total Peak Demand Savings...
AI summary Table 53 presents demand savings from the introduction of LED street lighting in Nova Scotia in 2014, showing 12,052 units replaced, with a demand savings of 57 W/unit and total peak demand savings of 0.689 MW.
Peak demand savings are calculated using an on-peak demand-to-energy ratio of 0.257 MW/GWh. This ratio was established based on a weighted-average ratio of modelled system-coincident peak demand savings and energy savings for a projected d...
AI summary Peak demand savings are calculated using a ratio of 0.257 MW/GWh, based on a weighted average from modelled system-coincident peak demand and energy savings projections in Nova Scotia. The Evaluator estimates that the introduced regulation generated 0.202 MW in energy savings in 2014.
E-7E1 (NSPI) RIR-1 to RIR-47
95 passages
2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-1: 2 3 Reference: EfficiencyOne, Appendix A – 2016-2018 DSM Resource Plan - Page 21, Line 17: 4 5 Please provid...
AI summary EfficiencyOne (E1) responds to NSPI's request for advertising expenditure data from 2012-2014 and 2015-2018 budgets, stating that 2016-2018 DSM budgets depend on the UARB's decision on the DSM Resource Plan. The response includes a table of historical and projected advertising costs.
NON-CONFIDENTIAL 1 2 b) The media strategy is developed using research to identify target audiences and 3 understand their media consumption habits. ENS is not able to provide the specific 4 studies as they are subscription-based. Sources...
AI summary The text outlines ENS's media strategy, emphasizing research-driven audience targeting and the dominance of television in influencing Atlantic Canadians. Television is prioritized due to high recall and time spent, with annual budgets adjusted based on program performance relative to energy savings targets. Three criteria guide media weight allocation: sector appropriateness, marketing goals, and reach consistency.
versa. 23 24 ENS’s marketing strategy is working to achieve three goals: 25 1. Increase awareness of ENS: 26 Increasing awareness was a priority in 2012 and 2013, which is a standard practice 27 for new brands. To that end, more weight was...
AI summary ENS's marketing strategy focuses on increasing brand awareness, driving program uptake, and educating the public to change energy behavior. TV advertising boosted awareness from 16% to 37% between 2012-2014. Reduced Appliance Retirement ad spending in 2013 led to a 15% drop in program uptake, which was reversed by increasing radio/print ads. Surveys showed 20% of Nova Scotians reported behavior change due to ENSC in 2013.
e Filed: March 27, 2015 E1 (NSPI) IR-2 Page 1 of 7 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Enabling Strategies - DSM Portion 2012 2013 2014 ($k) ($k) ($k) Develop...
AI summary E1 (EfficiencyOne) submitted a non-confidential response to NSPI's information requests regarding the 2016-2018 EECA supply agreement (M06733), detailing Enabling Strategies expenses for DSM from 2012-2014, including development, education, outreach, and innovative financing costs.
NON-CONFIDENTIAL 1 2 ENS’s involvement in Codes and Standards (described in the 2016-2018 DSM Resource 3 Plan as Working with Governments) helps to improve the efficiency of electricity- 4 consuming devices and equipment, through either vo...
AI summary ENS contributes to energy efficiency through codes and standards, research informing DSM plans, and education/outreach initiatives. Research on rebates and program participation barriers guides policy, while events like the Bright Business Conference enhance industry collaboration. Advertising efforts aim to increase energy efficiency awareness.
icipation, 25 networking and collaboration. 26 27 In regards to the qualitative benefits of advertising, ad recall measures illustrate that 28 ENSC and ENS messages are reaching the public, which means a strong likelihood that 29 ENS will...
AI summary The text highlights the effectiveness of ENSC and ENS advertising in raising public awareness of energy efficiency programs, leading to increased program uptake. It references a 2016-2018 EECA supply agreement (M06733) and E1's responses to NSPI information requests.
o expects to continue partnering with the 25 Nova Scotia Home Builders’ Association to support energy efficiency practices within 26 their member base. 27 28 Qualitative benefits of Regulatory Affairs include providing a fair and transpare...
AI summary EfficiencyOne (E1) plans to continue collaborating with the Nova Scotia Home Builders’ Association to promote energy efficiency. The text highlights qualitative benefits of Regulatory Affairs, such as enabling stakeholder input into DSM Resource Plans and programs.
iled: March 27, 2015 E1 (NSPI) IR-2 Page 7 of 7 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-3: 2 3 Reference: EfficiencyOne, Evidence - Page 46, Lines 18-2...
AI summary E1 (EfficiencyOne) responds to NSPI's IR-3 request regarding DSM providers' multi-year approval periods and performance requirements. E1 cites the Edison Foundation's report, noting it does not specify approval periods but provides a table evaluating ten jurisdictions' annual vs. multi-year performance metrics.
Date Filed: March 27, 2015 E1 (NSPI) IR-3 Page 2 of 2 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-4: 2 3 Reference: EfficiencyOne, Appendix A – 2016-2018 D...
AI summary E1 (EfficiencyOne) responds to NSPI's request regarding its definition of 'market transformation' for the 2016-2018 DSM Resource Plan, citing the American Council for an Energy Efficient Economy (ACEEE) definition. E1 asserts that market transformation involves removing barriers to accelerate cost-effective energy efficiency adoption as standard practice.
e Filed: March 27, 2015 E1 (NSPI) IR-4 Page 2 of 2 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-5: 2 3 Reference: EfficiencyOne, Evidence – Page 39, Lines 1...
AI summary E1 (EfficiencyOne) responds to NSPI's inquiry about the 2016-2018 DSM Resource Plan's cost-effectiveness, stating that UARB requires a Total Resource Cost test ratio of 1.0 or greater. E1 clarifies that the RIM test is not part of their analysis but notes Navigant's model can calculate RIM ratios.
S-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Figure 1 - 2016-2018 DSM Resource Plan Investment and Savings Incremental Incremental Annual Net Annual Net Program Ratepayer Impact Investment Lifetime Benefits Total Re...
AI summary The figure presents data on investment and savings for the 2016-2018 DSM Resource Plan, including metrics like annual net energy savings, demand savings, and cost tests (TRC and PAC). It highlights the financial and energy efficiency aspects of the program.
at Generator at Generator Cost Test (PAC)c (RIM)d (GWh) (MW) 2016 38.5 127.3 133.1 20.4 1.9 3.6 0.5 2017 40.3 139.8 136.5 21.0 2.0 3.8 0.5 2018 42.6 150.5 136.3 21.0 2.1 3.9 0.5 Total 121.5 417.5 405.9 62.5 2.0 3.8 0.5 Currency is expresse...
AI summary The text presents data on demand-side management (DSM) resource plan investments and savings from 2016 to 2018, including metrics like RIM and PAC. Annual avoided costs, calculated using ENSC’s DSM Potential Study, are highlighted as including energy and capacity costs. Terms like TRC, PAC, and RIM are defined as benefit/cost ratios.
g lifetime benefits to ENS’s costs. d RIM is a benefit/cost ratio comparing lifetime benefits to ENS’s costs and NSPI lost revenues. 2 3 Figure 2 - 2016 DSM Resource Plan Investment and Savings Incremental Incremental Annual Net Annual Net...
AI summary The text discusses metrics used in evaluating the 2016 DSM Resource Plan, including RIM, TRC, and PAC. These metrics compare lifetime benefits to ENS’s costs and NSPI’s lost revenues, focusing on energy and demand savings.
at Generator at Generator Cost Test (PAC)c (RIM)d (GWh) (MW) Residential DSM Programs Efficient Product Rebates 2.5 6.6 11.0 1.1 1.6 2.7 0.4 Existing Residential 12.0 50.9 41.0 7.5 1.8 4.3 0.5 Low Income Participation e 2.0 7.8 1.0 New Res...
AI summary The table presents metrics for residential and business energy efficiency programs, including Program Assessment Cost (PAC), Resource Investment Metric (RIM), and output in GWh and MW. It details participation rates, costs, and program-specific data across categories like rebates, direct installation, and enabling strategies.
Other Enabling Strategies 0.6 Total 38.5 127.3 133.1 20.4 1.9 3.6 0.5 Currency is expressed in 2016 dollars. Columns may not add correctly, due to rounding. Annual avoided costs, calculated using ENSC’s DSM Potential Study at the Base Leve...
AI summary The text discusses avoided costs from ENSC's DSM Potential Study, including energy and capacity costs, and defines TRC, PAC, and RIM as benefit/cost ratios. It references the 2015 DSM Resource Plan Settlement Agreement and a 2016-2018 EECA supply agreement. Metrics include lifetime net present value of benefits and participation by low-income customers.
pation by low income customers, per the 2015 DSM Resource Plan Settlement Agreement. Numbers are a subset of Existing Residential. 1 2 Figure 3 - 2017 DSM Resource Plan Investment and Savings Incremental Incremental Annual Net Annual Net P...
AI summary The text references the 2015 DSM Resource Plan Settlement Agreement and highlights data on low-income customer participation in energy efficiency programs. Figure 3 outlines 2017 DSM investment and savings metrics, including energy and demand savings, total resource costs, and program administrator evaluations.
at Generator at Generator Cost Test (PAC)c (RIM)d (GWh) (MW) Residential DSM Programs Efficient Product Rebates 2.7 7.3 12.0 1.1 1.7 2.8 0.4 Existing Residential 13.6 58.3 44.2 8.0 1.9 4.3 0.5 Low Income Participation e 2.3 8.2 1.1 New Res...
AI summary The table presents cost and performance metrics for Nova Scotia's demand-side management (DSM) programs, including residential and business initiatives. It details program expenditures, energy savings (GWh), capacity (MW), and associated metrics like Program Assessment Cost (PAC) and Resource Investment Metric (RIM). Totals for program categories and enabling strategies are summarized.
Other Enabling Strategies 0.7 Total 40.3 139.8 136.5 21.0 2.0 3.8 0.5 Currency is expressed in 2016 dollars. Columns may not add correctly, due to rounding. Annual avoided costs, calculated using ENSC’s DSM Potential Study at the Base Leve...
AI summary The text presents data on avoided costs, lifetime benefits, and cost-benefit ratios (TRC, PAC, RIM) for demand-side management (DSM) programs. It references the 2015 DSM Resource Plan Settlement Agreement and the 2016-2018 EECA Supply Agreement (M06733), highlighting low-income participation and energy efficiency metrics.
(E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 2 Figure 4 - 2018 DSM Resource Plan Investment and Saving Incremental Incremental Annual Net Annual Net Program Ratepayer Impact Investment Lifetime Benefits Total R...
AI summary Figure 4 from E1's response to NSPI outlines the 2018 DSM Resource Plan's investment and savings, including incremental energy/demand savings, total resource costs (TRC), program assessment costs (PAC), and ratepayer impact metrics. The data evaluates efficiency program economics.
at Generator at Generator Cost Test (PAC)c (RIM)d (GWh) (MW) Residential DSM Programs Efficient Product Rebates 2.7 7.9 12.2 1.1 1.8 2.9 0.4 Existing Residential 14.8 61.8 43.6 8.0 1.9 4.2 0.5 Low Income Participation e 2.6 7.7 1.0 New Res...
AI summary The document presents a table detailing metrics for various demand-side management (DSM) programs, including cost tests, resource investment metrics, and energy output figures. It categorizes programs into residential, business, nonprofit, and institutional segments, with data on participation, costs, and performance indicators.
Other Enabling Strategies 0.9 3 Total 42.6 150.5 136.3 21.0 2.1 3.9 0.5 Currency is expressed in 2016 dollars. Columns may not add correctly, due to rounding. Annual avoided costs, calculated using ENSC’s DSM Potential Study at the Base Le...
AI summary The text outlines avoided costs, TRC, PAC, and RIM metrics for energy efficiency programs, referencing ENS's 2015 DSM Resource Plan Settlement Agreement and NSPI's data. It includes a 2016-2018 EECA supply agreement and E1's responses to NSPI information requests.
E1 (NSPI) IR-5 Page 4 of 4 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-6: 2 3 Reference: EfficiencyOne, Appendix A – 2016-2018 DSM Resource Plan – Page 14,...
AI summary EfficiencyOne (E1) explains its Custom Program's approach to free-ridership screening by assessing financial barriers and allowing participation at any project phase. The program accommodates diverse customer needs without directly comparing its breadth to other Canadian jurisdictions.
NON-CONFIDENTIAL 1 participants provide responses to a series of questions designed to screen for free- 2 ridership. These questions focus on topics such as: 3 • Impact of potential incentives on the decision-making process, by identifying...
AI summary The document outlines a screening process for free-ridership in energy efficiency programs, including questions on incentives, financial support, project timelines, and technical support. It also describes the Custom program, which supports a wide range of non-prescriptive measures and complex projects, with examples from other Canadian jurisdictions.
m 23 (http://takechargenl.ca/business/custom/) 24 • Ontario: SaveonEnergy Custom Incentives 25 (https://www.saveonenergy.ca/Business/Program-Overviews/Retrofit-for- 26 Commercial/Available-Incentives/Custom.aspx) 27 • Manitoba: Manitoba Hy...
AI summary The text provides links to various provincial commercial custom incentive programs across Canada, including those in Alberta, Ontario, Manitoba, British Columbia, and the Northwest Territories. It also references a 2016-2018 Supply Agreement for EECA under matter number M06733.
ate Filed: March 27, 2015 E1 (NSPI) IR-6 Page 3 of 3 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-7: 2 3 Reference: EfficiencyOne, Appendix A – 2016-2018 DS...
AI summary E1 responds to NSPI's information request regarding income verification and participation statistics in residential programs. E1 states it does not collect income levels for most programs, relying instead on independent evaluations to assess program effectiveness and cost efficiency.
e Filed: March 27, 2015 E1 (NSPI) IR-7 Page 1 of 1 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-8: 2 3 Reference: EfficiencyOne, Evidence - Page 39, Line 19...
AI summary E1 (EfficiencyOne) responds to an information request regarding the reasons for lower unit costs in its proposed DSM Plan compared to prior plans. A table is provided showing the first-year unit costs for each plan from 2012 to 2018.
2013 2014 2015 2016 2017 2018 Average Proposed $0.35 $0.34 $0.35 $0.32 $0.29 $0.30 $0.31 $0.30 14 Unit Cost 15 16 The 2016-2018 DSM Resource Plan has lower unit costs for the following reasons: 17 • Short-Term Affordability: The proposed 2...
AI summary The 2016-2018 DSM Resource Plan has lower unit costs due to the removal of the Home Energy Report, reduced Enabling Strategies investment, and a shift towards lower-cost programs like Existing Residential, Efficient Products (BNI), and Custom Incentives.
nent: Column V 28 29 b) Please refer to Attachment 1. Measure counts are outputs from 2016-2018 DSM 30 Resource Plan modelling; they are not “anticipated” counts of measure uptake. ENS Date Filed: March 27, 2015 E1 (NSPI) IR-9 Page 1 of 2...
AI summary The text discusses the 2016-2018 DSM Resource Plan modelling, noting that measure counts are outputs from the model and not anticipated uptake. It also provides data on daylighting controls as part of the Efficient Product Rebates (BNI) program.
. As Nova Scotia installers gain Efficient Product Rebates (BNI) 2,320 experience with installation, installation costs are expected to decrease. ENERGY STAR® appliances, such as self-contained ice makers, for restaurants and commercial fo...
AI summary The text discusses the impact of installation experience on Efficient Product Rebates (BNI) for ENERGY STAR® appliances and LED Low Bay fixtures, noting cost reductions over time. It highlights the strategic importance of ENERGY STAR® branding and the role of DSM jurisdictions in promoting energy-efficient products.
te Filed: March 27, 2015 E1 (NSPI) IR-11 Page 1 of 7 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 b) As shown in ENS’s rate and bill impact analysis, for total custome...
AI summary The document discusses the impact of different Demand Side Management (DSM) scenarios on average customer bills, showing that increased investment in DSM reduces bills, while reduced investment increases them. It references ENS’s rate and bill impact analysis and provides examples from the Small General rate class.
nt for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Mid-DSM Scenario 2 3 4 For clarification, the reason that participants’ (the blue lines) bills are reduced in all 5 scenarios is because of the as...
AI summary The text explains how the ENS rate and bill impact model assumes that 75% of changes in energy savings are due to changes in the number of participants, while 25% are due to changes in energy savings per participant. It also notes that the UARB-approved cost allocation methodology was used due to NSPI not filing its own proposed methodology.
Filed: March 27, 2015 E1 (NSPI) IR-11 Page 3 of 7 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 general trends would be expected to remain the same but specific values...
AI summary The document discusses the impact of varying levels of Demand Side Management (DSM) investment on rates and bills, showing that increased DSM investment leads to higher rates in the short term but lower rates over the lifetime of the program for most rate classes.
EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Mid-DSM Scenario 2 3 4 These results are dependent on the cost-allocation methodology approved for the 2016- 5 2018 years. Rate impacts by class are affe...
AI summary The document discusses the impact of the cost-allocation methodology approved for the 2016-2018 period on rate and bill impacts, noting that rate impacts are more significantly affected than bill impacts. It also references the use of the existing UARB-approved methodology and directs to specific appendices for detailed rate-class specific results.
NON-CONFIDENTIAL Measure Analysis Part of Demand Response Program. Please refer Heat & Power Load Control to part c). Home Energy Report Program removed. Please refer to part c). Removed due to current expectations of 2016- Nest Thermostat...
AI summary The document discusses the removal of several energy efficiency measures due to low uptake and strategic rationale, and outlines the development of a revised DSM Resource Plan by ENS in collaboration with NSPI, considering system requirements and short-term affordability.
NON-CONFIDENTIAL 1 a lower investment level, ENS removed the program from the Plan, as, based on a one- 2 year measure life, it has the highest lifetime unit cost in ENS’s portfolio. Removing this 3 program did not affect local industry ca...
AI summary Efficiency Nova Scotia (ENS) removed a program from its DSM Plan due to high lifetime unit costs and lack of data on assumptions for demand response measures. ENS also removed demand response from consideration due to its inability to provide energy savings or avoid capacity costs during the Plan period. Future research and pilot programs are expected.
Existing Residential or New 22 Residential programs as applicable (Application, Appendix A, page 23, lines 5-7). Any 23 piloted measures would be subject to cost-effectiveness screening. 24 25 Business Demand Response: The Business Demand...
AI summary The document discusses the removal of the Business Demand Response program due to cost-effectiveness concerns and lower priority from NSPI. It also references the 2016-2018 Supply Agreement for EECA under matter number M06733.
NON-CONFIDENTIAL 1 Enabling Strategies: Enabling strategies build demand for, and support the long-term 2 sustainability of, energy savings. When ENS reduced its proposed investment level from 3 the $50 million plan to the current proposed...
AI summary The document discusses Enabling Strategies and their role in supporting long-term energy savings, noting reductions in investment levels by ENS. It also mentions the use of the EL-RAM model to determine program-level investments and highlights considerations for the overall DSM portfolio, including cost-effectiveness, affordability, and industry capacity.
iveness screening requirements. This analysis is provided in 23 EfficiencyOne’s Application Evidence, page 42, lines 17-23 and was informed by 24 Dunsky Energy Consulting’s memo, “DSM Portfolio Design Principles and 25 Considerations”, pro...
AI summary The text references EfficiencyOne's application evidence and Dunsky Energy Consulting’s memo on DSM portfolio design principles, which informed ESN's approach to portfolio offerings. It also mentions a 2016-2018 supply agreement for EECA under matter number M06733.
NON-CONFIDENTIAL 1 f) Yes. As provided in Appendix F, Dunsky Energy Consulting’s memo “DSM Portfolio 2 Design Principles and Considerations,” which informed ENS’s approach to overall 3 portfolio offerings, maximizing equity, or social lice...
AI summary The document discusses the importance of social license in Demand Side Management (DSM) programs, emphasizing equitable access and customer participation. It references Dunsky Energy Consulting's principles and Tim Woolf's recommendations for promoting participation and addressing equity concerns. The EL-RAM model is mentioned in relation to energy savings calculations.
NON-CONFIDENTIAL 1 filed electronically, for the energy savings values, which can be found in column 2 E (column 5 in the printed version). 3 4 (ii) ENS does not have estimated measure-level participation rates, and the EL-RAM, 5 which has...
AI summary The document discusses the absence of estimated measure-level participation rates in the EL-RAM model, the importance of TRC, PAC, and RIM ratios in evaluating demand-side management programs, and references to EfficiencyOne's responses to NSPI IR-10 and IR-9 for detailed data on incentives and net-to-gross ratios.
y: Rates, Bills and Participation Impacts Slide 16 Date Filed: March 27, 2015 NSPI IR-12 Attachment 1 Page 17 of 26 Program Designs to Increase Participation • EE programs should address all end-uses. • EE programs should address all custo...
AI summary The document outlines program designs and policy options aimed at increasing participation in energy efficiency programs. It emphasizes addressing all customer types and end-uses, tailoring incentives, and improving data collection and analysis. It also suggests increasing budgets, setting explicit participation goals, and linking utility incentives to participation rates.
ncy: Rates, Bills and Participation Impacts Slide 21 Date Filed: March 27, 2015 NSPI IR-12 Attachment 1 Page 22 of 26 Benefits of EE that Flow to All Customers - III • Energy efficiency will avoid costs of transmission and distribution lin...
AI summary The text discusses the benefits of energy efficiency (EE), including avoided transmission and distribution costs, with estimates of $423 million in savings from MA Three-Year Plans. It also highlights the impact of EE on New England's peak and energy demand, as well as large commercial and industrial rate impacts.
NSPI IR-13 Attachment 1 Page 6 of 8 Achievable Potential and Associated Investment for the 2016-2018 Period
AI summary This section discusses the achievable potential and associated investment for the 2016-2018 period, likely related to energy efficiency or demand-side management programs.
approach is also not 29 consistent with DSM portfolio design principles and considerations, as outlined by 30 Dunsky Energy Consulting in Appendix F of EfficiencyOne’s Application. Date Filed: March 27, 2015 E1 (NSPI) IR-14 Page 1 of 2 201...
AI summary The document discusses E1's response to NSPI's information request regarding performance targets for the 2016-2018 Supply Agreement for EECA. E1 explains that it does not include a performance target for total spending or unit cost ($/kWh) due to the lack of recourse for additional revenue in case of over-expenditure.
Filed: March 27, 2015 E1 (NSPI) IR-16 Page 2 of 2 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-17: 2 3 Reference: EfficiencyOne, Evidence - Page 28, Lines 1...
AI summary The document outlines information requests related to changes in the methodology for estimating demand savings under the DSM plan, including the use of 8760 hourly savings profiles and a comparison of demand savings estimates between the current filing and prior studies.
NON-CONFIDENTIAL 1 Response IR-17: 2 3 a) This difference is a result of different modelling techniques used for ENSC’s DSM 4 Potential Study and its proposed 2016-2018 DSM Resource Plan. As a result of this 5 change in modelling technique...
AI summary The difference in demand savings values between ENSC’s DSM Potential Study and its 2016-2018 DSM Resource Plan is due to changes in modelling techniques. The new methodology, developed in collaboration with NSPI and Navigant, focuses more on capacity avoidance and uses building simulation software with detailed load profile data.
nymous, one-year load profile data, in 8760 25 hourly format, for typical BNI customers, as well as customer class data for the 26 Commercial and Industrial classes. For Residential data, NSPI provided customer class 27 data, as well as da...
AI summary The document discusses the provision of load profile data for BNI customers and Residential classes by NSPI, which was used by Navigant to calibrate simulation models. It also references a 2016-2018 Supply Agreement for EECA under matter number M06733.
NON-CONFIDENTIAL 1 The building simulations were used to develop DSM Resource shapes in 8760 format. 2 This was made possible by running the simulation models using historical Nova Scotia 3 weather data. The results of these simulation mod...
AI summary The document discusses the use of building simulations to develop DSM resource shapes in 8760 format using historical Nova Scotia weather data. It also outlines evaluation methods for energy and demand savings, including the use of demand-to-energy ratios and system coincident peak diversity ratios. The verification process is determined by the UARB.
NON-CONFIDENTIAL 1 Request IR-18: 2 3 Reference: EfficiencyOne, Evidence - Page 30, Lines 23-25: 4 5 E1 states that the DSM savings “are of benefit to Nova Scotians in the short term due to 6 fuel savings resulting in lower bills for DSM p...
AI summary The document addresses a request for data on energy savings from demand-side management (DSM) programs in Nova Scotia. ENS notes that while it has not analyzed energy savings by sector, it has compared the Base and Low DSM scenarios, showing that the Base scenario provides greater fuel-related savings to Nova Scotians.
fuel-related savings of a Base DSM scenario over Year a Low DSM scenario1 2016 $3.7 million additional savings Date Filed: March 27, 2015 E1 (NSPI) IR-18 Page 1 of 2 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to N...
AI summary The document shows additional fuel-related savings from a Base DSM scenario compared to a Low DSM scenario for the years 2016, 2017, and 2018, with figures of $3.7 million, $5.9 million, and $7.1 million respectively. These savings are calculated using NSPI’s annual avoided costs and ENSC’s DSM Potential Study.
e Filed: March 27, 2015 E1 (NSPI) IR-18 Page 2 of 2 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-19: 2 3 Please provide in electronic format the following d...
AI summary The document outlines an information request (IR-19) made by NSPI to EECA, seeking detailed data on customers participating in DSM programs from 2012 to 2014, including customer identifiers, location, energy consumption, installed measures, and financial details.
ling of its initial rate and bill 24 impact analysis in 2013, from March until October, and its subsequent request to file historical 25 rate and bill impact analyses in October of each year). ENS has already consolidated it on a rate- 26...
AI summary The document discusses the consolidation of rate and bill impact analyses by ENS on a rate-class and per-program basis, which has already been provided to NSPI and stakeholders. Repeating the work on a per-customer basis is not feasible within the timeframe of the proceeding. ENS is planning system enhancements to better track data.
ed electronically. 24 i) Total incentive dollars: please refer to Attachment 1, filed electronically. 25 j) Total project costs: please refer to Attachment 1, filed electronically, for program 26 administrator costs (by program/program com...
AI summary The document discusses responses to information requests regarding incentive dollars, project costs, and potential changes to building codes and standards affecting DSM benefits by 2018. ENS states no changes to energy-related building codes are anticipated by 2018.
Filed: March 27, 2015 E1 (NSPI) IR-20 Page 1 of 1 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-21: 2 3 Reference: EfficiencyOne, Appendix A – 2016-2018 DSM...
AI summary The document contains an information request (IR-21) from NSPI to E1, seeking a list of custom projects from 2012 to 2014 with detailed information including customer names, rate classes, programs, energy and demand savings, project costs, incentives, and payback periods.
e Filed: March 27, 2015 E1 (NSPI) IR-21 Page 1 of 3 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 2 (m) Customer’s payback period with incentives 3 4 Response IR-21: 5...
AI summary The document outlines E1's response to NSPI's information request (IR-21), referring to EfficiencyOne's prior response to IR-19 for details on customer payback periods, program components, and energy savings data, all provided in an aggregate format.
Filed: March 27, 2015 E1 (NSPI) IR-21 Page 3 of 3 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-22: 2 3 Reference: EfficiencyOne, Evidence - Page 9: 4 5 Plea...
AI summary EfficiencyOne provides an estimate of direct installation savings for 2016-2018, including the number of customers served, energy and demand savings, and associated costs. The data is derived from the EL-RAM and references prior responses for detailed measure-level information.
E1 (NSPI) IR-22 Page 1 of 1 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-23: 2 3 Reference: EfficiencyOne, Appendix G – DSM Performance Indicators (Dunsky E...
AI summary The document outlines ENS's response to an information request regarding the measurement and verification of performance indicators in the 2016-2018 DSM Resource Plan. ENS proposes eight performance indicators, with cumulative energy and peak demand savings as targets assessed once at the end of the contract, while annual progress reports would be provided.
NON-CONFIDENTIAL 1 Request IR-24: 2 3 Reference: EfficiencyOne, Evidence - Page 7: 4 5 Please provide anticipated energy savings, demand reductions and program administrator 6 costs for all sub-components in the approved 2015 DSM Resource...
AI summary The response to Request IR-24 provides detailed information on anticipated energy savings, demand reductions, and program administrator costs for sub-components of the approved 2015 DSM Resource Plan, including various residential programs and components.
0.5 1.3 0.6 New Residential 1.3 3.0 0.8 Energy Savings Actions 1.2 15.4 0.0 Residential Subtotal 17.6 60.8 9.3 BUSINESS, NON-PROFIT AND INSTITUTIONAL PROGRAMS AND Direct Installation 6.0 13.0 2.8 Custom Incentives 5.8 20.5 2.1 Custom Retro...
AI summary The text presents a table with figures related to energy savings actions, residential and business programs, and enabling strategies. It includes data on various initiatives such as direct installation, custom incentives, and education & outreach, with corresponding numerical values.
Date Filed: March 27, 2015 E1 (NSPI) IR-25 Page 1 of 2 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL Investment 2016-2018 Total ($ million)a Residential DSM Programs Effi...
AI summary The document outlines the investment amounts allocated to various energy efficiency programs by EECA from 2016 to 2018, including residential and business programs, with a total investment of $121.5 million.
March 27, 2015 E1 (NSPI) IR-25 Page 2 of 2 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-26: 2 3 Reference: EfficiencyOne, Evidence - Page 33, Lines 23-24: 4...
AI summary E1 argues that reducing program capacity now may not be cost-effective if it leads to future rebuilding. E1 refers to its Application Evidence for analysis and discusses a reduced investment plan to address affordability while preserving industry capacity. No further mitigation measures were considered beyond the proposed plan.
its 2016- 27 2018 DSM Resource Plan development process so did not consider additional mitigation 28 measures. 29 30 c) Please refer to the Application Evidence, pages 32-33. Date Filed: March 27, 2015 E1 (NSPI) IR-26 Page 1 of 1 2016-2018...
AI summary The document refers to the 2016-2018 Demand Side Management (DSM) Resource Plan development process, noting that it did not consider additional mitigation measures. It also references the Application Evidence, pages 32-33, and mentions the 2016-2018 Supply Agreement for EECA under matter number M06733.
NON-CONFIDENTIAL 1 Request IR-27: 2 3 Reference: EfficiencyOne, Evidence - Page 34, Lines 4-5: 4 5 E1 states that “maintaining current DSM levels has the additional benefit of providing 6 DSM-related rate stability over time.” 7 8 Please r...
AI summary The response to Request IR-27 explains that maintaining current DSM levels helps avoid future rate increases by reducing the need for costly capital expenditures. It references the UARB’s 2014 decision on the DSM Cost Recovery Rider and changes to the Public Utilities Act that embedded DSM costs into the overall energy charge.
The amendments to the Public 28 Utilities Act also resulted in payments which would have been collected from NSPI customers 29 for DSM in 2015 being deferred, with payment beginning in 2016. 30 Date Filed: March 27, 2015 E1 (NSPI) IR-27 Pa...
AI summary Amendments to the Public Utilities Act caused payments for DSM in 2015 to be deferred until 2016. The document includes a 2016-2018 Supply Agreement for EECA and responses to NSPI information requests.
Filed: March 27, 2015 E1 (NSPI) IR-27 Page 1 of 2 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 All else being equal, these amendments would have caused a reduction in...
AI summary The document discusses the financial implications of the 2015 DSM deferral and its impact on the FAM under-recovery balance. It notes a $53 million offset from the deferral, along with other contributions, which are expected to largely repay the FAM under-recovery in 2015. The 2015 DSM level of activity is $39 million, with $35 million to be recovered over 8 years starting in 2016.
stment for 2016, 2017, and 2018 together 20 with the annual amortized cost of 2015 DSM for these years. This investment can be made 21 without DSM putting pressure on overall electricity rates. Date Filed: March 27, 2015 E1 (NSPI) IR-27 Pa...
AI summary The document discusses the 2016-2018 Supply Agreement for EECA M06733 and responses to information requests regarding IT system enhancements. The response indicates that the changes will improve reporting efficiency but no additional information will be available.
ast, as 28 evidenced by the evaluation and verification of tracked energy savings results. 29 Enhancements will provide more automation and make participation data more easily Date Filed: March 27, 2015 E1 (NSPI) IR-28 Page 1 of 2 2016-201...
AI summary The document outlines a 2016-2018 Supply Agreement for EECA under matter M06733, with E1 responding to NSPI information requests. It mentions improvements in database architecture and reporting functionality to make participation data more accessible and automated.
ate Filed: March 27, 2015 E1 (NSPI) IR-28 Page 2 of 2 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-29: 2 3 Reference: EfficiencyOne, Evidence – Appendix D 2...
AI summary E1 responds to NSPI's request regarding the exclusion of lost revenue recovery in its rate and bill impact model. E1 explains that it was unable to incorporate NSPI's feedback due to timing issues and plans to address it in future model versions.
Filed: March 27, 2015 E1 (NSPI) IR-29 Page 1 of 1 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-30: 2 3 Reference: EfficiencyOne, Appendix I – DSM Screening...
AI summary The response to Request IR-30 explains that the non-participant test (RIM test) is not considered appropriate for screening energy efficiency or demand-side management initiatives, as it only reflects the perspective of non-participants and does not provide a comprehensive evaluation.
efficiency or demand-side management initiatives. This is largely because the 30 RIM test reflects a very partial perspective – that of non-participants alone. For Date Filed: March 27, 2015 E1 (NSPI) IR-30 Page 1 of 2 2016-2018 Supply Agr...
AI summary The text discusses the RIM test's limited perspective, focusing only on non-participants, and notes that the Participant Cost Test was not considered a reasonable screening option. It also includes responses to information requests related to a supply agreement and a filing date.
Filed: March 27, 2015 E1 (NSPI) IR-30 Page 2 of 2 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests
AI summary This document, filed on March 27, 2015, includes E1's responses to NSPI information requests related to the 2016-2018 Supply Agreement for EECA, matter number M06733 (E-ENS-R-15).
NON-CONFIDENTIAL 1 Request IR-31: 2 3 Reference: EfficiencyOne – Evidence – Page 41, Lines 28-29: 4 5 E1 states that it has “worked with Navigant to refine the assumptions of the EL-RAM 6 model to put a greater emphasis on lower first-year...
AI summary EfficiencyOne explains modifications to the EL-RAM model to reduce first-year unit costs in the 2016-2018 DSM Resource Plan. Changes included reducing New Home Construction opportunities, removing the Demand Response program, and adjusting Existing Residential program assumptions to prioritize lower-cost measures. These adjustments led to significant cost and energy savings changes.
n a 26 decrease in unit cost for the program of $0.18 per kWh. Energy savings for the 2016- 27 2018 period for this program increased by 33.3 GWh. 28 • BNI programs were prioritized in plan development via changes in assumptions relating 2...
AI summary The text discusses a decrease in unit cost for a program by $0.18 per kWh and an increase in energy savings for the 2016-2018 period. BNI programs were prioritized in plan development, leading to an increase in BNI energy savings as a percentage of total energy savings from 50 percent to 57 percent.
Date Filed: March 27, 2015 E1 (NSPI) IR-31 Page 2 of 2 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests
AI summary This document outlines E1's responses to NSPI's information requests related to the 2016-2018 Supply Agreement for EECA, referenced in matter M06733 (E-ENS-R-15).
NON-CONFIDENTIAL 1 Request IR-32: 2 3 (a) Please explain in detail how new codes and standards are included in, or affect, E1’s 4 long term planning. 5 6 (b) Have past energy/demand savings figures been amended for subsequently adopted 7 c...
AI summary The response explains that ENS incorporates new energy codes and standards into NSPI’s Integrated Resource Planning process. It highlights that DSM potential studies account for these codes, and their effects are modeled as percent changes in savings over time.
26 year savings for each year before 2015. Starting in 2015, the program administrator’s 27 share of the measure savings would be reduced by 50 percent over the remainder of the 28 measure life, with the other 50 percent being attributed t...
AI summary The text discusses a reduction in the program administrator’s share of measure savings starting in 2015, with 50% attributed to the code or standard. It references a study by Navigant Consulting and a supply agreement for EECA.
27, 2015 E1 (NSPI) IR-32 Page 1 of 2 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 2 b) Yes, in ENSC’s DSM Potential Study. By utilizing the codes and standards time ve...
AI summary The document discusses how energy savings calculations are affected by the adoption of new energy codes and standards, particularly in the context of the DSM Potential Study. Savings from past DSM programs and codes are not revised even when new standards are implemented.
iled: March 27, 2015 E1 (NSPI) IR-32 Page 2 of 2 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests
AI summary This document outlines E1's responses to information requests from NSPI under the 2016-2018 Supply Agreement for EECA, referencing matter number M06733 (E-ENS-R-15).
NON-CONFIDENTIAL 1 Request IR-33: 2 3 Reference: EfficiencyOne, Appendix F - Balanced Plan Principles (Dunsky Energy 4 Consulting) – Pages 3 and 6: 5 6 Mr. Dunsky states that E1 “devote(s) resources to some higher risk long term efforts.”...
AI summary The response to Request IR-33 explains that EfficiencyOne balances risk minimization and strategic risk-taking in its 2016-2018 DSM Resource Plan, emphasizing diversification across sectors and investing in enabling strategies to reduce long-term costs.
te Filed: March 27, 2015 E1 (NSPI) IR-33 Page 2 of 2 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-34: 2 3 Reference: EfficiencyOne, Appendix I – DSM Screeni...
AI summary E1 responds to NSPI's information request regarding DSM potential in Nova Scotia, stating that there are still significant energy efficiency opportunities available at a lower cost than new supply, refuting the claim that most low-hanging fruit has been picked.
that these coming changes were fully accounted for in ENSC’s DSM 21 potential study, i.e. the potential and associated costs are net of anticipated new 22 standards. Date Filed: March 27, 2015 E1 (NSPI) IR-34 Page 2 of 2 2016-2018 Supply A...
AI summary The text references a demand-side management (DSM) potential study by ENSC, which accounts for new standards and their associated costs. It also includes a table related to program spending, energy savings, and demand reductions under a supply agreement for EECA, with notes on currency and verification status.
: March 27, 2015 E1 (NSPI) IR-35 Page 1 of 2 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 2 3 Notes: 4 Per Balance Adjustment filings. 5 2014 energy savings and demand...
AI summary This document outlines E1's responses to NSPI's information requests regarding the 2016-2018 Supply Agreement for EECA, referencing a matter number (M06733) and including notes about energy savings, spending estimates, and currency in 2016 dollars.
h 27, 2015 E1 (NSPI) IR-35 Page 2 of 2 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-36: 2 3 Reference: EfficiencyOne, Appendix G – DSM Performance Indicator...
AI summary The document contains a request (IR-36) from E1 to NSPI, asking for responses related to performance metrics used in demand side management (DSM) programs in various states and jurisdictions. The request includes questions about performance indicators, cost effectiveness, and the exclusion of Delaware and New Jersey from the study.
e Filed: March 27, 2015 E1 (NSPI) IR-36 Page 1 of 4 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests
AI summary This document pertains to E1's responses to information requests from NSPI under the 2016-2018 Supply Agreement for EECA, referenced in matter M06733 (E-ENS-R-15).
hich cumulative lifetime energy 29 savings are a critical input. As a result, half of our 10 case studies use cumulative lifetime 30 energy savings either implicitly or explicitly in their Performance targets. Date Filed: March 27, 2015 E1...
AI summary The document discusses the importance of cumulative lifetime energy savings in performance targets, noting that half of 10 case studies use this metric. It references a 2016-2018 supply agreement for EECA and E1 responses to NSPI information requests.
iled: March 27, 2015 E1 (NSPI) IR-36 Page 2 of 4 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests
AI summary The document references a 2016-2018 Supply Agreement for EECA under matter number M06733 (E-ENS-R-15) and includes E1 responses to NSPI Information Requests. It appears to be part of a regulatory proceeding involving energy efficiency programs and agreements.
NON-CONFIDENTIAL 1 2 d) As explained in our report (page 8), the choice of the 10 case studies aimed to strike a 3 balance between jurisdictions with a third party DSM administrator and those commonly 4 considered as leaders, even though t...
AI summary The text discusses the selection criteria for 10 case studies in energy efficiency programs, emphasizing the balance between third-party program administrators and recognized leaders, and the inclusion of performance targets based on complexity. Ohio is noted as a hybrid state with both investor-owned and municipal utility programs, while some jurisdictions use program expenditures as performance indicators.
rio and Vermont use program expenditures as a 24 performance target. In all cases, they are used to determine performance incentives paid 25 out to the Program Administrators. 26 27 g) As indicated in our report (page 8), Ontario is the on...
AI summary The text discusses the use of program expenditures as performance targets in energy efficiency programs, noting that Ontario and Nova Scotia are the only Canadian provinces using performance mechanisms. It references a 2016-2018 Supply Agreement for EECA and mentions E1 responses to NSPI information requests.
NON-CONFIDENTIAL 1 performance incentives. Elsewhere across the country, energy savings targets are used for 2 reporting purposes only, not as part of a performance contract mechanism. 3 4 h) For clarity, our report recommended that the cu...
AI summary The document discusses performance indicators for energy efficiency programs, including the inclusion of cumulative energy and peak demand savings as Target Performance Indicators. It references practices in Vermont and Oregon, such as Service Quality and Customer Satisfaction metrics, and notes that Nova Scotia considered similar metrics in its report.
led: March 27, 2015 E1 (NSPI) IR-36 Page 4 of 4 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-37: 2 3 Please provide a breakdown of employees by full-time, p...
AI summary The document provides a breakdown of employees by full-time, part-time, and temporary for E1 and ENS from 2011 to 2015, with 2016-2018 data pending the UARB’s decision on the DSM Resource Plan.
.6% 86.6 88 86 1 1 2015 59.2 70.1% 84.5 85 84 1 0 Budgeted 13 The table above does not include EfficiencyOne’s On-Site Energy Managers (OEMs), as these 14 positions are not included in compensation expenses. The cost of OEMs is covered thr...
AI summary The text discusses the exclusion of EfficiencyOne’s On-Site Energy Managers (OEMs) from compensation expenses, as their costs are covered through incentives and reimbursements. It also references a 2016-2018 supply agreement for EECA and E1 responses to NSPI information requests.
NON-CONFIDENTIAL 1 Request IR-40: 2 3 (a) Please provide the following information on the breakdown of labour costs (actual 4 and forecasted/budgeted) of E1 and ENS (as applicable) for each of the years from 5 2011 to 2018, inclusive: 6 7...
AI summary The request asks for a breakdown of labour costs, including wages, overtime, benefits, and pension costs, for E1 and ENS from 2011 to 2018. The response indicates that data is provided for 2011-2015 and that 2016-2018 data will be available after the UARB’s decision on the DSM Resource Plan.
E1 (NSPI) IR-40 Page 1 of 2 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 2 b) Please refer to the table below for 2011-2015 information. 2016-2018 consultant 3 require...
AI summary The document outlines consultant costs for the Demand Side Management (DSM) portion from 2011 to 2015 and indicates that 2016-2018 consultant requirements will be determined after the UARB’s decision on the 2016-2018 DSM Resource Plan.
is filed Confidentially and must be accessed through the UARB Confidential 2 Repository. 2016-2018 Supply Agreement for EECA M06733 (E-ENS-R-15) E1 Responses to NSPI Information Requests NON-CONFIDENTIAL 1 Request IR-44: 2 3 Please provide...
AI summary The document provides aggregate senior management compensation data for EfficiencyOne and ENS from 2011 to 2015, with 2016-2018 data pending the UARB’s decision on the DSM Resource Plan. The information is withheld on individual employee basis to protect confidentiality.
NON-CONFIDENTIAL 1 Request IR-46: 2 3 (a) Please provide, as applicable, total annual cost (historical and forecasted/budgeted) 4 for benefits offered by E1 and ENS (as applicable) for each of the years 2011 to 2018 5 inclusive. 6 7 (b) Pl...
AI summary The response to Request IR-46 provides historical benefit costs for the years 2011 to 2015, including statutory, dental, and pension costs, as well as their percentage of total payroll. It also notes that 2016-2018 data will be available after the UARB’s decision on the DSM Resource Plan.
E-8Evidence of Nova Scotia Power Inc.
111 passages
Nova Scotia Utility and Review Board IN THE MATTER OF The Public Utilities Act, R.S.N.S. 1989, c.380, as amended. - and - IN THE MATTER OF AN APPLICATION by EfficiencyOne for Approval of a Supply Agreement for Electricity Efficiency and Co...
AI summary The Nova Scotia Utility and Review Board is considering EfficiencyOne's application for approval of a supply agreement with Nova Scotia Power Inc., establishment of a final agreement, and approval of a 2016-2018 Demand Side Management (DSM) Plan under the Public Utilities Act. The proceeding is referenced as M06733.
2016-2018 DSM Plan Nova Scotia Power Evidence
AI summary The document outlines the 2016-2018 Demand Side Management (DSM) Plan submitted by Nova Scotia Power as evidence in a regulatory proceeding.
April 10, 2015 1 TABLE OF CONTENTS 2 3 1.0 EXECUTIVE SUMMARY 3 4 2.0 INTRODUCTION 7 5 2.1 Transparency and Accountability 9 6 3.0 AFFORDABILITY 14 7 3.1 DSM Spending Levels 15 8 3.2 Lowering the Cost of DSM 24 9 3.3 Affordability from a Sy...
AI summary NS Power supports acquiring affordable and cost-effective demand side management (DSM) to ensure stable electricity prices. However, it believes the E1 DSM Plan is not sufficiently affordable or cost-effective for customers.
17 E1 DSM Plan recommends DSM spending that is among the highest in Canada on 18 both a per-capita basis and a per-customer basis; 19 20 the level of DSM proposed by E1 is significantly more than required to avoid 21 capacity investments b...
AI summary The E1 DSM Plan recommends high levels of DSM spending in Nova Scotia, but NS Power argues that such spending is not necessary during the current contract period for compliance with renewable electricity standards or to meet power demand. NS Power suggests a lower DSM spending level of approximately $22 million per year.
DATE FILED: April 10, 2015 Page 3 of 51 1 rate pressure for customers and avoids resource additions for capacity planning purposes 2 until 2032. 3 4 During the course of contract negotiations, NS Power had requested E1 to model a $10 5 mil...
AI summary NS Power requested E1 to model a DSM plan with a lower investment level, but E1 refused and instead proposed a higher spending plan. NS Power is concerned about E1's autonomy, flexibility, and the structure of deliverables and compensation.
1 E1 (NSPI) IR-14, March 27, 2015, page 1, lines 3-6. E1 (NSPI) IR-26(b), March 27, 2015, page 1, lines 26-28. the creation of a "reserve fund" financed by NS Power customers with 50 percent of any surplus balance being placed in a reserve...
AI summary NS Power requests E1 to redesign its DSM plan with a more appropriate portfolio of programs and spending level, suggesting a funding level of approximately $22 million per year over the Contract Period to achieve energy savings of about 100 GWh annually and avoid adding generation capacity until 2032.
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 amount owing in the following. 3 EfficiencyOne Evidence, February 27, 2015, page 55. agreement. 3 DATE FILED: April 10, 2015
AI summary The document references an agreement and includes a citation to EfficiencyOne evidence from February 27, 2015, page 55, and notes the date filed as April 10, 2015.
& lt;sup>4 Please refer to Figure 4.1 on page 34 herein. 1 A decision on the allocation and recovery of costs of any approved DSM Plan 2 from NS Power be deferred until an application is made by NS Power. 3 4 E1's request for the estab...
AI summary The text outlines several decisions related to the Demand Side Management (DSM) Plan, including deferring cost allocation until an application is made, rejecting requests for a reserve fund and a change in cost-effectiveness testing methodology, and establishing standardized filings for future DSM applications.
1 2.0 INTRODUCTION 2 3 As a result of recent amendments to the Public Utilities Act (Nova Scotia) ("Act"), the 4 Province of Nova Scotia has created a franchise system for the supply of cost-effective 5 energy efficiency and conservation a...
AI summary Nova Scotia amended the Public Utilities Act to create a franchise system for energy efficiency (DSM) programs. NS Power and E1 could not finalize a 3-year Supply Agreement due to disagreements over DSM quantity, cost, and E1's autonomy. NS Power supports DSM for stable prices but opposes E1's flexibility in altering plans, citing testimony from David Pickles.
7 Navigant, 2014 IRP, Nova Scotia 2015 ‐ 2040 Demand Side Management (DSM) Potential Study , Presented to Efficiency Nova Scotia Corporation, NSUARB M05522/P-884.14, January 7, 2014. 1 period, customer impacts can be mitigated by implement...
AI summary NS Power is seeking approval for a Supply Agreement for the provision of Energy Efficiency Conservation Agreements (EECAs) and emphasizes the need for transparency and accountability from E1, now a regulated public utility, in justifying its DSM Plan. The Act requires that the Board ensure the agreement is in the best interests of customers.
9 Please refer to Appendix A, Direct Testimony of David Pickles, April 10, 2015, page 27, lines 16-19. 1 insufficient details to allow a robust review nor meaningful consideration of 2 alternatives. E1 did not provide these plans. 3 4 • NS...
AI summary NS Power submitted an Information Request (IR) to E1, requesting a DSM plan within an annual $20 million investment level. E1 refused to provide such a plan, citing lack of development during the 2016-18 DSM Resource Plan process and the time required for modeling. David Pickles testified that it is common for energy efficiency planners to evaluate various program scenarios and expenditure levels.
& lt;sup>10 E1 (NSPI) IR-14(a), March 27, 2015, page 1, lines 22-25. 11 Please refer to Appendix A, Direct Testimony of David Pickles, April 10, 2015, page 19, lines 13-20. assess the impacts, if any, which result if E1 is not able to clai...
AI summary E1 refused to provide data on the impact of not claiming ITCs and failed to compare DSM plans as requested by NS Power. NS Power criticized E1's use of flat load profiles instead of hourly 8760-hour DSM profiles, which contradicted the ELRAM model and the Final 8760 profile.
onth). NS Power also questions whether the information is correct since it does not correspond to the Final 8760 profile provided in conjunction with E1's Electric Resource Assessment Model ("ELRAM"). NS Power had requested E1 provide cert...
AI summary NS Power disputes the accuracy of information provided by E1, citing discrepancies with the Final 8760 profile in ELRAM. NS Power requested historical data on customer participation and custom projects to assess the cost-effectiveness of DSM programs, but E1 refused, claiming the data was not relevant and too difficult to consolidate.
& lt;sup>14 E1 (NSPI) IR-19 and IR-21, March 27, 2015. 1 provided to NS Power in the aggregate, making it extremely difficult for NS 2 Power to perform any type of substantive analysis on it. 3 4 E1 provides minimum detail on which to as...
AI summary The document highlights concerns raised by NS Power regarding the insufficient detail provided in E1's DSM plan application, making it difficult to assess the program's merits and reasonableness of costs. NS Power suggests the need for a standardized filing process for future DSM applications.
3 Affordability of electricity service is of paramount concern to NS Power customers. This 4 is evident through NS Power engagements with our customers and stakeholders, both in 5 regulatory forums such as General Rate Applications and the...
AI summary NS Power emphasizes the affordability of electricity service for customers and highlights the impact of demand-side management (DSM) on rate pressure. The company notes that removing the energy efficiency charge from bills has left no dedicated funding for DSM, and additional DSM spending increases revenue requirements, thereby raising rates. NS Power seeks to balance DSM efforts with cost-effectiveness to avoid economic impacts on the province.
16 3.1 DSM Spending Levels 17 18 NS Power understands and agrees cost-effective and affordable DSM can provide long 19 term value to customers. Through our partner, Clean Nova Scotia, NS Power will 20 finance efficiency upgrades for an est...
AI summary NS Power agrees that cost-effective and affordable DSM can provide long-term value to customers. They plan to finance efficiency upgrades for 6,600 low-income homeowners through Clean Nova Scotia, using up to $37 million over 10 years, funded by shareholders. This initiative aims to address affordability concerns without passing costs to customers.
DATE FILED: April 10, 2015 Page 15 of 51 $2032.^{17}$ Any proposal which would obligate NS Power to p ay for addit ional DSM I in the near-ter m requires careful scr utiny and consider ation. 1 2
AI summary The text discusses the need for careful scrutiny of proposals that would obligate NS Power to pay for additional DSM (Demand Side Management) initiatives in the near term.
Included with the direct evidence of David Pickles (Appendix A, Attachment A) is a copy of a report prepared by ICF International ("ICFI") for NS Power (Review of Nova Scotia Energy Savings Portfolio). The Report reviews E1's energy saving...
AI summary The ICF International report reviews Nova Scotia's energy savings portfolio, noting that DSM spending in Nova Scotia is higher than any other Canadian jurisdiction on a per capita basis and among the highest on a per customer basis. The report compares Nova Scotia's spending with other provinces and highlights the proposed spending levels by NS Power during the Contract Period.
2015 PLAN DSM SPEND PROVINCE YEAR $DSM/CAPITA $DSM/CUSTOMER $DSM/CAPITA $DSM/CUSTOMER NOVA SCOTIA 2014 41.05 77.21 41.37 77.81 BRITISH COLUMBIA 2014 25.97 62.82 31.96 77.29 MANITOBA 2012 22.39 51.02 20.44 47 14 NEW BRUNSWICK 2013 22.07 47....
AI summary The table compares the 2015 DSM spend per capita and per customer across various provinces in Canada, including Nova Scotia, British Columbia, Manitoba, New Brunswick, Ontario, Quebec, Saskatchewan, and Newfoundland and Labrador, with data from different years.
3 In addition to Nova Scotia having the highest spending level on DSM, the ICFI Report 4 also reveals the unit cost of DSM is comparatively expensive relative to other 19 Please refer to Appendix A, Attachment B, Review of NS Energy Saving...
AI summary The document discusses the high unit cost of Demand Side Management (DSM) in Nova Scotia compared to other Canadian jurisdictions. It references figures showing the 2015 budgeted DSM first year unit cost per kWh for E1 and highlights that Nova Scotia's installed DSM costs have consistently been higher than those in other provinces.
Savings Portfolio , April 8, 2015, page 6. 22 E1 (NSPI) IR-35, March 27, 2015. 1 2 In each year, Nova Scotia's cost of installed DSM has been higher than that in other Canadian jurisdictions.23 3 4 23 ENS has filed for approval of its cost...
AI summary Nova Scotia's cost of installed Demand Side Management (DSM) has been higher than in other Canadian jurisdictions. ENS collected $8.8 million in excess DSM costs in 2014, which raises concerns about recovery and whether these costs should have been collected in the first place.
24 Please refer to Appendix A, Attachment B, Review of NS Energy Savings Portfolio , April 8, 2015, page 15. • In the E1 DSM Plan, E1 is now requesting $0.29 to $0.31/kWh, although they were able to achieve an actual delivered cost of $0.2...
AI summary E1 is requesting a higher DSM Plan cost of $0.29 to $0.31/kWh, despite achieving $0.26/kWh in 2014. The increase is attributed to high unit costs from low-income homeowner programs and full HST costs, which are expected to be reduced in 2016 through ITCs.
10 11 12 13 14 8 1 2 3 4 5 6 7 In its initial evidence for the 2013-2015 DSM Plan Evidence, E1 proposed an increase in installed DSM costs. 25 Actual results to-date show that E1 actually achieved significantly lower costs than proposed. T...
AI summary The document discusses the performance of E1's 2013-2015 DSM Plan, noting that actual costs were significantly lower than initially proposed. It compares E1's costs to Manitoba Hydro's programs and highlights that E1's 2015 DSM programs are among the highest-cost in Canada, while the Canadian average is around $0.25/kWh. NS Power argues that a robust program can align with this average.
BC, MB, and NB. Alberta is not included as it does not provide DSM. & lt;sup>29 Please refer to Appendix A, Attachment B, Review of NS Energy Savings Portfolio, April 8, 2015, page 6. those of other DSM providers30 1 and that there may als...
AI summary The text discusses Nova Scotia's Demand Side Management (DSM) investment levels compared to other Canadian provinces, noting that Nova Scotia has the highest investment. It references a report showing that the 2015 DSM plan proposes 1.1% savings of electricity sales and highlights the cost and payback period for DSM programs.
is, and accounting for the time value of money, the 22 collective payback period for recovering these up-front DSM costs is approximately 7 23 years. 24 DATE FILED: April 10, 2015 Page 22 of 51 30 Please refer to Appendix A, Attachment B,...
AI summary The text discusses the payback period for DSM costs, noting a 7-year mid-term realization of benefits but near-term rate pressures. It highlights concerns about intergenerational inequity and cost recovery limits under Section 79M(6) of the Act, and notes that not all customers benefit from DSM in the short-term, raising affordability concerns.
33 DSM measure effects are assumed to be realized on average midway through the year. As a result, recognized first year savings are 50% of the annual thereafter. 1 products and services that they do not personally use, but which may benef...
AI summary The text discusses the assumption that DSM measure effects are realized midway through the year, leading to first-year savings being 50% of annual savings. It also raises concerns about indirect benefits to lower-income customers from products and services they do not personally use.
5 3.2 Lowering the Cost of DSM 6 7 NS Power submits that the level of investment proposed in the E1 DSM Plan is not 8 required in the near-term and only adds unnecessary upward pressure on rates in the near 9 term. Energy efficiency improv...
AI summary NS Power argues that the E1 DSM Plan's proposed investment is unnecessary in the near term, risking increased rates. They suggest lower-cost alternatives like selecting cost-effective measures, promoting energy efficiency codes, and leveraging market adoption of efficient technologies to reduce long-term program costs.
20 (a) Selection of Lower Unit Cost Options (Measures and Programs) 21 22 E1's primary DSM planning tool in the development of the E1 DSM Plan was the 23 ELRAM. This is a proprietary spreadsheet-based model developed by Navigant 24 which u...
AI summary NS Power analyzed E1's DSM Plan using ELRAM and found that selecting lower unit cost measures could reduce costs significantly. E1's consultants argue that only choosing the lowest cost measures is not viable, but other Canadian utilities achieve lower unit costs. NS Power urges E1 to explore lower-cost options, noting E1's refusal to prepare such plans for analysis.
(b) Codes and Standards Energy efficiency improvements can also be achieved in ways other than through rate-payer-funded DSM, such as through the enhancement of codes and standards and financing. E1 has indicated its support for, and parti...
AI summary NS Power and E1 (NSPI) advocate for enhancing energy efficiency through codes and standards, reducing reliance on DSM incentives. Strengthening appliance and building codes can improve efficiency and address cross-subsidization issues without direct incentives.
7 (c) Eliminate Adoption of Emerging Technologies at High Costs 8 9 With continual improvements in appliance efficiency standards and building 10 codes, the market increasingly adopts more efficient technologies and the cost of 11 these te...
AI summary The document argues that emerging technologies, like LED lighting and solar PV, become more affordable over time due to market trends and economies of scale. NS Power contends that subsidizing early adoption in Nova Scotia is costly, as the province's small market cannot influence technology maturation. Waiting until costs decrease through larger market adoption is more economically efficient.
4 (d) Elimination of Market Dampening Subsidies 5 6 Enabling market penetration of energy efficient products is a key function of 7 DSM. Emerging products and market transforming industries can benefit from 8 subsidies. However, the effici...
AI summary The text discusses the potential negative impacts of subsidies on market efficiency, noting that while subsidies can support emerging energy-efficient technologies, they may stifle competition and economic growth. It references NS Power's acknowledgment of intervenors in the proceeding and suggests that past ENS programs may have created inefficiencies in the local lighting market.
17 3.3 Affordability from a System Planning Perspective 18 19 Through the course of the 2014 IRP, the Company analyzed revenue requirements 20 resulting from a variety of different DSM profiles. NS Power has further considered the 21 affor...
AI summary NS Power analyzed the affordability of DSM profiles via NPV of revenue requirements over time horizons. The $22M annual DSM plan (Contract Period) yields the lowest long-term NPV beyond 2030, while the $25M plan (CRP 1-1) is more affordable in the short term. NS Power argues this balances cost-effectiveness and rate stability.
Figure 3.6: Ranking of CRPs low and low to a mid-investment level. In terms of a revenue requirement analysis, the Low DSM energy and capacity savings for the $22 million expenditure plan again demonstrates superior near term affordability...
AI summary The text discusses the affordability and cost-effectiveness of different Demand Side Management (DSM) expenditure levels in the context of the 2014 Integrated Resource Plan (IRP). It highlights that the 'Low' DSM energy and capacity savings plan offers superior near-term affordability while remaining cost-effective beyond 2030.
1 4.0 ANALYSIS OF NS POWER'S DSM REQUIREMENTS 2 3 4.1 NS Power System Requirements 4 5 The 2014 IRP tested 3 alternative levels of DSM expenditure with capacity and energy 6 savings based on ENS's DSM potential study with 25 year spending...
AI summary The 2014 Integrated Resource Plan (IRP) tested three levels of Demand Side Management (DSM) expenditure, with capacity and energy savings based on ENS's DSM potential study. It did not aim to optimize annual DSM spending but indicated that a more detailed examination of DSM would follow to prepare a near-term plan. Figure 4.1 shows that DSM savings of about 100 GWh per year could allow NS Power to avoid adding generation capacity until 2032.
Figure 4.1: NS Power System Requirements Based on 2014 IRP Assumptions 44 1 2014 IRP No DSM Plan CRP01-01-FGD-R01 Low DSM CRP2-17 FGD CRP Mid DSM/FGD Half-Low DSM Base DSM (Synapse Model) 2015 2016 2017 ML Oct 2017 ML Oct 2017 ML Oct 2017...
AI summary This table outlines NS Power's system requirements based on the 2014 Integrated Resource Plan (IRP) assumptions, comparing different scenarios including the implementation of a Demand Side Management (DSM) plan. It includes details on power generation, infrastructure projects, and net present value (NPV) figures for various years.
5.0 ALTERNATIVE DSM PLAN
AI summary The section outlines an alternative Demand Side Management (DSM) plan, referencing regulatory entities and prior planning documents. Key entities include the Nova Scotia Utility and Review Board (NSUARB) and ICF International, with acronyms like IRP and DSM central to the discussion.
5.1 NS Power's Alternative DSM Plan E1 did not develop or model any DSM investment scenarios lower than that contained in the proposed E1 DSM Plan. NS Power had requested E1 develop different plan scenarios, including one within an annual...
AI summary NS Power requested E1 (NSPI) to model lower DSM investment scenarios but was declined. E1's analysis lacks quantitative evaluation of lower expenditure options, limiting informed decision-making. NS Power proposes an alternative DSM plan aligned with Canadian benchmarks, emphasizing affordability and cost-effectiveness.
1 From a planning perspective, the difference between the alternative DSM scenario which 2 NS Power produced and the E1 DSM Plan is approximately 35 GWh a year on average. 3 This represents only approximately 0.3 percent of NS Power's tota...
AI summary The difference between the alternative DSM scenario produced by NS Power and the E1 DSM Plan is approximately 35 GWh per year, representing 0.3% of NS Power's total load. However, the cost difference is nearly $20 million annually, which is 1.5 to 2% of customer rates.
7 NS Power acknowledges that there could be enhancements to this approach that would 8 benefit from further modeling and input from E1, especially if program costs can be 9 achieved at similar levels to 2014 actuals, as opposed to the high...
AI summary NS Power suggests that a $22 million DSM plan over the Contract Period would be more affordable than E1's plan and deliver significant long-term benefits. It recommends E1 design such a plan with savings of approximately 100 GWh per year and present it for consideration. NS Power also references David Pickles' testimony for alternate assumptions and modeling.
DATE FILED: April 10, 2015 Page 39 of 51 1 6.0 FORM OF AGREEMENT 2 3 Since September 2014, NS Power worked to negotiate a Supply Agreement with E1 that 4 served the best interests of NS Power's customers taking into account the issues of b...
AI summary NS Power negotiated a Supply Agreement with E1 but could not agree on key terms, including the quantity and cost of DSM deliverables. NS Power does not support the proposed level of DSM or its associated contract price, finding it inconsistent with Canadian standards and unaffordable for ratepayers.
30 acceptable to NS Power. In order for NS Power to forecast its load requirements and 1 effectively manage the provision of capacity and energy, the Company requires annual 2 DSM performance, measurement and reporting. 3
AI summary NS Power requires annual Demand Side Management (DSM) performance, measurement, and reporting to effectively forecast load requirements and manage the provision of capacity and energy.
18 6.2 Schedule B – Compensation 19 20 E1 takes the position that the Supply Agreement should effectively be a fixed price 21 contract based on the total deliverable at the end of the Contract Period. E1 is paid 22 monthly and this would e...
AI summary E1 argues that the Supply Agreement should be a fixed price contract based on total deliverables at the end of the Contract Period, while NS Power believes the contract price should be allocated annually with adjustments for unspent funds.
49 EfficiencyOne Evidence, February 27, 2015, page 44. 1 discretion to make significant adjustments to the approved E1 DSM Program without any 2 further input from NS Power, the Board, or other stakeholders. Such changes could 3 include la...
AI summary The text discusses concerns about the potential for significant adjustments to the approved DSM Program by EfficiencyOne without input from NS Power, the Board, or stakeholders, which could affect implementation and cost distribution among customers. Appendix C includes draft forms of Schedules 'A' and 'B' based on an alternate DSM plan proposed by NS Power.
1 8.0 RATE IMPACT, BILL IMPACT AND PARTICIPATION RATES 2 3 As part of the E1 DSM Plan, E1 filed a Rate and Bill Impact analysis as Appendix C to 4 its Application. NS Power and other stakeholders had provided feedback on the Rate and Bill...
AI summary E1's Rate and Bill Impact Model (RBIM) does not account for the recovery of fixed costs lost due to reduced energy consumption from DSM programs, leading to an incomplete and understated analysis of rate and bill impacts. NS Power has pointed out this critical issue and supports future improvements to the model.
51 EfficiencyOne Evidence, February 27, 2015, Appendix D, page 2. 1 9.0 RESERVE FUND 4 program delivery. In terms of termination or expiration of the franchise, the Act 5 is clear. The term of the franchise is 9 years. This gives the franc...
AI summary EfficiencyOne (E1) discusses risk factors related to the termination of its franchise and potential reduction in funding sources for its Demand Side Management (DSM) programs. E1 proposes ratepayer funding to mitigate these risks, but NS Power argues that such a proposal lacks evidence and is premature.
DATE FILED: April 10, 2015 Page 48 of 51 1 11.0 ICFI EVIDENCE 2 3 To assist in its analysis of the E1 DSM Plan, NS Power engaged ICFI to carry out a 4 separate review and provide testimony. Attached hereto as Appendix A is a copy of the 5...
AI summary NS Power argues that the proposed E1 DSM Plan is not cost-effective or affordable for Nova Scotians. While recognizing the long-term benefits of DSM, NS Power suggests a reduced investment level during the Contract Period, estimating annual spending of approximately $22 million would achieve energy savings of 100 GWh per year and avoid the need for additional generation capacity until 2032.
1 I. INTRODUCTION - 2 Q. PLEASE STATE YOUR NAME. - 3 A. My name is David K. Pickles. My business address is 7160 North Dallas - 4 Parkway, Suite 340, Plano, Texas 75024. I am employed by ICF - 5 International ("ICF"), as Senior Vice Presid...
AI summary David K. Pickles, Senior Vice President of ICF International, testifies on behalf of Nova Scotia Power Inc. before the Nova Scotia Utility and Review Board. He outlines his 25-year experience in Demand Side Management (DSM) programs, energy efficiency initiatives, and integrated resource planning across multiple U.S. states.
13 A. I find that: - 14 The program information provided by EfficiencyOne is insufficient for 15 regulatory approval and contract development, and I recommend that 16 EfficiencyOne be directed to provide additional information; - 17 The re...
AI summary The findings indicate that EfficiencyOne's program data lacks sufficiency, cost justification, and breadth. The board recommends enhanced data submission, broader program evaluation, alternative DSM portfolio analysis, improved reporting standards, and expanded performance targets. These issues require corrective action for regulatory approval.
15 Appropriateness of the Proposed DSM Program Portfolio - 17 Q. HAVE YOU REVIEWED EFFICIENCYONE'S APPLICATION AND 18 PROPOSED PORTFOLIO OF DSM PROGRAMS? - 19 A. Yes, I have reviewed the Application and proposed programs and find 20 three...
AI summary The reviewer identifies three issues with EfficiencyOne's DSM program proposal: incomplete information, potential excessive budgets, and insufficient alternate scenarios. Recommends rejecting the plan and evaluating alternatives.
1 Reasonableness of the Proposed Costs 2 - 3 Q. WHY DO YOU BELIEVE THAT THE COSTS OF CERTAIN PROGRAMS - 4 MAY BE EXCESSIVE? - 5 A. Given the limited information provided with respect to each program 6 discussed above, it is difficult to ma...
AI summary The witness questions the reasonableness of EfficiencyOne's proposed program costs, suggesting they may be higher than those of other DSM providers. Benchmarks from 2013 and adjusted for inflation are referenced to compare costs between 2013 and 2016-2018.
1 Table 1. Residential DSM Portfolio Cost Benchmarks Rank State/ Province Program Administrator Data Type Year 2016 CAD/ kWh 1 WI Wisconsin Focus on Energy Actual 2013 $0.12 2 ON PowerStream Actual 2013 $0.16 3 ME Efficiency Maine Actual 2...
AI summary Table 1 presents residential DSM portfolio cost benchmarks from 2013 to 2018, comparing programs across various provinces and territories. EfficiencyOne's planned costs for 2016-2018 are modeled by Navigant, while other programs use actual data from 2013. The data highlights cost variations among different program administrators.
3 Table 2. Non-Residential DSM Portfolio Cost Benchmarks Rank State/ Province Program Administrator Data Type Year 2016 CAD/ kWh 1 MB Manitoba Hydro Actual 2013 $0.07 2 WI Wisconsin Focus on Energy Actual 2013 $0.14 3 BC BC Hydro Actual 20...
AI summary Table 2 presents non-residential DSM portfolio cost benchmarks from various provinces and states, including EfficiencyOne's planned costs for 2016-2018. The data shows the cost per kilowatt-hour for different program administrators, with EfficiencyOne's modeled cost being higher than other provinces' actual costs in 2013.
Table 3. Residential DSM Program Cost Benchmarks1 1 Rank State/ Province Program Administrator Data Type Program Name Year 2016 CAD/ kWh 1 BC BC Hydro Actual Residential Rate Structures 2013 $0.01 2 ON Toronto Hydro Actual HVAC Incentives...
AI summary Table 3 presents cost benchmarks for residential demand-side management (DSM) programs across various provinces and states, including Nova Scotia's EfficiencyOne programs. The table lists programs, administrators, data types, years, and associated costs per kWh.
1 Table 4. Non-Residential DSM Program Cost Benchmarks Rank State/ Province Program Administrator Data Type Program Name Year 2016 CAD/ kWh 1 BC BC Hydro Actual C&I Distribution Rate Structures 2013 $0.00 2 MB Manitoba Hydro Actual Bioener...
AI summary Table 4 presents non-residential DSM program cost benchmarks from various provinces, including Nova Scotia's EfficiencyOne programs, highlighting cost per kWh for different initiatives from 2013 to 2018.
1 This review finds that: - 2 The EfficiencyOne portfolio ranks among the highest in DSM 3 spending per capita and spending per customer - 4 EfficiencyOne has the most expensive programs in $ per first year 5 kWh - 6 EfficiencyOne's actual...
AI summary This review highlights that EfficiencyOne's Demand Side Management (DSM) programs have high per capita and per customer spending, with the most expensive programs in terms of cost per kWh. Actual spending and energy savings have deviated significantly from planned values, as illustrated in Table 5.
10 Table 5. Comparison of DSM Program Costs in Canada ACTUAL 2015 PLAN DSM SPEND PROVINCE YEAR $DSM/CAPITA $DSM/CUSTOMER $DSM/CAPITA $DSM/CUSTOMER NOVA SCOTIA 2014 41.05 77.21 41.37 77.81 RITISH COLUMBIA 2014 25.97 62.82 31.96 77.29 MANITO...
AI summary Table 5 compares DSM program costs in Canada across provinces, showing Nova Scotia's 2014 DSM costs per capita and per customer, along with the 2015 plan's projected costs. Other provinces like British Columbia, Manitoba, and Quebec are also included with their respective years and cost metrics.
16 Range of Scenarios Considered - 18 Q. WHAT RANGE OF DSM PROGRAM TYPES DID EFFICIENCYONE 19 CONSIDER? - 20 A. According to Company IR-12(b) the only programs considered by 21 EfficiencyOne were the six included in the final proposal, alo...
AI summary EfficiencyOne considered only a limited range of DSM program types and expenditure levels in its proposal, excluding many low-cost programs and not conducting quantitative analysis on demand response programs. The expert testimony suggests that a broader range of programs and expenditures should have been considered for a more cost-effective and balanced portfolio.
1 Q. COULD YOU PLEASE ILLUSTRATE THE CONSIDERATION OF 2 ALTERNATE PROGRAM ASSUMPTIONS AND EXPENDITURE 3 LEVELS? 4 A. Yes. In order to illustrate the potential impact of considering alternate 5 policy and program assumptions, ICF and NSP de...
AI summary The witness explains that ICF and NSP developed alternate scenarios using EfficiencyOne's ELRAM model to assess the impact of different program assumptions, including the exclusion of non-cost-effective measures. The witness argues that including a large number of non-cost-effective measures is not justified.
1 Scenario B: Which is the same as Scenario A and produces similar 2 energy savings, with the exception that program 3 implementation costs are allowed to vary plus or minus 20% 4 relative to the EfficiencyOne assumptions. In addition 5 in...
AI summary Scenario B allows program implementation costs and incentive costs to vary within a +/-20% range relative to EfficiencyOne assumptions, with specific exceptions for solar and fridge/freezer recycling incentives. This leads to a range of participation rates and costs, from which the least expensive option is selected as the preferred portfolio.
hodology and a 21 distribution of potential outcomes is developed. The optimum 22 value from this distribution (i.e., the least expensive) is 23 chosen as the preferred portfolio for this scenario. 1 2 Scenario C: The "NS Power Alternate S...
AI summary The document outlines four scenarios for energy efficiency planning, including the 'NS Power Alternate Scenario' and modifications to target energy savings and participation floors. These scenarios are analyzed using the ELRAM model, with results summarized in Table 6.
Table 6. Summary of Alternate DSM Scenarios Scenario Assumption Changes Three Ye ar Impacts Name Assumption Changes GWH MW $M TRC E1 None 405.9 62.5 $ 121.5 2.0 Α Eliminate TRC's < 1.0 387.0 59.8 $ 110.0 2.2 Eliminate TRC's < 1.0 В Allow i...
AI summary Table 6 outlines various Demand Side Management (DSM) scenarios with different assumptions and their impacts on energy savings, costs, and TRC. Scenario A, which eliminates non-cost-effective measures, reduces portfolio costs by ~10% with a small reduction in energy savings.
The TRC benefit cost ratio also improves from 2.0 to 2.2. The impact of permitting reasonable variations in program costs and incentives (Scenario B) is to permit slightly lower energy savings and program costs relative to Scenario A. The...
AI summary The TRC benefit cost ratio improves from 2.0 to 2.2. Scenario B allows for slightly lower energy savings and program costs compared to Scenario A. Scenario C provides 279 GWh and 33.0 MW of savings at a cost of $65.4 million. The analysis relies on ELRAM's participation forecasting algorithms to predict customer response to different program offerings and incentive levels.
1 Table 7. Summary of Scenario C (Company's Alternate Scenario) Impacts Cumulative Cost ($Millions) Peak Demand (MW) Cumulative (GWh) TRC Ratio Program Name E1 Case C % Diff. E1 Case C % Diff. E1 Case C % Diff. E1 Case C % Diff. RES‐Applia...
AI summary Table 7 presents the impacts of Scenario C, the company's alternate scenario, on various programs and enabling strategies. It shows cumulative costs, peak demand, and cumulative energy usage for different program categories, highlighting significant differences in cost and demand reductions compared to the baseline (E1). The TRC ratio also shows an increase in some cases.
1 Table 8. Summary of Scenario D Impacts Cumulative Cost ($Millions) Peak Demand (MW) Cumulative (GWh) TRC Ratio Program Name E1 Case D % Diff. E1 Case D % Diff. E1 Case D % Diff. E1 Case D % Diff. Efficient Products (Res) $ 7.83 $ ‐ 4.47...
AI summary Table 8 summarizes the impacts of Scenario D on various programs, showing reductions in cumulative costs, peak demand, and energy consumption compared to the baseline (E1). The table highlights the percentage differences in cost, demand, and energy usage across different programs, with overall reductions of up to 51% in cumulative costs and 25% in energy consumption.
11 Q. HOW DO YOU RECOMMEND THE UARB PROCEED? 12 A. I recommend that EfficiencyOne be directed to engage with NSP to 13 consider a broad range of program types and program expenditures, that 14 consider trade-offs between various policy obj...
AI summary The expert recommends that EfficiencyOne collaborate with NSP to evaluate diverse program types and expenditures, balancing policy objectives like rate impact, equity, and long-term resource needs. This process aims to ensure the UARB's approval of DSM portfolios reflects balanced, substantiated decisions.
13 Adequacy of the Description of the Scope of Services 14 15 Q. WHAT DESCRIPTION OF THE PROPOSED PROGRAMS AND SCOPE 16 OF WORK IS PROVIDED BY THE APPLICATION? 17 A. The most detailed description of the proposed programs is provided in 18...
AI summary The description of proposed programs in the application is criticized for being too brief and lacking necessary details to assess appropriateness, track implementation, or ensure delivery of promised activities. The response highlights the need for more detailed program descriptions and budget information to support prudence evaluation and contract development.
- 20 A description of the measures to be included in the program, including 21 specification of the qualifying efficiency level(s) and assumed baseline 22 technology 1 A description of the incentive to be provided, including the dollar 2...
AI summary The text outlines the requirements for describing the measures included in a program, focusing on the specification of efficiency levels, baseline technologies, and the structure of incentives, including their amounts, recipients, and conditions.
- 10 A description of the target market, including size and key 11 characteristics - 12 A description of any activities to recruit, support, monitor, and perform 13 QA/QC on trade allies or other market participants - 14 A count of all maj...
AI summary The text outlines requirements for describing the target market, activities for recruiting and supporting market participants, program achievements, marketing budgets, staffing plans, and metrics for energy savings and participation by measure.
- 22 Annual budget detail, including at least the following categories: 23 incentives (cash), incentives (free/discounted services), administration, 1 marketing, EM&V, QA/QC, application/incentive processing, IT, and 8 Expenditure by cat...
AI summary The text discusses the need for detailed annual budget reporting, including categories like incentives and administration, and recommends quarterly filings for certain data to monitor the development of the DSM resource effectively.
1 Appropriateness of the Requested Flexibility 2 3 Q. EFFICIENCYONE REQUESTS THE FLEXIBILITY TO MAKE 4 SIGNIFICANT CHANGES TO THE APPROVED PLAN (INCLUDING 5 ACTIONS SUCH AS ADDING A NEW PROGRAM, TERMINATING A 6 PROGRAM, AND INCREASING/DECR...
AI summary EfficiencyOne requests flexibility to make significant changes to the approved DSM plan without requiring approval from NSP and the UARB. The response argues this would give EfficiencyOne too much discretionary control, risking the effectiveness of the DSM resources and potentially affecting equity, rates, and costs. Most jurisdictions require UARB review for such changes.
18 change program designs, budget, or goals – and many provide no 1 terms of the Agreement. Further, I recommend against attaching the 2 "program change" process to the APR process, since this may 3 unnecessarily delay important revisions....
AI summary The text discusses the need for flexibility in program designs, budgets, and goals, suggesting a mechanism to address this. It outlines specific triggers for flexibility, such as changes exceeding 5% in energy savings or budget, and proposes a process involving the UARB and NSP for approval.
5 Performance Standards, Annual vs. 3-year Goals, and Remedies - 7 Q. WHAT PERFORMANCE TARGETS DOES EFFICIENCYONE PROPOSE 8 TO ESTABLISH FOR THE PROPOSED PROGRAMS? - 9 A. EfficiencyOne proposes two "Performance Targets": 1) cumulative annu...
AI summary EfficiencyOne proposes performance targets for its programs, including cumulative annual energy and demand savings measured over a three-year period (2016-2018), with a 90% threshold for meeting targets. It also plans to report on additional program indicators such as incremental savings, lifetime savings, ratepayer benefits, spending, and customer satisfaction annually.
1 Table 9. Comparison of Performance Targets and Indicators Reporting Level Performance Metric Unit E1 ICF Energy Savings Annual Incremental (each year) GWh ○ ● Cumulative Annual (over 3 years) GWh ● ● Lifetime Savings GWh ○ ○ Peak Demand...
AI summary Table 9 compares performance targets and indicators for Energy Savings, Peak Demand Savings, and other metrics across different reporting levels (Portfolio and Program) for E1 and ICF. It outlines which metrics are used as annual performance indicators and whether they have targets.
ENERGY EFFICIENCY PROGRAMS, POLICY, AND IMPLEMENTATION For a confidential Southwestern electric utility, provided a detailed assessment of DSM cost recovery mechanisms including financial modeling of alternative DSM cost recovery, lost mar...
AI summary ICF International provided energy efficiency and DSM program analysis, cost recovery modeling, regulatory filings, and stakeholder engagement for multiple utilities and states, including Entergy, Maryland Energy Administration, Hawaii Electric Light Company, and others. Services included DSM potential studies, rate design assessments, and shareholder incentive mechanisms.
Attachment A Page 2 of 6 2016-2018 DSM NS Power Evidence Appendix A Page 45 of 100 Developed DSM program filings (including DSM potential, detailed program designs, regulatory filing and benchmarking documents, and full implementation serv...
AI summary The text details Mr. Pickles' work on demand-side management (DSM) programs for multiple utilities, including regulatory filings, energy efficiency initiatives, and financing programs. Projects span program design, cost-effectiveness analysis, and evaluations for utilities like Exelon, Delmarva Power, and Maui Electric, with a focus on compliance, implementation, and regulatory engagement.
Attachment A Page 3 of 6 2016-2018 DSM NS Power Evidence Appendix A Page 46 of 100 For multiple clients, prepared an analysis of innovative DSM in a competitive environment. Mr. Pickles provided a summary and analysis of innovative approac...
AI summary Mr. Pickles conducted analyses of demand-side management (DSM) programs for multiple clients, including assessments of rate impacts, rebate/loan program comparisons, and design of energy efficiency rate structures (e.g., time-of-use, interruptible rates). Work involved evaluating effectiveness, equity, and regulatory compliance across utilities in Wisconsin, Indiana, Hawaii, and Guam.
Review of Nova Scotia's Energy Savings Portfolio April 8, 2015 Submitted to: Nova Scotia Power Submitted by: ICF International 300-1090 Homer Street Vancouver, British Columbia V6B 2W9 Tel: +1 778.375.2347 Fax: +1 778.375.2301 canada@icfi....
AI summary A 2015 review of Nova Scotia's Energy Savings Portfolio, submitted by ICF International to Nova Scotia Power, evaluates energy efficiency programs under the 2014 Integrated Resource Plan (IRP) and Energy Efficiency Conservation Agreement (EECA). The analysis focuses on Demand Side Management (DSM) and regulatory frameworks involving the Nova Scotia Utility and Review Board (NSUARB).
Purpose The following report reviews Efficiency Nova Scotia's energy savings portfolio in the context of other electricity demand side management (DSM) portfolios in the region with a focus on Canada. The report is intended to assist Nova...
AI summary This report evaluates Efficiency Nova Scotia's energy savings portfolio alongside regional DSM initiatives, aiming to support Nova Scotia Power Incorporated's (NSPI) DSM efforts. It focuses on Canada's electricity demand management context and NSPI's pursuit of DSM strategies.
Background Through the "Electricity Efficiency and Conservation Restructuring (2014) Act", which amended the Public Utilities Act (Nova Scotia) ("Act"), the design and implementation of DSM programs have now become the responsibility of a...
AI summary The 2014 Electricity Efficiency and Conservation Restructuring Act amended Nova Scotia's Public Utilities Act, transferring DSM program responsibility to franchise holders effective 2015. Efficiency Nova Scotia Corporation (ENSC) assumed this role during the 2015 transition year, as outlined in Section 79C(2) of the Act.
Context and Limitations The unique nature of DSM programs (given utilities and program administrators with differing objectives, between individual programs within a single program administrator, between outwardly similar programs at diffe...
AI summary The text discusses challenges in evaluating Demand Side Management (DSM) programs due to differences in design, objectives, and metrics across utilities and program administrators. Variations in program structure, customer demographics, and regulatory environments complicate peer group analysis. Metrics remain unadjusted for factors like accounting practices and weather zones, limiting comprehensive comparisons.
Organization of this Report Following the outline of Scope (Section 2) and Approach (Section 3), this report presents the summary Results of the Research (Section 4) and closes with a Discussion of Efficiency Nova Scotia's Energy savings P...
AI summary This report outlines its structure, including sections on Scope, Approach, Research Results, and a discussion of Efficiency Nova Scotia's energy savings portfolio. It emphasizes the organization of findings and analysis related to energy efficiency initiatives.
Summary of Insights - The ENSC portfolio ranks highest on the list of jurisdictions reviewed for DSM spend per capita and per customer. - ENSC has the highest first year cost per kWh of energy savings of the jurisdictions reviewed. - Withi...
AI summary ENSC leads Canada in DSM energy savings and per capita spend but has high first-year costs per kWh. Nova Scotia plans the highest electrical DSM investment relative to energy sales. Despite industrial sector's cost-effectiveness, ENSC lacks targeted programs. ENSC's diverse DSM portfolio includes costly elements, and performance variances may impact system planning.
2 Scope The following DSM program administrators were chosen for research. While mostly Canadian administrators were chosen, Efficiency Maine was added due to proximity to NS. A cross section of sizes, maturities, regulatory environments a...
AI summary The scope section outlines the selection of DSM program administrators across Canada, including Efficiency Maine for proximity to Nova Scotia. Key data points researched include utility sales, DSM savings, and program performance. A complete dataset was not found due to limited public information availability.
4 Results of the Research The following exhibits present a consolidated view of the research findings: - Exhibit 1: DSM Program Administrator Actual and Planned $DSM/capita and $DSM/customer - Exhibit 2: 2015 First Year Cost Comparison ($/...
AI summary The research findings show that Nova Scotia's DSM program expenditure per capita and per customer in 2015 was higher than other jurisdictions reviewed. Exhibits provide data on DSM program administrator costs, energy savings, and cost-effectiveness. Nova Scotia's DSM portfolio is discussed in detail in Section 5 of the research.
Exhibit 1: DSM Program Administrator Actual and Planned $DSM/capita and $DSM/customer5,6,7 ACTUAL DSM SPEND 2015 PLAN DSM SPEND PROVINCE YEAR $DSM/CAPITA $DSM/CUSTOMER $DSM/CAPITA $DSM/CUSTOMER NOVA SCOTIA 2014 41 .05 77.21 41 .37 77.81 BR...
AI summary Exhibit 1 provides a comparison of actual and planned demand-side management (DSM) spending per capita and per customer across various provinces in Canada, including Nova Scotia, British Columbia, Manitoba, and others. The exhibit highlights spending figures for 2014 and earlier years, with Exhibit 2 detailing first-year costs for 2015.
Exhibit 2: 2015 First Year Cost Comparison ($/kWh of Planned Savings)8,9, 10 A better representation of the cost per kWh would factor in the program administrator's discount rate and consider the average measure life of the various measure...
AI summary The exhibit compares the 2015 first-year costs per kWh of planned energy savings across different provinces. It notes that ENSC, BC Hydro, and Efficiency Maine use different metrics to calculate cost per kWh, with ENSC having some of the highest costs. The exhibit also includes weighted averages and upper and lower cost limits based on planned savings.
anies is presented for a six year period (2015 – 2020). 9 The DSM Plan for Manitoba Hydro includes electricity and gas savings. Only the electricity DSM has been considered in this report. 10 EfficiencyOne and Efficiency Maine have not bee...
AI summary The text discusses the evaluation of demand-side management (DSM) programs across various jurisdictions, highlighting Nova Scotia's leadership in DSM energy savings as a portion of energy sales. It also notes the exclusion of certain programs and data sources from the analysis and provides context on factors influencing energy savings and spending variations.
being offered, the policy and legislation in effect, the avoided cost and the conservation culture of the region. 15 This exhibit uses electricity sales from the most recent year reported. 16 DSM Plan for Efficiency New Brunswick presents...
AI summary This text discusses the allocation of DSM costs in Nova Scotia, highlighting that industrial customers, despite contributing significantly to sales, only account for a small portion of DSM program participation and cost recovery. It suggests that a combined BNI and industrial program may be influencing participation rates.
6/17). Similarly, the DSM Plan for Ontario is presented for a six year period (2015 – 2020). 20 EfficiencyOne and Efficiency Maine have not been included in the calculation of the average. Exhibit 7: 2015 Sector Breakdown of the Program Im...
AI summary The text discusses the structure and scope of Demand Side Management (DSM) plans in various jurisdictions, noting that Efficiency Nova Scotia's BNI programs serve both commercial and industrial customers and that ENSC offers one of the most comprehensive DSM portfolios in Canada, which may influence higher initial program costs.
Exhibit 8: A Categorization of DSM Program Offerings across Jurisdictions 21,22 cotiv stal dr o SaskP ,48 , O .ec ' th maine percentage of rotal ٥,, wer Pak. CIES Quebec vet 'exl ! th Maine Perentage of Total 14 lo. The o' arii o, va in 94...
AI summary Exhibit 8 categorizes Demand Side Management (DSM) program offerings across various jurisdictions, highlighting the prevalence of different types of programs such as prescriptive, existing home, new home, low income, appliance retirement, and demand response programs. It also includes statistics on the percentage of total programs offered in different regions.
5 Discussion of Efficiency Nova Scotia's Energy Savings Portfolio RatepayerͲfunded DSM programs have been delivered to Nova Scotia's electricity customers since 2008. The first three years of programming were administered by NSPI and, in l...
AI summary Nova Scotia's electricity customers have had ratepayer-funded DSM programs since 2008, initially administered by NSPI and later transferred to ENSC (now EfficiencyOne). ENSC, a government-created third-party entity, ensures cost-effective electricity savings for customers.
History of Results Nova Scotia began increasing its investment in DSM program delivery in 2008. In the first year of program activity the reported annual savings were 42 GWh, and by 201324, when program activities had fully ramped up, cumu...
AI summary Nova Scotia began increasing its investment in DSM programs in 2008, resulting in energy savings that grew from 42 GWh in 2008 to 611 GWh by 2013. Exhibits show cumulative energy and demand savings, as well as increasing utility costs of saved energy and higher DSM installation costs compared to other Canadian jurisdictions.
Programs and Pricing The proposed mix or DSM activities in 2015 leverages a diverse mix of approaches, channels and partners and includes "enabling strategies".
AI summary The proposed 2015 DSM activities include a diverse mix of approaches, channels, and partners, with an emphasis on enabling strategies to support program implementation.
ENSC's DSM portfolio includes residential and business, nonͲprofit, and institutional (BNI) programs: Residential34 BNI35 Efficient Product Rebates (includes components ƒ marketed as Instant Savings and Appliance Retirement); Existing Resi...
AI summary ENSC's DSM portfolio includes residential and BNI programs, with a focus on efficient product rebates and direct installation. The portfolio is 31% residential and 69% commercial, though no targeted industrial programs exist despite the 2015Ͳ2040 DSM Potential Study indicating industrial savings as the most cost-effective.
The ENSC portfolio ranks highest on the list of jurisdictions reviewed for DSM spend per capita and per customer and also appears to have the highest DSM expenditure relative to savings. Exhibit 15 shows the verified cost per kilowattͲhour...
AI summary The ENSC portfolio has the highest DSM spend per capita and per customer, with Exhibit 15 showing verified cost per kilowatt-hour of ENSC's programs over the past three years. More detailed cost effectiveness tests are required to evaluate individual measures and programs within the portfolio.
Appendix A DSM Program Implementer Profiles Efficiency Nova Scotia Business Structure Franchise DSM Funding Mechanism DSM Cost Recovery Rate, Rate Smoothing Adjustment Population Served Number of Customers Planned DSM Savings C, 31% 942,70...
AI summary This appendix outlines the DSM Program Implementer Profiles for Efficiency Nova Scotia, detailing its business structure, funding mechanisms, customer base, and DSM savings targets. It includes financial data such as planned and actual DSM costs, savings, and energy usage metrics.
40 Nova Scotia Power email from Nicole Cadek, FW: Most recent publically available sales actuals, February 5, 2015 41 Efficiency Nova Scotia Corporation, Evidence of ENSC As DSM Administrator – Revised July 3, 2014
AI summary This document references an email from Nova Scotia Power and evidence submitted by Efficiency Nova Scotia Corporation regarding their role as a Demand Side Management (DSM) administrator. The documents are part of a regulatory proceeding.
42 Nova Scotia 2015 DSM Plan M06247 Decision BC Hydro Business Structure Crown Corporation DSM Funding Mechanism Deferred for future rate recovery Planned DSM Savings R, 16% I, 52% Population Served 4,631,302 Year DSM Started 1989, 200844...
AI summary The 2015 DSM Plan by BC Hydro outlines funding mechanisms, savings goals, and customer participation across residential, commercial, and industrial sectors. It includes deferred rate recovery, savings targets, and various programs such as refrigerators buy-back, lighting incentives, and smart meter infrastructure.
44 Following the 2007 Long Term Acquisition Plan (LTAP), BC Hydro reset the reporting of energy savings. 45 BC Hydro Quick Facts, https://www.bchydro.com/content/dam/BCHydro/customerͲ portal/documents/corporate/accountabilityͲreports/finan...
AI summary The text references BC Hydro's 2007 Long Term Acquisition Plan (LTAP), which led to a reset in the reporting of energy savings. It also cites various documents, including Quick Facts, Revenue Requirements Rate Applications, and Service Plans, related to BC Hydro's operations and regulatory filings.
SaskPower Business Structure Crown Corporation DSM Funding Mechanism Rate Recovery Population Served Number of Customers 1,106,200 500,922 Year DSM Started Last year of IRP 2008 Internal Process Planned DSM Savings I, 26% R, 33% C, 41% Res...
AI summary The document discusses SaskPower's demand-side management (DSM) funding mechanism and related metrics, including population served, planned DSM savings by sector, utility sales, DSM plan costs, and savings ratios. It provides data from 2013 to 2015, showing the cost per capita and customer, as well as savings percentages.
51 Final Independent Report for the Saskatchewan Rate Review Panelon SaskPower's 2014Ͳ2016 Rate Plan, Forkast Consulting, 2014 Manitoba Hydro Business Structure Crown Corporation DSM Funding Mechanism Profits on export, rates targeted at c...
AI summary This document provides a summary of Manitoba Hydro's business structure, DSM funding mechanism, and energy efficiency programs. It includes data on customer numbers, DSM savings, utility sales, and DSM plan costs and savings. The document references a 2014 annual report and provides financial and operational metrics related to energy efficiency initiatives.
57 Manitoba Power 2013Ͳ2016 Power Smart Plan, OntarioͲIndependent Electricity System Operator (IESO) Business Structure "IESO works collaboratively with local distribution companies and other partners to deliver conservation programs throu...
AI summary The document outlines the Ontario Independent Electricity System Operator (IESO) and its role in delivering conservation programs through a systems benefit charge. It details the IESO's business structure, DSM funding mechanisms, customer numbers, and energy efficiency programs. The 2015-2020 DSM plan is outlined with financial figures and savings targets.
65 Ibid. Hydro Quebec Business Structure Crown Corporation DSM Funding Mechanism Rate Recovery Population Served Number of Customers 8,154,000 4,142,000 Planned DSM Savings Year DSM Started Last year of IRP 2013 Not Available R, 34% I, 34%...
AI summary This table presents information about Hydro Quebec's business structure, demand-side management (DSM) funding mechanism, and key DSM metrics including planned savings, customer numbers, and cost per capita and per customer. It also references annual reports and other data sources for further details.
69 Plan Gobal En Efficacity Energetique Budget 2015, http://publicsde.regieͲenergie.qc.ca/projets/282/DocPrj/RͲ3905Ͳ2014ͲBͲ 0038ͲDemandeͲPieceͲ2014_08_01.pdf, Accessed January 30, 2015 Efficiency New Brunswick Business Structure Crown Corp...
AI summary The document compares energy efficiency programs in New Brunswick and Nova Scotia, focusing on the DSM funding mechanism, customer numbers, and efficiency targets. It highlights differences in program structures, funding, and performance metrics between the two regions.
73 The 2014/15Ͳ2016/17 Energy Efficient Plan prepared for the New Brunswick Department of Business Structure Private DSM Funding Mechanism Rate Recovery Population Served 510,000 Number of Customers 256,000 Cumulative DSM Savings Year DSM...
AI summary The document outlines the 2014/15Ͳ2016/17 Energy Efficient Plan for New Brunswick, including funding mechanisms, customer statistics, and DSM savings. It provides data on population served, customer numbers, and cumulative savings, as well as financial figures related to DSM plans and energy sales.
77 Ibid. Efficiency Maine Business Structure Independent Administrator governed by a stakeholder Board of Trustees with oversight from the Maine Public Utilities Commission. DSM Funding Mechanism System Benefits Charge Population Served 1,...
AI summary The text provides a table with details about Efficiency Maine's business structure, DSM funding mechanism, and key metrics such as population served, customer numbers, and DSM savings. It also includes data on utility sales and DSM plan costs and savings.
orts/bcͲhydroͲannualͲ reportͲ2013.pdf, accessed January 28, 2015. BC Hydro Conservation Potential Review 2007ͲCombined Potential Report BC Hydro F2015 to F2016 Revenue Requirements Rate Application, https://www.bchydro.com/content/dam/BCHy...
AI summary The document lists regulatory filings, reports, and evaluations related to energy efficiency, resource planning, and revenue requirements by BC Hydro and Efficiency Nova Scotia Corporation. Key topics include demand-side management (DSM), integrated resource planning (IRP), and regulatory proceedings. Entities involved include BC Hydro, Efficiency Nova Scotia Corporation, and Econoler.
MeasureLevel Results for Baseline E1 and Optimized Case D Scenarios Pro m T gra ype Sub ͲPro gra m Me asu re Mo del Bui ldin g T ype End Use Cat ego ry Sto ck T tme nt rea Dem and (kW ) Ene rgy (M Wh ) Tot l. Cos al I mp t ($ ) usin eba 1...
AI summary The document presents MeasureLevel results comparing baseline E1 and optimized Case D scenarios for energy efficiency programs, including demand-side management rebates and lighting controls in commercial office buildings. The data includes metrics such as demand (kW), energy (MWh), and total cost impact ($).
(Tables to be populated by E1, based on the final 2016‐2018 DSM Plan as approved by the UARB.) Total 2016-2018 Program and Sub‐Component Cumulative Annual Net Energy Savings at Generator Cumulative Annual Net Demand Savings at Generator Un...
AI summary The document outlines tables for energy efficiency programs under the 2016–2018 DSM Plan approved by the UARB, including residential, business, and enabling strategies sectors, with metrics such as energy savings and unit costs. These tables are to be populated by E1.
Schedule B
AI summary Schedule B from the Nova Scotia regulatory proceeding document lists acronyms and their expansions relevant to energy efficiency, utility regulation, and resource planning. It includes organizations, programs, and regulatory frameworks involved in Nova Scotia's electricity sector.
The figure below identifies the Contract Price allocated for each year of the Term. Year $M 2016 2017 2018 Total The schedule below provides the current projection of the cash requirement profile of EfficiencyOne over the term of the 2016‐...
AI summary This text outlines the allocation of the Contract Price for each year of the 2016-2018 Agreement and provides a projected cash requirement profile for EfficiencyOne. It also specifies that any unspent funds from previous years are retained by EfficiencyOne, with the surplus deducted from the current year's cash requirements.