HAS MR. SCHMEISSER BEEN OVERCHARGED? p. p. 0
January 2004, 4.6 KW per month, February 2004, 4 KW, March 2004 to February 2005, 4.4 KW per month March, April, May 2005, 4 KW per month total 9.2 KW total 4.0 KW total 52.8 KW total 12.0 KW 78.0 KW Total at November 1, 2003 rates (78 KW...

AI summary The document discusses billing errors involving incorrect multiplier usage by the Utility, leading to under-billing and over-billing for Mr. Schmeisser. The net result was a savings of $376.62. The Utility has not proposed re-billing to recover the under-billing.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →