Topic:"Cost Considerations" in M03714

Matter: CI# 39406 - P-510 - NSPI WO - U&U Dickie Brook Unit #1 - $601,706$82K spent to date
3 passages 1 document

Cost Considerations across all matters →

N-1Redacted Work Order 3 passages
Stuffing box p. pp. 19-20
Stuffing box We wanted to compare the cost of repairing versus a new casting. This part is badly corroded inside and NPT threads are damaged. Unfortunately we are still awaiting price for the casting and our estimate for this part is not c...

AI summary The document discusses the cost comparison between repairing and replacing a corroded stuffing box with damaged NPT threads. A budgetary estimate of $214,205 is provided for various components, and the proposal includes considerations for potential cost reductions during the rehabilitation process. The service life of the reconditioned unit is difficult to estimate due to external factors such as installation and alignment.

9-Nov-10 39406 p. p. 23
9-Nov-10 39406 Alternative After Tax WACC PV of EVA / NPV Rank IRR Disc Pay A DICKIE BROOK UNIT #1 0 6.55% 1,668,642 1 NA NA NA 16.35% 10.8 years #NUM! 0.0 years 0 NA NA NA NA NA #NUM! 0.0 years #NUM! 0.0 years Recommendation: Proceed with...

AI summary The document recommends proceeding with repairs to Unit #1 at the Dickle Brook Generating Station based on a net present value (NPV) of $1.595M. The analysis includes financial metrics such as after-tax weighted average cost of capital (WACC), internal rate of return (IRR), and discounted payback period.

DICKIE BROOK UNIT #1 p. p. 23
DICKIE BROOK UNIT #1 Capital costs include the major capital expenditures to be carried out over the 25 year economic life of the Dickie Brook development. Operating costs are the costs associated with the day to day operation of the devel...

AI summary The document discusses capital and operating costs for the Dickie Brook Unit #1, including avoided energy costs of $337,500 in 2010 and $369,000 in 2011, and annual generation of 4,500 MWh from Unit #1.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →