11 Sep
DocumentNova Scotia Power filed an Unforeseen and Unbudgeted capital application for the emergency replacement of the 101H-T62 transformer at the Cobequid Road substation, totalling $2,933,002.
The filings themselves
Documents
Exhibits
2 files
- N-1 CI C0085226 101H-T62 Transformer Replacement U&U - Application - Redacted
- N-1(C) CI C0085226 101H-T62 Transformer Replacement U&U - Application - Confidential
Other documents
1 file
- 103550 Letter NSPI re: Capital Items Filed Outside the Quarter Package
What's discussed — click to drill in
Topics
Capital Expenditures
8 passages across 2 documents
Confidentiality
4 passages across 2 documents
Infrastructure Planning
4 passages across 1 documents
Distribution Planning
3 passages across 1 documents
System Reliability
3 passages across 2 documents
Project Schedule
2 passages across 1 documents
Accounting Policies
1 passages across 1 documents
Affordability
1 passages across 1 documents
Afudc
1 passages across 1 documents
Capacity Costs
1 passages across 1 documents
Cost Considerations
1 passages across 1 documents
Cost Recovery
1 passages across 1 documents
Cost To Customer
1 passages across 1 documents
Depreciation Amortization
1 passages across 1 documents
Generation Grid Resources
1 passages across 1 documents
Planned Outage
1 passages across 1 documents
Regulatory Approval Processes
1 passages across 1 documents
Right Of Way
1 passages across 1 documents
Transmission Planning
1 passages across 1 documents