NSEB APPROVAL SHEET Project Title: Ragged Lake Generator Replacement CI Number: C0017098 Date: July 7, 2025 Expenditure Profile Type of Filing Year Budget Amount Project Estimate Capital Project Authorization Unforeseen and Unbudgeted (U&U...
AI summary The NSEB Approval Sheet outlines the expenditure profile for the Ragged Lake Generator Replacement project from 2019 to 2025, including budget amounts, project estimates, and authorization types such as Planned & Advanced (P&A), Subsequent Approval Item, and Authorization to Overspend (ATO).
Approved $2,229,267 Current Amount $1,681,714 Variance -$547,553 Submitted on behalf of NOVA SCOTIA POWER INCORPORATED Approved on behalf of NOVA SCOTIA ENERGY BOARD Authorized Signatory DATE DATE Dave Pickles Chief Operating Officer July...
AI summary The Ragged Lake Generator Replacement project, managed by Nova Scotia Power Incorporated, has a forecast amount of $1,681,714, with an approved current amount of $2,229,267, showing a variance of -$547,553. The project started in 2019 and was completed in 2021.
Summary of Related CIs +/- 2 years : Pursuant to Section 11.2 of the CEJC, related CIs for General Plant projects include "work completed on the same asset (application, building, etc.)." • No other projects in 2018, 2019, 2020, 2021 or 20...
AI summary The summary outlines related Capital Improvement (CI) projects for General Plant under Section 11.2 of the CEJC, focusing on work completed on the same asset. No other projects were completed between 2018 and 2022.
JUSTIFICATION: Justification Criteria: Work Support Facilities Sub Criteria: Building Replacement/Modifications
AI summary The justification criteria for work support facilities includes sub criteria related to building replacement and modifications.
Why do this project this way? NS Power engaged CBCL Limited to review the building electrical system and provide an assessment of the Control Center and recommendations for improvement. In addition to the electrical equipment assessment, t...
AI summary NS Power commissioned CBCL Limited to assess the electrical system at the Ragged Lake Control Centre. The report recommends replacing aging generators and switchgear, acquiring a mobile load bank, and replacing the building service transformer to ensure backup power reliability. A second independent supply option is not currently feasible due to cost and infrastructure limitations.
Reason for Variance – FIN This project was underspent by approximately $548K compared to the approved 2020 P&A budget of $2,229,267 for a total final spend of $1,681,714. Overall, the project was less complex from a technical perspective t...
AI summary The project was underspent by approximately $548K due to lower complexity and internal resource utilization, though material costs increased by $352K post-pandemic. The project was delayed due to part availability, vendor availability, and encroachment issues. Final work was completed in February 2025.
Please refer to the Variance sheet for more detail. C0017098 - Ragged Lake Generator Replacement Account Approved Current Submission Variance Reason for Variance Regular Labour 230,056 25,419 (204,637) Less labour was required than estimat...
AI summary The document outlines a variance analysis for the Ragged Lake Generator Replacement project. It shows significant cost variances due to factors such as reduced labor requirements, local resourcing, and increased material costs during the pandemic. Some costs were lower than expected, while others increased due to unforeseen circumstances.
99446Board Decision Letter
2 passages
September 23, 2025 [[email protected]](mailto:[email protected]) Lana Myatt Senior Regulatory Analyst Nova Scotia Power Inc. 1223 Lower Water Street Halifax, NS B3J 3S8 Dear Ms. Myatt: M12374 - Nova Scotia Power Inc. - CI C0017098...
AI summary The Board has approved the final cost of $1,681,714 for the Ragged Lake Generator Replacement project, which is $547,553 less than the original approved cost. This reduction is attributed to lower technical complexity, the use of internal resources instead of contract labour, and unused contingency funds, despite increased material costs due to post-COVID-19 price fluctuations.
NSEB APPROVAL SHEET Project Title: Ragged Lake Generator Replacement CI Number: C0017098 Date: July 7, 2025 Expenditure Profile Type of Filing Year Budget Amount Project Estimate Capital Project Authorization Unforeseen and Unbudgeted (U&U...
AI summary The document outlines the expenditure profile for the Ragged Lake Generator Replacement project, including budget amounts, project estimates, and various types of filings from 2019 to 2025. The total budget is listed as $2,229,267, with a final cost of $1,681,714.