Topic/Matter Intersection

Topic:"Capital Expenditures" in M03430

Matter: CI# 28867 - P-128.10 - NSPI WO - LIN Unit#1 Low Nox Combustion Firing System $3,875,373
7 passages 3 documents

Capital Expenditures across all matters →

N-1Non-Confidential Work Order 7/30/2010 5 passages
- , p. p. 1
- , S266 11/8/2007 201006/06 Forecast Variance 23,039 26,355 2,582 25,029 83,527 48,788 2,568 1,029 533 546 116,637 1,024 910 1,048 116,396 (531) 1,462 4,372 19,289 89,240 1,067 14,000 2,184 51,438 2,217 5,352 7 2,116 699,557 2,532,493 73...

AI summary The table presents financial and project data, including forecast amounts and variances for a project related to the LIN UNIT#1 LOW NOX COMBUSTION FIRING SYSTEM under Project Number YSTEM. It includes budget versions, approved dates, and cost details for activities such as the SGP - Boiler.

Project Number p. pp. 1-8
Project Number Low Nox Combustion Firing System Lingan Unit #1- Low Nox Combustion Firing System . CI #28867 -S266 Account Activated Actual Variance Explain Variance THERMAL Regular Labour 001 - $295,000 $153,701 ($141,299) Less plant trad...

AI summary The document provides a detailed account of financial variances for the Low Nox Combustion Firing System project at Lingan Unit #1, including differences between estimated and actual costs for various categories such as labour, materials, contracts, and administrative overheads. The variances are explained by factors like changes in resource usage, incorrect initial estimates, and cost savings from internal resources.

Capital Management System Capital Item Detail Forecast p. p. 8
Capital Management System Capital Item Detail Forecast Date: 2007/09/24 Page: 2 of 4 CI Number: 28867 - LIN UNIT#l LOW NOX COMBUSTION FIRING SYSTEM Parent CI Number: Responsibility: 05270000 - GENERATION SERVICES Cost Centre: 304 - Lingan...

AI summary This document provides a forecast detail for the Low NOx Combustion Firing System (LNCFS) under the Capital Management System. It outlines the project's responsibility, cost centre, and current ACE year as 2008.

Work Order Requests p. p. 16
Work Order Requests Pending DARB approval, in 2008 NSPI will undertake the third year of its four year NO x Reduction program. Three low NOx retrofits are required for Lingan Unit 1 eCI 28867), Point Tupper Unit 2 eCI 28865), and Trenton U...

AI summary NSPI seeks DARB approval for the third year of its four-year NOx Reduction program in 2008, involving three low NOx retrofits at Lingan Unit 1, Point Tupper Unit 2, and Trenton Unit 6, with estimated costs of $4.1 million. Higher costs at Trenton 6 are attributed to complex boiler design and market price fluctuations.

. p. p. 16
. Name of Project: Lingan Unit 1 - Low NOx Combustion Firing System- JULY 20,2007 ESTIMATE Project No. Division Power Production Generation Services Estimated Completion Date: 200B Capital Item No. Responsibility Code 05130000 Function Est...

AI summary The document outlines a capital project involving the design, supply, erection, and testing of a low NOx combustion firing system for Lingan Unit 3. It includes costs for regular labour, travel, materials, consulting, and meals and entertainment, with a total estimated cost of $301,500.00 for the design activity.

04986Board Decision Letter 1 passage
By E-mail and Courier p. p. 0
By E-mail and Courier Ms. Lee Thomson-Lutz Capital Manager Nova Scotia Power Inc. 14th Floor, Barrington Tower Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI- Request for final cost approval for Work Order CI# 28867 - LIN Unit #1 Low NOx...

AI summary Nova Scotia Power Inc. (NSPI) requested final cost approval for a work order related to a Low NOx Combustion Firing System, originally approved in 2007. The Board approved a reduced final cost of $3,875,331, $274,547 less than the original amount, citing lower material, labor, and consulting costs despite higher contract costs.

04986Board Decision Letter 1 passage
By E-mail and Courier p. p. 0
By E-mail and Courier Ms. Lee Thomson-Lutz Capital Manager Nova Scotia Power Inc. 14th Floor, Barrington Tower Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI- Request for final cost approval for Work Order CI# 28867 - LIN Unit #1 Low NOx...

AI summary The Board approved Nova Scotia Power Inc.'s request to reduce the final cost of Work Order CI# 28867 for a Low NOx Combustion Firing System from $4,149,920 to $3,875,331, citing lower material and labor costs and higher-than-forecasted contracts as the reason for the $274,547 reduction.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →