Matter: Nova Scotia Power inc. - CI C0085226 – 101H-T62 Transformer Replacement - $2,933,002 (U&U)
1 passage 1 document

Cost Recovery across all matters →

N-1CI C0085226 101H-T62 Transformer Replacement U&U - Application - Redacted 1 passage
Execution Year: 2025-2026
Execution Year: 2025-2026 Description Unit Quantity Unit Estimate Total Estimate Cost Support Reference Completed Similar Projects (FP#'s) Regular Labour Engineering & Project Management PD 25 $ 452 $ 11,424 Substation Operations Personnel...

AI summary The document outlines the estimated costs for labor, materials, freight, and administrative overhead for a project during the 2025-2026 execution year. It includes regular and overtime labor costs, material purchases, and capitalization of interest (AFUDC). The total estimated cost is $2,933,002, with a note that labor figures are averaged for budgeting purposes.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →