Topic/Matter Intersection

Topic:"Boards Regulatory Rules" in M13082

Matter: Nova Scotia Power Inc. - CI C0047278 – IT – Oracle MDM Upgrade - $8,211,297
3 passages 3 documents

Boards Regulatory Rules across all matters →

103767Hearing Order 1 passage
The following timetable will apply to this matter:
The following timetable will apply to this matter: Notice to Interested Parties Friday, October 2, 2026 Notice of Intervention Friday, October 9, 2026 Information Requests (IRs) to NS Power Thursday, October 29, 2026 NS Power's Responses t...

AI summary A timetable for a regulatory proceeding is outlined, with key dates for notices, interventions, information requests, and submissions. The Board's Regulatory Rules , particularly Rule 7(3), will govern the filing process, requiring documents to be submitted by 2:00 p.m. on due dates.

103547Letter NSPI re: Capital Items Filed Outside the Quarter Package 1 passage
Request for Confidentiality
Request for Confidentiality Pursuant to Rule 12 of the Board Regulatory Rules, NS Power requests confidential treatment of certain portions of the material filed in support of the following Capital Work Orders: - 1. CI C0068718 IT DERMS So...

AI summary NS Power is requesting confidential treatment for certain portions of materials filed in support of four Capital Work Orders under Rule 12 of the Board Regulatory Rules.

103767Hearing Order 1 passage
The following timetable will apply to this matter:
The following timetable will apply to this matter: Notice to Interested Parties Friday, October 2, 2026 Notice of Intervention Friday, October 9, 2026 Information Requests (IRs) to NS Power Thursday, October 29, 2026 NS Power's Responses t...

AI summary The timetable for the regulatory proceeding outlines key dates for notices, interventions, information requests, responses, and submissions. The Board's Regulatory Rules , including Rule 7(3), will govern the filing process.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →