CI# 39406 - P-510 - NSPI WO - U&U Dickie Brook Unit #1 - $601,706$82K spent to date
What's happened
Filing Timeline
-
22 Dec
DocumentNSEB approved Nova Scotia Power's $601,706 unforeseen and unbudgeted work order for storm-damaged Dickie Brook Unit #1 repairs
-
24 Nov
DocumentNova Scotia Power filed a capital work order application seeking UARB approval for $601,706 in repairs to Unit #1 at the Dickie Brook Hydroelectric Generating Station following a January 2010 storm surge flood.
The filings themselves
Documents
Key documents
1 file
- 75525 Board Decision Letter
Exhibits
1 file
- N-1 Redacted Work Order
Other documents
1 file
- 75525 Board Decision Letter
What's discussed — click to drill in
Topics
Asset Management
9 passages across 1 documents
Capital Expenditures
7 passages across 2 documents
Infrastructure Planning
4 passages across 3 documents
Cost Considerations
3 passages across 1 documents
Evidence Requirements
2 passages across 1 documents
Hearing Procedures
2 passages across 1 documents
Regulatory Approval Processes
2 passages across 2 documents
Accounting Policies
1 passages across 1 documents
Cost Recovery
1 passages across 1 documents
Distribution Planning
1 passages across 1 documents
Emergency Response
1 passages across 1 documents
Generation Grid Resources
1 passages across 1 documents
Grid Modernization
1 passages across 1 documents
Operating Expenses
1 passages across 1 documents
Performance Monitoring
1 passages across 1 documents
Planned Outage
1 passages across 1 documents
Project Schedule
1 passages across 1 documents
Renewable Electricity Regulations
1 passages across 1 documents
Renewable Energy
1 passages across 1 documents
Revenue Requirement
1 passages across 1 documents