13.4 Dispute Resoiution (a) In the event of a dispute arising between the Parties as to the subject Blatter of the PPA that cannot be resolved between them, the Parties agree to submit the dispute to binding arbitration~ pursuant to the te...
AI summary Section 13.4 outlines a binding arbitration process for resolving disputes under the PPA, governed by the Commercial Arbitration Act (Nova Scotia). It details procedures for selecting an arbitrator, cost-sharing, and enforceability of awards. Performance under the PPA continues during disputes, with undisputed amounts payable per the agreement.
GC 14 VALUATION AND CERTIFICATION OF CHANGES IN THE WORK - 14.1 If the type of work involved in a Change Order is included in the items contained in the Schedule of Lump Sum Prices, it shall be performed on the same payment basis as the or...
AI summary GC 14 outlines procedures for valuing and certifying changes in work under a contract. It specifies methods for determining costs (lump sum, unit prices, cost-plus) and requires agreement between DEVELOPER and CONTRACTOR. Dispute resolution (GC 9) is referenced for unresolved disagreements, with DEVELOPER initially determining adjustments.
GC 16 EFFECT OF PAYMENTS - 16.1 No payment made by the DEVELOPER under this Contract or partial or entire use or occupancy of the Work by the DEVELOPER shall constitute an acceptance of Work or Products which are not in accordance with req...
AI summary The section outlines that payments by the developer or use of the work do not imply acceptance of non-conforming work. Both parties waive claims against each other post-completion, except for specific exceptions like prior written claims, indemnification/warranty issues, interest charges, disputes under GC 9, and construction lien legislation.