M12506 - CI C0041805 – L7005 Replacements and Upgrades Phase 2 – $2,910,451 (FIN) On October 6, 2025, Nova Scotia Power Inc. submitted a final cost capital approval (FIN) application in the amount of $2,910,451 to the Board. This applicati...
AI summary Nova Scotia Power Inc. submitted a final cost capital approval application for the L7005 Replacements and Upgrades Phase 2 project, which involves replacing deteriorated assets on a 230kV transmission line. The project’s final cost was $2,910,451, $272,067 less than the originally approved amount, due to cost savings from alternative access routes, although partially offset by increased overtime costs. The project was delayed due to transmission line outages and other work, and the final submission was delayed further due to a cyber incident.
CI Number: C0041805 Date: October 6, 2025 Expenditure Profile Type of Filing Year Budget Amount Project Estimate Capital Project Authorization Unforeseen and Unbudgeted (U&U) 2022 1,399,971 1,706,635 Planned & Advanced (P&A) 2023 1,684,391...
AI summary The document presents an expenditure profile with budget amounts, project estimates, and types of filings for various years. It includes categories such as Unforeseen and Unbudgeted, Planned & Advanced, Subsequent Approval Item, and Authorization to Overspend. The total expenditure amounts are also summarized.