REFERENCES Kleinschmidt (Kleinschmidt Associates). 2015. 2015 Sheet Harbour Hydro System Dam Safety Review. December 2015.
AI summary A reference to a 2015 dam safety review conducted by Kleinschmidt Associates for the Sheet Harbour Hydro System.
6.0 Facilities & Hygiene Cleaning/sanitizing supplies will be available at all Elliot Group sites and all personnel are encouraged to maintain a clean and healthy site. Handrails, door knobs, vehicles door handles and steering wheels, equi...
AI summary The document outlines hygiene and facility management practices at Elliot Group sites, including cleaning protocols, provision of disinfectants, portable toilets, and changes to break and water access procedures to ensure cleanliness and prevent cross-contamination among employees.
2.0 DESCRIPTION OF PROPOSED WORK, UNDERTAKING OR ACTIVITY NSPI is proposing refurbishment of the Ruth Falls Dam (the "Project"), located on the Sheet Harbour Hydro System in Sheet Harbour NS, in 2021. This work is necessary in order to add...
AI summary NSPI proposes to refurbish the Ruth Falls Dam to address structural and safety issues, in line with CDA guidelines. The project involves replacing stop-log bays with rubber dams and vertical lift gates, modifying spillway structures, and temporarily lowering the reservoir for construction. Fish conveyance systems will be dewatered during the work.
CONTINGENCY PLANNING Table 4 demonstrates the statistical flood peaks for the Ruth Falls Main Dam, from the 2008 Sheet Harbour Hydro System Flood Study.
AI summary Table 4 presents statistical flood peak data for the Ruth Falls Main Dam, derived from the 2008 Sheet Harbour Hydro System Flood Study.
Post‐Construction Monitoring NS Power will monitor the operation of the new dam structure as part of its regular bi‐annual dam inspection and maintenance program as well as weekly inspections conducted by Hydro Operations. NS Power does no...
AI summary NS Power plans to monitor the new dam structure through regular bi-annual inspections and weekly checks by Hydro Operations, and does not expect erosion or scour issues downstream.
5.1 OVERVIEW Once construction is complete, NS Power will monitor the operation of the new dam structure as part of its regular bi-annual dam inspection and maintenance program as well as weekly inspections conducted by Hydro Operations. T...
AI summary NS Power will conduct bi-annual and weekly inspections of the new dam structure and fish passage improvements post-construction. A two-year monitoring program will evaluate the effectiveness of these improvements, focusing on migration impacts and overall dam operation.
CI 50518 NSUIARB IR-12 Attachment 12 Page 420 of 576 REDACTED (CONFIDENTIAL INFORMATION REMOVED) A B C D E F42 Channel Connection & The most persistent surface water connection (outlet channel or pipe, ditch, or overbank water exchange) be...
AI summary The document discusses the identification of the most persistent surface water connection between an Area of Assessment (AA) and a downslope stream network, emphasizing the importance of considering all surface water connections regardless of freezing conditions and the use of topographic maps for determination.
N-8Midgard Evidence - Redacted
3 passages
5.2.5 Conclusion - Midgard is concerned that the Project remains exposed to several risk areas (environmental compensation - costs, archaeological costs, and geotechnical risks) that have the potential to cause additional overages to - Pro...
AI summary Midgard is concerned that the Project faces risks such as environmental compensation, archaeological, and geotechnical costs, which may lead to overages beyond current contingency allowances. Midgard suggests that if NS Power had analyzed a decommissioning option, it might have clarified the extent of potential cost overruns and their impact on the economic analysis favoring reinvestment.
M&A DUE DILIGENCE - § Technical due diligence of hydroelectric project portfolios in Canada, US and Internationally - § Risk profiling and asset valuation
AI summary The document outlines the scope of M&A due diligence, focusing on technical evaluation of hydroelectric project portfolios across multiple countries and risk profiling and asset valuation.
P R O F E S S I O N A L E X P E R I E N C E – H Y D R O E L E C T R I C CRANBERRY CREEK HYDROELECTRIC PROJECT ( 2023 to present) – A run-of river project in British Columbia's interior. Asset condition assessment and capital investment pri...
AI summary The text outlines the professional experience of an individual in hydroelectric projects, including advisory roles in asset assessments, project optimization, and technical advisory services in regulatory proceedings across Canada and Sierra Leone.
N-12Reply Evidence - Redacted
4 passages
1 4.0 DECOMMISSIONING 2 3 In its evidence, Midgard states: 4 …despite Project costs increasing by 113% and $8.2M, NS Power has not re-5 evaluated its decision to not consider a decommissioning option. Midgard 6 understands the stated justi...
AI summary Midgard argues that NS Power should have considered decommissioning the Ruth Falls Dam and Powerhouse, despite increased project costs, and that the NSUARB should have evaluated this option for ratepayer benefit. NS Power responded by analyzing decommissioning costs based on existing data and forecasts from 2025 to 2035.
22 Figure 4: Decommissioning Activities by Year Year Activity 2025 Development of the conceptual design for Ruth Falls main dam and powerhouse decommissioning including cofferdam design 2026-2028 Completion of the detailed design for the d...
AI summary This section outlines the timeline for decommissioning activities at Ruth Falls, including the development of conceptual design in 2025, detailed design and environmental assessment from 2026 to 2028, and demolition in 2029. The process involves consultation, baseline data collection, and environmental permitting.
CI 50518 – HYD – Ruth Falls Main Dam Refurbishment ATO – Reply Evidence Redacted 2030-2031 Sediment management and archaeological reconnaissance of the exposed shoreline. Sedimentation management is a large work scope during hydro decommis...
AI summary The document outlines decommissioning activities for the Ruth Falls Main Dam, including sediment management, environmental monitoring, and habitat restoration from 2030 to 2035. It also mentions the categorization of decommissioning costs.
CI 50518 – HYD – Ruth Falls Main Dam Refurbishment ATO – Reply Evidence Redacted - 1 with a broad range of accuracy ranging from -50 to +100 percent. Please refer to Appendix A for - 2 a detailed breakdown of the contingency and management...
AI summary The reply evidence argues that refurbishing the Ruth Falls Main Dam is the most economical option for NS Power, emphasizing that decommissioning would lead to higher costs for customers due to the need to replace lost renewable energy generation.
98138Board Decision
3 passages
IN THE MATTER OF THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF an application by NOVA SCOTIA POWER INCORPORATED for approval of an Authorization to Overspend in the amount of $8,201,086 on capital application project CI 50518 – HYD Rut...
AI summary Nova Scotia Power Inc. applied for an authorization to overspend on a dam refurbishment project, but the decision is held in abeyance until they obtain a Fisheries Act authorization. Once obtained, they must submit an amended application with a Net Present Value analysis comparing refurbishment and decommissioning options.
ated entirely to DFO requirements, so changes to the project cost and timeline would apply to all refurbishment options, as drawdown is the primary driver of the environmental permitting requirements. [55] NS Power also submitted that it a...
AI summary NS Power argues that changes in DFO requirements, including the Fisheries Act amendments, have impacted project timelines and costs for refurbishment and decommissioning. It emphasizes that it acted prudently in its original application and that updated cost estimates reflect revised requirements and scope.
3.4 Decommissioning Cost [74] When the Ruth Falls project was included in the 2019 ACE Plan, NS Power had two choices to address safety concerns arising from the related dam safety review: either decommission the dam or refurbish it. At th...
AI summary The Ruth Falls project's decommissioning cost was not chosen in 2019 due to higher costs compared to refurbishment. The refurbishment extends the dam's life by 50 years and maintains 7.2 MW of renewable power. However, ongoing capital investments and operating expenses are required. The document suggests that if decommissioning and procuring alternative power proved more cost-effective, it would have been in ratepayers' best interest.
98573Submissions - IG
3 passages
Delivered by E-mail Crystal Henwood Regulatory Affairs Officer/Clerk Nova Scotia Utility and Review Board 3rd Floor, 1601 Lower Water Street PO Box 1692, Unit "M" Halifax NS B3J 3S3 Dear Ms. Henwood: Re: M11927 - NSPI - CI 50518 – HYD Ruth...
AI summary The Industrial Group submits comments on M11927 regarding the Ruth Falls Main Dam Refurbishment ATO, addressing unit rates for offsetting, decommissioning, and reporting.
Background In its Application for Authorization to Overspend (" ATO" ), NSPI sought approval for an additional $8.21 million on corrective actions regarding the main dam representing more than a doubling of the original approval of $7.24 m...
AI summary NSPI sought approval for an additional $8.21 million in corrective actions for the main dam, increasing the total project spend to $15.45 million. The Board held the ATO application in abeyance until the final FAA from DFO is received, and required an updated cost estimate and a decommissioning cost analysis in the amended application.
2. Decommissioning Costs In comparing the refurbishment versus the decommissioning option, it appears that the capital investment over time is greater for refurbishment, but it becomes more economic when factoring in the cost of replacing...
AI summary The text discusses decommissioning costs for a hydro plant, comparing refurbishment and decommissioning options. NSPI provided a capital cost for partial decommissioning, but the definition of 'partial' is unclear. The Industrial Group recommends more detailed information on decommissioning options and their environmental impact.