14 4. PRICE & PAYMENT p. p. 339
14 4. PRICE & PAYMENT - 15 4.1 NSPI agrees to pay EfficiencyOne for EECA DSM as set out in Schedule "B" 16 Compensation (the "Contract Price"). - 17 4.2 The Contract Price shall constitute full compensation for the EECADSM, and no addition...

AI summary NSPI agrees to pay EfficiencyOne for EECA DSM services at the Contract Price outlined in Schedule B, with no additional compensation for indirect costs. Monthly payments are due on the first business day of each month, subject to HST and applicable tax withholdings. All amounts are in Canadian currency, and statutory withholdings may apply for non-resident services.

4. PRICE & PAYMENT p. pp. 379-380
4. PRICE & PAYMENT - 4.1 NSPI agrees to pay EfficiencyOne for DSM as set out in Schedule "B" Compensation (the " Contract Price "). - 4.2 The Contract Price shall constitute full compensation for the DSM, and no additional compensation sha...

AI summary NSPI agrees to pay EfficiencyOne for Demand Side Management (DSM) per Schedule B's Contract Price, which covers full compensation with no additional payments. Monthly payments are due on the first business day of each month, including HST. Withholding requirements for non-residents and cooperation to ensure proper tax deductions are outlined.

20. DEFAULT AND TERMINATION p. p. 387
tive obligations under this Agreement for DSM provided up to the date of termination. Any claim for payment by EfficiencyOne must be asserted within thirty (30) days from the date of such termination.

AI summary The text outlines termination obligations under a DSM agreement, requiring EfficiencyOne to assert payment claims within 30 days of termination. It emphasizes adherence to contractual obligations up to termination and timely claim assertion.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →