Matter: CI# 38266 - P-128.10 - NSPI WO - 2010 Projection Upgrades - $313,331
1 passage 1 document

Cost Deferral across all matters →

06430Board Decision Letter 2/18/2011 1 passage
The Board has reviewed Nova Scotia Power's ("NSPI") letter dated on October 15, 2010 (hard copy received on October 18, 2010), requesting Board approval of the following Work Order: p. p. 0
The Board has reviewed Nova Scotia Power's ("NSPI") letter dated on October 15, 2010 (hard copy received on October 18, 2010), requesting Board approval of the following Work Order: 2010 ACE Plan Deferral Approved Amount CI# 38266-2010 Pro...

AI summary Nova Scotia Power requested approval for a Work Order related to a 2010 ACE Plan, involving a protection upgrade with a deferral and approved amount. The Board issued information requests in December 2010, with responses received in January 2011.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →