Topic:"Emergency Response" in M03714

Matter: CI# 39406 - P-510 - NSPI WO - U&U Dickie Brook Unit #1 - $601,706$82K spent to date
1 passage 1 document

Emergency Response across all matters →

N-1Redacted Work Order 1 passage
Why do this project? p. p. 1
Why do this project? The Dickie Brook powerhouse was flooded with brackish water/seawater as a result of a storm surge in early January, 2010. Unit # 1 was running at the time of the stormlflood event, and the partially submerged flywheel...

AI summary The Dickie Brook powerhouse's Unit #1 was damaged by saltwater from a 2010 storm surge, rendering it inoperable. Post-flood inspections confirmed damage to rotor, stator, and bearings. Repairs to penstock and draft tube were unrelated to the flood event.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →