N-1Application
7 passages
NSEB APPROVAL SHEET Project Title: POA Boiler Refurbishment 2025 CI Number: C0067906 Date: July 7, 2025 Expenditure Profile Type of Filing Year Budget Amount Project Estimate Capital Project Authorization X Unforeseen and Unbudgeted (U&U)...
AI summary The NSEB Approval Sheet outlines the POA Boiler Refurbishment 2025 project, including budget amounts, project estimates, and authorization details. The project involves capital expenditures with approvals for 2025 and 2026, and includes comments and signatories.
July 4, 2025 CI Number: C0067906 Title: POA Boiler Refurbishment 2025 Start Date: 2025/05 In-Service Date: 2025/11 Final Cost Date: 2026/05 Function: Steam Forecast Amount: $1,218,254
AI summary The document outlines a project for the refurbishment of a boiler at POA, with a start date of May 2025, an in-service date of November 2025, and a final cost date of May 2026. The forecasted cost is $1,218,254, and the function of the boiler is steam generation.
DESCRIPTION: This project is for the refurbishment of the Point Aconi Boiler. The scope of work includes the refurbishment and replacement of boiler and air heater components critical to environmental compliance and the safe, reliable, and...
AI summary The project involves refurbishing the Point Aconi Boiler to ensure environmental compliance and operational efficiency, with final scope determined via annual data analysis. The Board mandated NS Power to notify DDA proceeding participants when filing capital work orders, which NS Power did on July 4, 2025, following Decision M11220.
Summary of Related CIs +/- 2 years: Pursuant to Section 11.2 of the CEJC, related CIs for Steam projects includes "work completed on the same asset (turbine, boiler, etc.) and on the same unit (Lingan Unit #3, for example)." - 2023 C005229...
AI summary The document lists capital improvement projects (CIs) for Steam Production Plant – Point Aconi under Section 11.2 of the CEJC, including boiler refurbishments, replacements, and upgrades from 2023 to 2027, with associated costs and depreciation classifications.
Retirement Information: • Categorization of Retirement: Accounting Policy 6420 - Retirement and Disposal of Capital Assets • Percentage of Asset Pool: 0.14% Estimated Life of the Asset: 8 Years JUSTIFICATION: Justification Criteria: Therma...
AI summary The text outlines retirement information for an asset with a 0.14% pool, an 8-year estimated lifespan, and justification based on thermal criteria under equipment replacement/refurbishment sub-criteria.
Why do this project? NS Power conducts condition and risk assessment and analysis based on the annual boiler inspection reports, boiler tube failure reports, root cause analyses, and boiler header reports. As a result of the most recent as...
AI summary NS Power requires replacement of boiler tubes, omega shielding, and superheater tubes to prevent unplanned outages, enhance safety, reduce financial risks from emergency repairs, and maintain asset integrity. Proactive replacement is essential to avoid higher costs, safety hazards, and long-term damage to the boiler system.
Execution Year: 2025 Description Unit Quantity Unit Estimate Total Estimate Cost Support Reference Completed Similar Projects (FP#'s) Regular Labour Electrician PD 10 $ 403 $ 4,033 C0052294, C0060250 Engineering PD 10 $ 457 $ 4,569 C005229...
AI summary The document outlines a detailed cost estimate for labor, materials, and contracts related to a project in 2025, with specific line items and references to similar projects. It includes labor classifications, quantities, unit estimates, and total estimates, along with references to cost support and completed projects.