B-1-(i)Appendix 1 - HSV-2024-043-CA01 Condition assessment - Factorydale
3 passages
Regarding Loses: - Maximum Hydraulic loses: The user enters a value that represents the estimated equivalent hydraulic losses (%) in the water passages. In a hydro plant, energy is lost as water flows through the water passages. - Miscella...
AI summary The text outlines hydraulic, miscellaneous, and generator efficiency losses in hydro plants, emphasizing the available flow adjustment factor for sensitivity analyses in financial modeling. This factor modifies capacity factors and electricity exports without altering flow-duration curve values, aiding in assessing project viability.
Now, we know that the maximum output of the current generator is 416 kW, understanding that it is a 520 kVA generator with a power factor of 0.8. A like-for-like replacement will allow the generator to work at peak performance, but no more...
AI summary The document discusses a like-for-like replacement of a 520 kVA generator with a 416 kW output, noting that energy production, capacity factor, efficiency curves, and emissions reduction are unchanged. Two quotes are provided for the replacement: Norcan Hydro at 2,472,500 CAD and Canyon Hydro at 1,953,000 CAD. Additional costs such as removal, engineering, and shipping are not included in the financial models.
6.3 Summary - costed option analysis Option to analyze Capacity (kW) Electricity (kWh) Initial costs CAD Electricity export revenue CAD O&M costs (savings) CAD Simple payback YEARS Like for Like - 3.39 m3/s (70%) - NORCAN 416 2,647,384 $2,...
AI summary The costed option analysis compares various hydroelectric options, with new units showing the most attractive potential. Preliminary numbers suggest that new units, particularly the 3.39 m3/s (70%) DIVE option, could be viable, especially with government loan and grant support.
B-1-(ii)Appendix 2 - HSV-2024-043-CA02 Additional Costed Option Scenarios - Factorydale
5 passages
EXECUTIVE SUMMARY This report is a complement of the Condition Assessment and costed option analysis report HSV - 2024 - 043 - CA01 and should be read and understood as an additional part of it. On this case, we are analysis different scen...
AI summary This executive summary discusses a hydrological analysis for the Factorydale plant, using flow duration curves from nearby rivers (Cornwallis and Beaverbank) to model water flow scenarios. Three scenarios (pessimistic, optimistic) were evaluated, reinforcing the recommendation for a new unit at the plant due to alignment with prior energy and financial analysis results.
Table 1: NORCAN unit – results on the three different scenarios of water flow Capacity kW Electricity KWh Initial costs $ Electricity export revenue $ Fuel cost $ O&M costs (savings) $ Simple payback Yr Factorydale - Beaverbank Ext -NEW -...
AI summary The table presents results for three different water flow scenarios at the NORCAN unit, showing variations in capacity, initial costs, fuel costs, and simple payback periods. The scenarios are based on similar flow duration curves, and the results show minimal differences between the Beaverbank and Cornwallis stations.
Table 4: Summary of costs, revenue, ROI and ROE for new units Option to analyze Capacity (kW) Electricity (kWh) Initial costs CAD Electricity export revenue CAD O&M costs (savings) CAD Simple payback YEARS Equity Payback YEARS Factorydale...
AI summary Table 4 presents a summary of costs, revenue, ROI, and ROE for various new unit options, including different capacity levels, electricity generation, initial costs, revenue from electricity exports, O&M costs, and payback periods for different projects like NORCAN, CANYON, and DIVE.
Table 5: Summary of costs, revenue, ROI and ROE for like for like replacement Option to analyze Capacity (kW) Electricity (kWh) Initial costs CAD Electricity export revenue CAD O&M costs (savings) CAD Simple payback YEARS Equity Payback YE...
AI summary Table 5 presents a summary of costs, revenue, ROI, and ROE for like-for-like replacements of various projects, including the CANYON and NORCAN projects, under different capacity and electricity scenarios. The table includes data on initial costs, electricity export revenue, O&M costs, and payback periods for multiple options.
CONCLUSION Once we see the numbers on different flow water duration scenarios, comparing it with the information available from the quotes received, it is even clearer than the best option is to go with a new unit. The like for like replac...
AI summary The analysis concludes that replacing existing equipment with a new unit offers significant non-financial benefits, including improved reliability, efficiency, and grid stability, despite similar ROI and ROE compared to like-for-like replacements. Key advantages include modern technology, increased energy output, and opportunities for carbon credit sales.
B-1-(iii)Appendix 3 - HSV-2024-043-SREP02 Feasibility Study
2 passages
Option to analyze Capacity (kW) Electricity (kWh) Initial costs (CAD) Electricity export revenue (CAD) O&M costs (savings) (CAD) Simple payback (YEARS) Equity Payback (YEARS) Factorydale - Beaverbank Ext - NEW - 3.39 m3/s (10%) - NORCAN 1,...
AI summary The table presents three options for the Factorydale Beaverbank Ext project with varying capacities and associated costs, revenues, and payback periods. Each option has the same initial cost but differs in electricity generation, export revenue, and operational savings, leading to different payback times.
Option to analyze Capacity (kW) Electricity (kWh) Initial costs (CAD) Electricity export revenue (CAD) O&M costs (savings) (CAD) Simple payback (YEARS) Equity Payback (YEARS) Factorydale - Cornwallis Ext - NEW - 3.39 m3/s (10%) - NORCAN 1,...
AI summary The table presents various options for a hydroelectric project, including capacity, electricity production, initial costs, revenue from electricity export, operational and maintenance cost savings, and payback periods. Different configurations and locations are compared, highlighting varying levels of capacity utilization and associated financial metrics.
B-3TOB (NSEB) RIR 1 to 42 - Redacted
6 passages
Response: The company that was conditionally awarded the contract for the new transformer is Because it is a conditional award, we cannot share at this point their information to the public, to not alter the normal course of the RFP proces...
AI summary The response discusses a conditional award of a transformer contract, highlighting the increased capacity from 600 kVA to 1000 kVA, technical specifications, and pending clarifications required before final approval. Key evaluation notes cover impedance, oil volume, insulation, and SCADA integration.
Response: The Tier 1 condition index was used as a screening tool to assess the apparent condition of the existing assets, but it was not the only criterion used to define the final project scope. The selected project is not a like-for-lik...
AI summary The project involves modernizing a hydro-generation system, not just replacing components based on condition scores. Decisions were influenced by factors like capacity, safety, reliability, and long-term risks. Older equipment was not replaced solely due to Tier 1 condition indices but because of integration and performance requirements.
Interrogatory: Question(s): On page 90 of Condition Assessment, 6.2.1 Option A – Like for Like Replacement, states that "we will assume that 70% of the time, the flow of 3.39 m3/s (120 cfs) is available," but page 12 of the Additional Cost...
AI summary The interrogatory questions the discrepancy between the flow assumptions used in evaluating the like-for-like replacement and the proposed refurbishment, and requests an evaluation of the like-for-like replacement using the same pessimistic-to-realistic scenario as the refurbishment.
Response: a) Current equipment weight is not known with enough accuracy, but we know that it is below the 10,000 kg limit (to be exact, 9,996 kg) that the crane can lift safely, as per the most recent test conducted on it in 2025. With tha...
AI summary The response addresses concerns about equipment weight and structural safety, confirming that the new generator weighs 8,410 kg, well below the crane's 9,996 kg limit. A structural analysis confirms the powerhouse can support heavier loads due to its original design. A scroll case with a snail shell design is recommended for efficiency.
Question(s): On page 38 of Feasibility Study, it states: Having said that, we are going to be even more conservative. We think that a unit on the lower end of the power output range, a 650 kW machine, will be closer to the final design app...
AI summary The text discusses the decision to use a 650 kW machine as a more conservative estimate for the final design, considering ancillary systems and financial models with two flow duration curve scenarios.
Response: The 650 kW scenario was described as "more conservative" because it uses the lower end of the expected output range, rather than assuming that the project would achieve the higher 750 kW output. This avoids overstating future gen...
AI summary The 650 kW scenario is considered more conservative due to lower expected output and alignment with known hydraulic conditions, avoiding overstating future generation and project economics. It uses realistic turbine-generator efficiencies and accounts for limited long-term flow records, ensuring a technically practical and financially cautious basis for the project.