Topic/Matter Intersection

Topic:"Financial Instruments" in M06733

Matter: E-ENS-R-15 - EfficiencyOne Application for approval of a Supply Agreement for Electricity Efficiency and Conservation Activities between Efficiency One and Nova Scotia Power Inc.- NSPI - 2016-2019 DSM Plan IN THE MATTER OF AN APPLICATION for Approval of a Supply Agreement for electricity efficiency and conservation activities between EfficiencyOne and Nova Scotia Power Incorporated, the establishment of a final agreement between the parties, and approval of a 2016-2018 Demand Side Management Resource Plan
17 passages 12 documents

Financial Instruments across all matters →

E-1EfficiencyOne Application - Revised Application see Exhibit E-43 1 passage
(3) Accounting Standards p. pp. 242-244
(3) Accounting Standards EfficiencyOne prepares its financial statements in accordance with Canadian Accounting Standards for NPO' s. Management must ensure that the establishment of the reserves as presented meets these requirements. We h...

AI summary EfficiencyOne is preparing its financial statements according to Canadian accounting standards for non-profit organizations. A reserve fund is being established to cover potential severance costs, loss of funding, and external factors that may impact program offerings. The reserve balance of $9,003,018 for 2024 is deemed plausible, but it is recommended that the reserve components be reviewed annually and approved by the Board of Directors.

E-22014 Electricity Demand Side Management Plan Evaluation Reports 3 passages
Key Findings p. pp. 176-177
Key Findings A total of 66 participants took part in Residential Financing in 2014—with three of them taking part through Solar, 21 through HEA and 42 through Green Heat. The 2014 evaluation of Residential Financing demonstrated that this...

AI summary The 2014 Residential Financing pilot was successful in encouraging home improvements, with the zero-percent interest rate being a major motivator. Participants expressed high satisfaction with the process, though some issues with communication and loan disbursement were noted. Recommendations include increasing awareness and establishing a formal communication timeline.

4.2.1 Awareness and General Perceptions p. pp. 185-186
4.2.1 Awareness and General Perceptions Nearly all participants interviewed (8 of 10) each hired a contractor to complete their home improvements, with all 10 participants having first heard about the financing option from their contractor...

AI summary Most participants in the ENSC energy efficiency program learned about financing options from contractors or suppliers, with many expressing frustration over limited information disclosure. The zero-percent interest rate financing was a major motivator for participation, and few considered alternative financing options due to its rarity. Some participants faced issues due to misinformation from suppliers.

This Appendix presents all recommendations made by the Evaluator throughout this report as well as the sections from which the recommendations originated. p. p. 190
This Appendix presents all recommendations made by the Evaluator throughout this report as well as the sections from which the recommendations originated. Sections Recommendations 2 Increase awareness of the financing option. All 10 partic...

AI summary The appendix highlights a recommendation to increase awareness of the Residential Financing option offered by ENSC. Participants learned about the financing only after deciding on home improvements, suggesting a need for better promotion and information on the financing terms and conditions.

E-7E1 (NSPI) RIR-1 to RIR-47 1 passage
Section 759
.6% 86.6 88 86 1 1 2015 59.2 70.1% 84.5 85 84 1 0 Budgeted 13 The table above does not include EfficiencyOne’s On-Site Energy Managers (OEMs), as these 14 positions are not included in compensation expenses. The cost of OEMs is covered thr...

AI summary The text discusses the exclusion of EfficiencyOne’s On-Site Energy Managers (OEMs) from compensation expenses, as their costs are covered through incentives and reimbursements. It also references a 2016-2018 supply agreement for EECA and E1 responses to NSPI information requests.

E-8Evidence of Nova Scotia Power Inc. 1 passage
The figure below identifies the Contract Price allocated for each year of the Term. p. p. 120
The figure below identifies the Contract Price allocated for each year of the Term. Year $M 2016 2017 2018 Total The schedule below provides the current projection of the cash requirement profile of EfficiencyOne over the term of the 2016‐...

AI summary This text outlines the allocation of the Contract Price for each year of the 2016-2018 Agreement and provides a projected cash requirement profile for EfficiencyOne. It also specifies that any unspent funds from previous years are retained by EfficiencyOne, with the surplus deducted from the current year's cash requirements.

E-11NSPI (CA) RIRs to IR-1 to IR-41 - Redacted 1 passage
E1 Responses to NSPI Information Request (IR 35) p. p. 76
E1 Responses to NSPI Information Request (IR 35) Act ual Pro gra m Spe ndi ng inc lud ing ST Ful l H Act ual Pr ogr am Spe ndi wit h H ST ng Ad jus ted for IT Cs An l nua En erg y Sav ing s An l nua Dem and Red ion uct s Full HS T HS T a d...

AI summary This document provides a detailed table of actual program spending, energy savings, and demand savings from 2010 to 2018, including adjustments for HST and ITCs. The data reflects spending by Nova Scotia Power Inc. (NSPI) for demand-side management (DSM) programs and their impact on energy efficiency and demand reduction.

E-16NSPI (NSUARB) RIRs to IR-1 to IR-15 1 passage
Section 7 p. pp. 4-6
1 DSM Plan has an estimated cumulative NPV savings of $5.7 million more than the 2 Scenario D DSM plan over the life of the programs; however, the crossover point is 2029 3 as shown on the graph below. For the first 13 years of the period...

AI summary The Scenario D DSM plan shows higher cumulative NPV savings after 2029 compared to the existing DSM plan, but initial years show lower revenue due to reduced investment costs. The analysis uses avoided costs from long-term IRP model runs and NS Power has adopted hourly dispatch models for fuel forecasting.

62745Board Decision 2 passages
Preamble p. p. 0
This suggests that the targets could have been met with less spending. [74] The Board is also very concerned about the lack of rigor with respect to the determination of incentives. The Board is not satisfied that El presently has sufficie...

AI summary The Board is concerned about the lack of rigor in determining incentives for achieving savings targets and has reduced the Quantum Agreement amounts by 10% for 2016, 2017, and 2018. The Board also denied inflationary increases requested by E1 due to insufficient evidence linking NSPI's costs to general inflation.

Lagend: p. p. 0
Lagend: Filing has not historically triggered an automatic regulatory Filing has historically tr riggered a regulatory process 2015 Annual Progress Report End of March Summary of 2015 context, activities and milestones achieved Total inves...

AI summary The document outlines various reporting requirements and timelines for a regulatory proceeding, including annual progress reports, evaluation reports, and quarterly filings. These reports include details on program performance, financial statements, and analyses of rate and bill impacts.

63307Board Order 2 passages
4 Figure 1.2 - 2016 DSM Resource Plan Investment and Savings p. p. 44
4 Figure 1.2 - 2016 DSM Resource Plan Investment and Savings 2016 Investment ($ million) Lifetime Benefits ($ million)" Incremental Annual Net Energy Savings at Generator (GWh) Incremental Annual Net Demand Savings at Generator (MW) Total...

AI summary Figure 1.2 presents the 2016 DSM Resource Plan investment and savings, detailing program investments, lifetime benefits, and energy and demand savings across residential and non-residential sectors. It includes data on program costs, benefits, and savings metrics such as Total Resource Cost (TRC) and Program Administrator Cost (PAC).

Figure 1.4 - 2018 DSM Resource Plan Savings and Investment p. p. 44
Figure 1.4 - 2018 DSM Resource Plan Savings and Investment 2018 Investment ($ million) Lifetime Benefits ($ million)" Incremental Annual Net Energy Savings at Generator (GWh) Incremental Annual Net Demand Savings at Generator (MW) Total Re...

AI summary Figure 1.4 outlines the 2018 DSM Resource Plan Savings and Investment, showing the investment amounts, lifetime benefits, and energy and demand savings for various programs. The table includes data on residential and non-residential programs, as well as enabling strategies, with figures expressed in 2018 dollars.

62380Closing Submission - Efficiency One 1 passage
Compensation p. p. 60
Compensation The schedule below identifies the monthly payments (not including HST) by Nova Scotia Power Inc. (NSPI) to EfficiencyOne for the Contract Price of $116 million (in nominal dollars) over the term of the 2016-2018 Agreement for...

AI summary The text outlines the monthly payment schedule by Nova Scotia Power Inc. (NSPI) to EfficiencyOne under the 2016-2018 Agreement, which includes a Contract Price of $116 million for energy and demand savings. Payments are made monthly, excluding HST, and are due on the first day of each month.

631072016-2018 DSM Supply Agreement - Schedule E - Final with Track Changes 1 passage
c PAC is a benefit/cost ratio comparing lifetime benefits to ENS's costs. d Reflects ENS's planned participation by low income customers, per the 2015 DSM Resource Settlement Agreement. p. pp. 8-10
c PAC is a benefit/cost ratio comparing lifetime benefits to ENS's costs. d Reflects ENS's planned participation by low income customers, per the 2015 DSM Resource Settlement Agreement. Figure 1.3 - 2017 DSM Resource Plan Investment and Sa...

AI summary The document presents a 2017 DSM Resource Plan Investment and Savings table, highlighting various programs and their associated investments, benefits, and cost tests. It includes specific figures for residential and business programs, as well as enabling strategies, with data expressed in 2016-2017 dollars.

63307Board Order 1 passage
This Plan has been modified to comply with the Utility and Review Board (UARB)'s August 12, 2015 Decision, which set annual DSM investment amounts of $33.21 million, p. p. 44
This Plan has been modified to comply with the Utility and Review Board (UARB)'s August 12, 2015 Decision, which set annual DSM investment amounts of $33.21 million, 1 million million $34.02 and $34.92 for 2016, 2017, and 2018 respectively...

AI summary This document outlines modifications to a DSM Plan to comply with the UARB's August 12, 2015 Decision, which set annual investment amounts of $33.21 million for 2016, $34.02 million for 2017, and $34.92 million for 2018. It describes ENS's proposed programs and strategies for achieving energy and demand savings targets.

63791Grant Thornton Report - Financing Demand Side Management 2 passages
EfficiencyOne Statement of Operations and Changes in Fund Balance - Demand Side Management Fund For 2016, 2017 & 2018 p. p. 34
EfficiencyOne Statement of Operations and Changes in Fund Balance - Demand Side Management Fund For 2016, 2017 & 2018 Estimates Only. 2016 2017 2018 Revenue 36,900,000 37,800,000 38,800,000 Expenses Direct Costs Incentives 25,547,000 26,18...

AI summary The document presents the financial operations and fund balance changes for the EfficiencyOne Demand Side Management Fund from 2016 to 2018. It outlines revenue, direct costs, and other program and administrative expenses over the three-year period, with projected figures provided for each year.

Statement of Financial Position - Demand Side Management Fund For 2016, 2017 & 2018 p. p. 34
Statement of Financial Position - Demand Side Management Fund For 2016, 2017 & 2018 Estimates Only. 2016 2017 2018 Assets Cash 3,075,000 3,150,000 3,233,000 Liabilities Accounts Payable & Accrued Liabilities (approx. 1 month of expense) 3,...

AI summary The Statement of Financial Position for the Demand Side Management Fund for the years 2016, 2017, and 2018 shows cash balances and liabilities for each year. The cash and liabilities remain consistent across the years, with no fund balance reported.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →