Document No: XXX-XX-XXXX-XXXX p. p. 2
Document No: XXX-XX-XXXX-XXXX Project Cost Estimate Input Checklist and Maturity Matrix Transmission Line Infrastructure Required fields: Risk Register Preliminary (P) NR P Stakeholder Consultation/Engagement/Management Plan Defined (D) NR...

AI summary The document outlines a checklist and maturity matrix for transmission line infrastructure projects, detailing the status of various required fields such as risk registers, stakeholder engagement plans, and technical deliverables. It also includes information on the completion status of different components like conductor design, foundation design, and land title negotiations.

5.4 Impact on Transmission System p. p. 22
5.4 Impact on Transmission System At maximum generation, IR#751 – Brooklyn Solar generator site injects 4.8 MW on Substation through a 12.47 kV distribution circuit. This does not exceed the minimum substation load for and is not expected...

AI summary The Brooklyn Solar generator site (IR#751) injects 4.8 MW into the substation via a 12.47 kV circuit. This does not exceed the minimum substation load and is not expected to impact existing transmission infrastructure.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →