HomeBilling ProceduresM12414Evidence
Topic/Matter Intersection

Topic:"Billing Procedures" in M12414

Matter: NSPI DRO Appeal - Solar Billing - Karen Chetwynd
8 passages 6 documents

Billing Procedures across all matters →

C-1DRO Appeal - Redacted 1 passage
Section 3 p. p. 0
DRO made decision on: July 28 2025 Type of complaint: Billing Issues Additional details: I have had solar panels on my home for a number of yrs. I upgraded my panels in applied in mid 2024 to add and upgrade my panels with NSP. At no time...

AI summary A customer is complaining about billing issues related to solar panels and net metering after upgrading with NSP. They claim NSP did not inform them that their net metering agreement changed, and that NSP is selling their excess energy for profit, without compensation. They request compensation or the ability to donate the extra power to a non-profit.

C-2Appellant's Evidence - Redacted 1 passage
4. METERING AND BILLING p. p. 7
4. METERING AND BILLING 4.1 Metering requirements and billing procedures shall be in accordance with regulation 3.6 of the UARB Rates & Regulations and any other applicable laws, as applicable.

AI summary This section outlines that metering requirements and billing procedures must follow regulation 3.6 of the UARB Rates & Regulations and any other applicable laws.

C-3DRO Decision - Redacted 1 passage
the year with excess generation remaining, NS Power would apply this to any billed consumption within the same calendar year up to a maximum of your total billed energy within the same calendar year" Board approved Regulation 3.6.1 states...

AI summary The document discusses the net metering service regulation, which allows customers to generate electricity and offset their consumption. Excess generation is credited over a year, and any surplus is purchased by the utility at the retail rate. The Dispute Resolution Officer is involved in a customer's dispute regarding a billing discrepancy.

C-6NSPI (NSEB) RIR1 to RIR-12 - Redacted 2 passages
4. METERING AND BILLING p. p. 24
4. METERING AND BILLING 4.1 Metering requirements and billing procedures shall be in accordance with regulation 3.6 of the UARB Rates & Regulations and any other applicable laws, as applicable.

AI summary The section outlines that metering requirements and billing procedures must comply with regulation 3.6 of the UARB Rates & Regulations and other applicable laws.

Chetwynd DRO Appeal (NSEB M12414) NSPI Responses to NSEB Information Requests p. p. 24
Chetwynd DRO Appeal (NSEB M12414) NSPI Responses to NSEB Information Requests 1 capacity is considered a material change. The difference in treatment reflects the regulatory 20 electricity up to a maximum of the customer's total usage per...

AI summary NSPI has responded to NSEB information requests regarding the Chetwynd DRO Appeal (NSEB M12414), confirming the customer's transition from a Legacy NM contract to the SGO and explaining billing practices under the SGO. This includes how excess generation is handled and communication with the customer on specific dates.

99216NSEB (CHETWYND) IR-1 to IR-2 - Redacted 1 passage
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF: A DRO Appeal regarding Billing by a customer of NOVA SCOTIA POWER INC. (NS Power) – Chetwynd NON-CONFIDENTIAL INFORMATION REQUESTS To: Karen and...

AI summary The Nova Scotia Energy Board has issued a non-confidential information request to Karen and Jeff Chetwynd regarding billing by NS Power. Responses are due by September 25, 2025, and the contact person is Rianne MacDonell.

99217NSEB (NSPI) IR-1 to IR-12 2 passages
NOVA SCOTIA ENERGY BOARD
NOVA SCOTIA ENERGY BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT - and - IN THE MATTER OF: A DRO Appeal regarding Billing by a customer of NOVA SCOTIA POWER INC. (NS Power) – Chetwynd NON-CONFIDENTIAL INFORMATION REQUESTS To: Kathleen M...

AI summary The Nova Scotia Energy Board has issued a non-confidential information request to Nova Scotia Power Inc. regarding billing practices under the Public Utilities Act. The request, directed to Kathleen Murray, seeks responses by September 25, 2025, and is part of a DRO appeal related to billing by a customer in Chetwynd.

Request IR-5:
Request IR-5: Reference Exhibit C3, page 3, of NS Power's response (July 17, 2025): NS Power spoke with Jeffrey regarding his bill. It was explained that excess generation is banked and applied to future bills or at the settlement period....

AI summary NS Power informed a customer about banked credits from excess generation and explained that payments are not due until the settlement period. Questions are raised about the settlement period and the application of banked credits to the customer's account.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →