Matter: E-ENS-R-15 - EfficiencyOne Application for approval of a Supply Agreement for Electricity Efficiency and Conservation Activities between Efficiency One and Nova Scotia Power Inc.- NSPI - 2016-2019 DSM Plan IN THE MATTER OF AN APPLICATION for Approval of a Supply Agreement for electricity efficiency and conservation activities between EfficiencyOne and Nova Scotia Power Incorporated, the establishment of a final agreement between the parties, and approval of a 2016-2018 Demand Side Management Resource Plan
7 passages 4 documents

Energy Efficiency Resource Standards across all matters →

E-1EfficiencyOne Application - Revised Application see Exhibit E-43 1 passage
Preamble p. pp. 224-226
published (this protects the franchisee from TRB changes that are outside of its control). The measures' estimated useful lives (EUL) used in the TRB calculation are also based on ex-ante values, which are regularly updated. Figure 3: Verm...

AI summary The document discusses the Total Resource Benefits (TRB) calculation, emphasizing that the estimated useful lives (EUL) used are based on ex-ante values and are regularly updated. It also highlights that energy and peak savings make up the majority of performance targets, with a weighted contribution of 59%, while TRB accounts for 30%.

E-22014 Electricity Demand Side Management Plan Evaluation Reports 4 passages
Table 8: Reasons for Participating p. pp. 29-30
Table 8: Reasons for Participating 2012 2014 Motivations Most Important Motivation Second Most Important Motivation Most Important Motivation Second Most Important Motivation Sample Size 56 56 27 27 Save on energy costs/bills 55% 32% 59% 2...

AI summary Table 8 presents data on participants' motivations for joining energy efficiency programs in 2012 and 2014. The primary motivation was saving on energy costs, with a significant decline in the percentage of participants citing this reason over time. Other motivations included taking advantage of program incentives, updating equipment, and environmental concerns.

5.1.2 Commercial Lighting Measures p. pp. 35-36
5.1.2 Commercial Lighting Measures A total of 25 on-site visits were conducted for the lighting measures category; however, as mentioned above, three projects were eliminated from the data analysis because they were incomplete at the time...

AI summary The document discusses the evaluation of commercial lighting measures, including on-site visits, adjustments to tracked savings, and the impact of ballast factors on energy savings calculations. Over 80% of projects involved LED measures, and the evaluation highlights the importance of considering ballast factors in calculating energy savings.

Table 1: Comparison of Tracked and Evaluated Savings at the Generator p. p. 36
Table 1: Comparison of Tracked and Evaluated Savings at the Generator Initial Gross Savings Adjusted Gross Savings Net-to-Gross Ratio (NTGR) Net Savings Energy Savings Tracked Savings from ENSC 7.122 GWh 7.122 GWh 1.00 7.122 GWh Evaluation...

AI summary Table 1 compares tracked and evaluated energy and peak demand savings from ENSC and the Econoler team. Evaluated savings are 6.5% and 3.9% lower than tracked savings, mainly due to adjustments in one LEED project. ENSC included a diversity factor in peak demand calculations this year, reducing the need for large adjustments.

done by the third-party contractor. Survey results showed that participants encountered issues with third-party contractors and the quality of their work. ENSC already requires that the DAs follow up with customers after installation to ensure their satisfaction. The Evaluator recommends that ENSC itself (instead of the DAs) make some follow-up phone calls with a certain portion of the participants so that p. pp. 77-78
sting cooling systems. This would enable more accurate savings calculations. The tracking report should also contain all hot water heat pump parameters required to perform energy savings calculations. 2014 BES-R5. Develop a process for val...

AI summary The document discusses the need for a validation process to ensure the accuracy of energy savings calculations in the Business Energy Solutions program. It highlights issues with third-party contractors and the need for ENSC to directly follow up with participants to ensure satisfaction and accurate tracking of energy savings parameters.

E-8Evidence of Nova Scotia Power Inc. 1 passage
MeasureLevel Results for Baseline E1 and Optimized Case D Scenarios p. p. 120
MeasureLevel Results for Baseline E1 and Optimized Case D Scenarios Pro m T gra ype Sub ͲPro gra m Me asu re Mo del Bui ldin g T ype End Use Cat ego ry Sto ck T tme nt rea Dem and (kW ) Ene rgy (M Wh ) Tot l. Cos al I mp t ($ ) 302 En y R...

AI summary The document presents MeasureLevel results comparing Baseline E1 and Optimized Case D scenarios, providing data on demand, energy usage, and cost impacts for various programs and measures, including refrigeration and cooling systems in commercial and institutional buildings.

62379Closing Submission - Nova Scotia Power Inc. 1 passage
8.0 NS POWER SYSTEM REQUIREMENTS p. p. 51
8.0 NS POWER SYSTEM REQUIREMENTS As noted above, the evidence before the Board is that no additional DSM is required by NS Power during the 2016-18 Contract Period for compliance with Nova Scotia's Renewable Electricity Standards or to mee...

AI summary NS Power states that no additional DSM is required during the 2016-18 Contract Period but proposes a DSM plan with 100 GWh annual savings. E1 challenges this, but the evidence supports Scenario D, which aligns with NS Power's proposal. A discussion between MR. CLARKE and MR. AGUINAGA clarifies that Scenario D is not included in the chart.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →