Nova Scotia Power Inc. - CI C0083589 – IR751 Brooklyn Community Solar - $0 (U&U)2026 Q1 Capital Reports
What's happened
Filing Timeline
-
08 Jul
DecisionNSEB approved Nova Scotia Power's $0 capital expenditure request for the Brooklyn Community Solar interconnection, confirming all project costs are borne by the developer and not ratepayers.
-
22 May
DocumentNSEB Board Staff issued seven information requests to Nova Scotia Power regarding the IR751 Brooklyn Community Solar $0 (U&U) capital project, with responses due June 12, 2026.
-
04 May
DocumentNova Scotia Power filed a capital authorization application for IR751 Brooklyn Community Solar, a $0 net-cost unforeseen and unbudgeted interconnection project adding 4.8 MW of solar generation to the distribution system at the Interconnection Customer's full expense.
The filings themselves
Documents
Key documents
1 file
- 102677 Decision Letter
Exhibits
4 files
- N-1 CI C0083589 – IR751 Brooklyn Community Solar - $0 - Redacted
- N-1(C) CI C0083589 – IR751 Brooklyn Community Solar - $0 - Confidential
- N-2 NSPI (NSEB) RIR 1 to 7 - Redacted
- N-2(C) NSPI (NSEB) RIR 1 to 7 - Confidential
Other documents
4 files
- 101856 Letter NSPI re:First Quarter 2026 Capital Items
- 102103 NSEB (NSPI) IR-1 to 7
- 102361 Letter NSPI re: RIRs & Request for confidentiality
- 102677 Decision Letter
What's discussed — click to drill in
Topics
Generator Interconnection
53 passages across 3 documents
Infrastructure Planning
19 passages across 1 documents
Capital Expenditures
13 passages across 4 documents
System Reliability
11 passages across 2 documents
Regulatory Approval Processes
8 passages across 7 documents
Renewable Energy
7 passages across 4 documents
Power Purchase Agreement
6 passages across 5 documents
Rate Design
6 passages across 4 documents
Confidentiality
5 passages across 3 documents
Cost Recovery
5 passages across 3 documents
Distribution
5 passages across 2 documents
Distribution Planning
5 passages across 1 documents
Grid Modernization
4 passages across 1 documents
Right Of Way
4 passages across 1 documents
Information Disclosure
3 passages across 2 documents
Project Schedule
3 passages across 2 documents
Procurement Practices
2 passages across 1 documents
Regulatory Oversight
2 passages across 1 documents
Standardized Filing
2 passages across 1 documents
Transmission Planning
2 passages across 1 documents
Compliance Legislation
1 passages across 1 documents
Cost Considerations
1 passages across 1 documents
Cost To Customer
1 passages across 1 documents
Depreciation Amortization
1 passages across 1 documents
Generation Grid Resources
1 passages across 1 documents
Rate Base
1 passages across 1 documents
Rate Smoothing Adjustment
1 passages across 1 documents
Regulatory Compliance
1 passages across 1 documents
Residential Solar Pv Program
1 passages across 1 documents