Topic/Matter Intersection

Topic:"Capital Expenditures" in M03509

Matter: CI# 38878 - P-128.10 - NSPI WO - 2010 Substation Cutout and Insulator Replacements - $1,506,414
9 passages 3 documents

Capital Expenditures across all matters →

N-1Redacted Work Order 9/2/2010 7 passages
Section 40 p. p. 1
Parent CI Number Cost Centre 800 - 800-Services - Admin. Budget Version - 201007/05 Forecast Forecast Start 12101/2010 Operational 11/01/2010 Final Cost 12/31/2010 2010 $1,506,414.10 Total: $1,506,414.10 Original Cost: $100,000.00 This cap...

AI summary The document outlines a capital item budget for replacing porcelain cutouts in 28 transmission substations, with a forecasted cost of $1,506,414.10 for 2010 and an original cost of $100,000.00.

No projects in 2008, 2009, 2010, 2011 and 2012 p. p. 1
No projects in 2008, 2009, 2010, 2011 and 2012 38878 CI Number 2010 Substation Cutout and Insulator Replacements - Project Number Parent CI Number Approved Date 800 Cost Centre Admin. 800-Services - Budget Version 201007/05 Forecast Capita...

AI summary The text indicates that there were no projects undertaken in the years 2008 through 2012. A table details a 2010 project related to substation cutout and insulator replacements with various cost breakdowns, but the overall context suggests a lack of activity during the specified years.

Capital Item Justification p. p. 1
Capital Item Justification Justification Criteria: TRANSMISSION PLANT Sub-Criteria: OUTAGE PERFORMANCE Name of Report : Document Location: Person Responsible: STEVE HAZEL

AI summary The document outlines capital item justification criteria for a transmission plant, focusing on outage performance. Steve Hazel is identified as the person responsible for the report, though the report's name and location are unspecified.

Why do this project this way? p. p. 1
Why do this project this way? The best approach to reduce outages caused by cutout failures is to focus on specific substations and replace the cutouts in kind. This work is being completed by an affiliate. Project Number Approved Date 201...

AI summary The project aims to reduce outages by replacing cutouts in specific substations. It is being executed by an affiliate and has exceeded the ACE budget by $5,453 mainly due to increased interest costs.

38878 - 2010 SUbstation Cutout and Insulator Replacements p. p. 1
38878 - 2010 SUbstation Cutout and Insulator Replacements Account ACE 2010 Current Submission Variance Regular Labour (No AO) 001 - 580 580 T&D Regular Labour 001 - 30,000 29,420 (580) Materials 012 - 304,000 304,000 COPS Contracts 013 - 9...

AI summary The document provides a comparison between the Approved Cost Estimate (ACE 2010) and the current submission for the 2010 Substation Cutout and Insulator Replacements project, highlighting variances in various cost categories such as labour, materials, and interest capitalized.

The following is a breakdown of costs associated with the 2010 Transmission Cutout Replacements p. p. 1
The following is a breakdown of costs associated with the 2010 Transmission Cutout Replacements • Administrative Overheads and Interest $272,414 • Labour $30,000 • Materials $304,000 • Contracts $900,000 • Total $1,506,414 The major projec...

AI summary The text provides a cost breakdown for the 2010 Transmission Cutout Replacements project, detailing administrative overheads, labour, materials, and contracts. The largest single cost category is materials at $304,000, and the contract estimate is $900,000 based on an hourly rate.

NSPI - 2010 Annual Capital Expenditure Plan (2010-2014) - P-128.09 NSPI Responses to UARB Information Requests p. p. 1
NSPI - 2010 Annual Capital Expenditure Plan (2010-2014) - P-128.09 NSPI Responses to UARB Information Requests

AI summary NSPI provides responses to UARB's information requests regarding its 2010-2014 Annual Capital Expenditure Plan. The document outlines NSPI's planned capital investments during this period, addressing regulatory inquiries about financial commitments and project timelines.

05462Board Decision Letter 1 passage
CI# 38878 2010 Substation Cutout and Insulator Replacements $1,506,414 p. p. 0
CI# 38878 2010 Substation Cutout and Insulator Replacements $1,506,414 Board Staff issued Information Requests on February 5, 2010 and NSPi's responses were received by the Board on September 2, 2010. Additional clarification of project de...

AI summary The Board approved NSPI's request for $1,506,414 to replace substation cutouts and insulators in 28 Nova Scotia substations, citing improved reliability for 135,000 customers. The project was deemed necessary and cost-justified after reviewing NSPI's responses to information requests and clarifications.

05462Board Decision Letter 1 passage
CI# 38878 2010 Substation Cutout and Insulator Replacements $1,506,414 p. p. 0
CI# 38878 2010 Substation Cutout and Insulator Replacements $1,506,414 Board Staff issued Information Requests on February 5, 2010 and NSPi's responses were received by the Board on September 2, 2010. Additional clarification of project de...

AI summary The NSUARB approved NSPI's request for $1,506,414 to replace substation cutouts and insulators in 28 substations, citing improved reliability for 135,000 customers. The Board accepted confidential portions of the work order and confirmed the project's necessity and cost justification.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →