SPECIAL CONDITIONS (1) Projections of the anticipated hourly energy price (week ahead and day ahead) will be provided to the customer according to the following schedule:
AI summary The document introduces a section on 'Special Conditions' regarding the provision of electricity pricing information. It specifically outlines that the utility is required to provide customers with projections for anticipated hourly energy prices on both a week-ahead and day-ahead basis, following a specified schedule.
SPECIAL CONDITIONS (1) Projections of the anticipated hourly energy price (week ahead and day ahead) will be provided to the customer according to the following schedule:
AI summary The document introduces a section on 'Special Conditions' regarding the provision of anticipated hourly energy prices. It specifies that Nova Scotia Power Inc. must provide customers with week-ahead and day-ahead energy price projections according to a defined schedule.
ONE PART DISTRIBUTION VOLTAGE REAL TIME PRICING TARIFF Page 2 of 3 - o By midnight each business day, hourly price forecasts for each hour of the next five days shall be provided to the customer. - o Major changes to the hourly price forec...
AI summary This section outlines the operational requirements and conditions for the Voltage Real Time Pricing Tariff. Key provisions include the requirement for the Company to provide hourly price forecasts for the next five days, rules for primary vs. secondary metering and associated capital contributions, and a minimum twelve-month service term. It also specifies conditions for transitioning from an Interruptible Rider to firm service and establishes a minimum power factor requirement of 90% lagging to avoid adjustment factors.
Penalty for Non-Compliance All energy served after the 10-minute deadline has expired will be billed at $5.00 per kWh. In addition a fixed charge of $2,000.00 will be applied. The penalty charge is applicable above and beyond the Port Auth...
AI summary The document specifies the financial penalties for non-compliance regarding energy service deadlines. Any energy served after the 10-minute deadline will incur a variable rate of $5.00 per kWh plus a fixed charge of $2,000.00. These penalty charges are explicitly stated to be in addition to the Port Authority's standard monthly billing.
Where: • "LWPFD" is LRS Winter Peak Firm Demand in respect of each billing month calculated as follows:
AI summary The document provides the technical definition for 'LWPFD' (LRS Winter Peak Firm Demand) within a regulatory context. It specifies that this metric represents the firm demand for Licensed Retail Suppliers (LRS) during each billing month, establishing the calculation basis for winter peak demand monitoring.
Where: "A" is any residual customer demand (above that required by the interruption notice) remaining in the third interval directly following two complete 5-minute intervals after the interruption call is initiated and sent by NSPI. "B" i...
AI summary The text defines the methodology for calculating penalties related to power interruptions. It specifies the calculation of 'A' as residual customer demand in a specific interval following an interruption call, and 'B' as the customer's average demand during the interruption event (excluding the interval used for 'A'). It also establishes a cap on the total penalty, limiting it to two times the cost of the appropriate firm billing for consumption during that period.
SPECIAL CONDITIONS - (1) The Company reserves the right to have a separate service agreement, if in the opinion of the Company issues not specifically set out herein, must be addressed for the ongoing benefit of the Company and its custome...
AI summary This section outlines special conditions for customers under the tariff, emphasizing customer responsibilities regarding power supply integrity, load management, and infrastructure costs. It specifies that customers must ensure their operations do not negatively impact the system's reliability or stability (e.g., harmonics, voltage flicker). Additionally, it establishes that costs for special metering, communication systems, or service requirements beyond a single step-down transformation are the customer's responsibility, while defining rules for transformer losses and power factor requirements.
SPECIAL CONDITIONS (1) Projections of the anticipated hourly energy price (week ahead and day ahead) will be provided to the customer according to the following schedule:
AI summary This section introduces the special conditions regarding the provision of hourly energy price projections (both week-ahead and day-ahead) to customers. It establishes that these projections will be provided according to a specific schedule, though the specific details of that schedule are not contained within this particular excerpt.
SPECIAL CONDITIONS (1) Projections of the anticipated hourly energy price (week ahead and day ahead) will be provided to the customer according to the following schedule:
AI summary The document introduces a section on special conditions regarding the provision of hourly energy price projections. It specifies that Nova Scotia Power Inc. (NSPI) is required to provide both week-ahead and day-ahead hourly energy price projections to customers, following a defined schedule.
ONE PART DISTRIBUTION VOLTAGE REAL TIME PRICING TARIFF Page 2 of 3 - o By midnight each business day, hourly price forecasts for each hour of the next five days shall be provided to the customer. - o Major changes to the hourly price forec...
AI summary This text outlines the terms and conditions for the One Part Distribution Voltage Real Time Pricing Tariff. Key provisions include the requirement for the Company to provide five-day hourly price forecasts, the finalization of hourly prices 20 minutes prior to the hour, and the treatment of metering costs as capital contributions for the customer. It specifies a minimum 12-month service term, rules for transitioning from interruptible to firm service for large industrial customers, and power factor requirements with associated adjustment factors.
Penalty for Non-Compliance All energy served after the 10-minute deadline has expired will be billed at $5.00 per kWh. In addition a fixed charge of $2,000.00 will be applied. The penalty charge is applicable above and beyond the Port Auth...
AI summary The document outlines the specific financial penalties imposed for non-compliance regarding energy service deadlines. Any energy served after the 10-minute deadline will incur a variable rate of $5.00 per kWh, plus a fixed charge of $2,000.00. These penalty charges are stipulated to be in addition to the Port Authority's standard monthly billing.
CUSTOMER CHARGE The monthly customer charge under this tariff is calculated according to the following formula: Monthly customer charge = \frac{\text{forecast annual administration costs}}{\text{forecast number of customers subscribed \ 12...
AI summary The document specifies the calculation method for the monthly customer charge under the tariff. It defines the charge as the forecast annual administration costs divided by the forecast number of customers subscribed multiplied by 12. The resulting monthly customer charge is set at $414.6342707.
Where: "LWPFD" is LRS Winter Peak Firm Demand in respect of each billing month calculated as follows: 2027 AAR Appendix G8 (redline) Page 3 of 5 Page 3 of 5
AI summary The document fragment provides a technical definition for 'LWPFD', which represents the Load Weighted Planning Factor Demand. It specifies that this metric corresponds to the Licensed Retail Suppliers (LRS) Winter Peak Firm Demand for each billing month. The text serves as a methodology note within the 2027 Annual Adjustment Rate (AAR) Appendix G8.