Topic:"Cost Considerations" in M12373

Matter: Nova Scotia Power Inc. - CI C0067908 – POA Boiler Refractory Refurbishment 2025 – $1,378,466
2 passages 1 document

Cost Considerations across all matters →

N-1Application 2 passages
Reason for Variance p. p. 1
Reason for Variance The increase of approximately $289,000 from the 2025 ACE Plan estimate of $1,089,478 to the revised estimate of $1,378,466 is primarily due to refined material cost estimates obtained through detailed vendor engagement....

AI summary The increase of approximately $289,000 in the 2025 ACE Plan estimate is primarily due to higher material costs, especially for refractory materials, influenced by tariffs and vendor pricing adjustments.

Preamble p. p. 5
This project is being filed as a AACE Class 3 estimate. The defined deliverables for this project indicate that 90% of Class 3 deliverables are completed. AACE recommends applying between 10% and 30% contingency ito estimates in this class...

AI summary The project is classified as an AACE Class 3 estimate, with 90% of deliverables completed. A 10% contingency was selected to address risks like market volatility and potential additional scope during refurbishments.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →