Matter: Nova Scotia Power inc. - CI C0085226 – 101H-T62 Transformer Replacement - $2,933,002 (U&U)
8 passages 2 documents

Capital Expenditures across all matters →

N-1CI C0085226 101H-T62 Transformer Replacement U&U - Application - Redacted 5 passages
CI C0085226 101H-T62 Transformer Replacement U&U REDACTED September 11, 2026 REDACTED (CONFIDENTIAL INFORMATION REMOVED) NSEB APPROVAL SHEET 101H-T62 Transformer Replacement Project Title: CI Number: C0085226 Date: September 11, 2026 Expen...

AI summary The document outlines the approval process for the 101H-T62 Transformer Replacement Project by Nova Scotia Power Incorporated, with a total project estimate of $2,933,002. The expenditure profile includes budget amounts for 2025 and 2026, and the project is categorized under Unforeseen and Unbudgeted (U&U) and Planned & Advanced (P&A). The Nova Scotia Energy Board has approved the project on September 11, 2026.

Summary of Related CIs +/- 2 years:
Summary of Related CIs +/- 2 years: Pursuant to Section 11.2 of the CEJC, related CIs for Transmission include "Work completed on the same asset class (Padmount transformers, Breakers, etc.) or in the same location (feeder, Transmission Li...

AI summary The summary outlines related Capital Investments (CIs) for Transmission, including specific projects such as replenishing spare transformers and adding a substation, all falling under the depreciation class of Transmission Plant – Station Equipment.

REDACTED CI C0085226 Page 3 of 5 REDACTED (CONFIDENTIAL INFORMATION REMOVED)
REDACTED CI C0085226 Page 3 of 5 REDACTED (CONFIDENTIAL INFORMATION REMOVED) Capital Project Detailed Estimate Location: Transmission C0085226 CI# : Title: 101H-T62 Transformer Replacement

AI summary The document details a capital project for the replacement of the 101H-T62 Transformer in the Transmission sector. It includes a reference to a confidential information redaction and provides a project title and location.

Execution Year: 2025-2026
Execution Year: 2025-2026 Description Unit Quantity Unit Estimate Total Estimate Cost Support Reference Completed Similar Projects (FP#'s) Regular Labour Engineering & Project Management PD 25 $ 452 $ 11,424 Substation Operations Personnel...

AI summary The document outlines the estimated costs for labor, materials, freight, and administrative overhead for a project during the 2025-2026 execution year. It includes regular and overtime labor costs, material purchases, and capitalization of interest (AFUDC). The total estimated cost is $2,933,002, with a note that labor figures are averaged for budgeting purposes.

Preamble
This project is being filed as a Class 0 estimate. The defined deliverables for this project indicate that 100% of Class 1 deliverables are completed. This project is complete; therefore, no contingency has been applied. towards Class Esti...

AI summary The project has been classified as a Class 0 estimate with all Class 1 deliverables completed, indicating the project is fully completed and no contingency has been applied.

103550Letter NSPI re: Capital Items Filed Outside the Quarter Package 3 passages
Preamble
September 11, 2026 Crystal Henwood Clerk of the Board Nova Scotia Energy Board 1601 Lower Water Street, 3rd Floor Halifax, NS B3J 3S3 Re: Capital Items Filed Outside the Quarter Package Dear Ms. Henwood: Enclosed for your review and approv...

AI summary A document dated September 11, 2026, from an individual named Crystal Henwood, Clerk of the Board at the Nova Scotia Energy Board, is sent to Ms. Henwood regarding capital items filed outside the quarter package for review and approval.

2026 ACE Plan Capital Items for Subsequent Approval
2026 ACE Plan Capital Items for Subsequent Approval - CI C0047278 IT Oracle MDM Upgrade $8,211,297 2026 ACE amount $7,949,409 $4,431,504 spent as at July 31, 2026 Partially Confidential - CI C0068718 IT DERMS Solution Project $2,965,414 20...

AI summary The document outlines two capital items under the 2026 ACE Plan for subsequent approval: an IT Oracle MDM Upgrade and an IT DERMS Solution Project, including their costs, allocated amounts, and spending status as of July 31, 2026.

Unforeseen & Unbudgeted (U&U) Capital Items
Unforeseen & Unbudgeted (U&U) Capital Items - CI C0085185 4S-332 George St Rebuild and Reconfiguration $0 $0 spent as at July 31, 2026 Partially Confidential - CI C0085226 101H-T62 Transformer Replacement $2,933,002 $0 spent as at July 31,...

AI summary The document lists two unforeseen and unbudgeted capital items, including a transformer replacement and a rebuild and reconfiguration project, with details on costs and confidentiality status as of July 31, 2026.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →