Matter: Nova Scotia Power Inc. - CI C0083589 – IR751 Brooklyn Community Solar - $0 (U&U)2026 Q1 Capital Reports
1 passage 1 document

Cost Considerations across all matters →

N-2NSPI (NSEB) RIR 1 to 7 - Redacted 1 passage
16 p. p. 8
16 Provision PDF Page # Article 5. Cost Responsibility, Milestones, Billing and Payment: Section 5.1.1 Cost Estimates 20 Article 5. Cost Responsibility, Milestones, Billing and Payment: Section 5.1.2 Interconnection Facilities 20 Article 5...

AI summary The text lists provisions from Article 5, focusing on cost responsibility, milestones, billing, and payment, including sections on cost estimates, interconnection facilities, and distribution upgrades. These are referenced on PDF page 20.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →