Matter: NSPI CI# 38819 - $7,452,511 - 51V Tremont Circuit Breaker & Bus
1 passage 1 document

Capacity Costs across all matters →

06178Board Decision and Order 1 passage
ORDER
ORDER WHEREAS Nova Scotia Power Incorporated ("NSPI") filed applications on July 27, 2010, with the Nova Scotia Utility and Review Board (the "Board") for approval of Work Orders CI# 38819 - 51V Tremont Circuit Breaker & Bus in the amount...

AI summary Nova Scotia Power Incorporated (NSPI) applied for approval of several electrical infrastructure projects. The Nova Scotia Utility and Review Board conducted a public review and received input from stakeholders, including the Consumer Advocate. After reviewing the applications and responses, the Board approved the projects, noting their necessity for improving service reliability and confirming the legitimacy of the affiliate transaction with Emera Utility Services.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →