CI# 38266 - P-128.10 - NSPI WO - 2010 Projection Upgrades - $313,331
The filings themselves
Documents
Key documents
1 file
- 06430 Board Decision Letter 2/18/2011
Exhibits
3 files
- N-1 Redacted Work Order
- N-2 Responses to Information Requests (IR-1 to IR-4) 1/12/2011
- N-2(C) NSPI (NSUARB) RIRs 1 - 4 - CONFIDENTIAL
Other documents
2 files
- 06021 Information Requests issued by Board Consultants
- 06430 Board Decision Letter 2/18/2011
What's discussed — click to drill in
Topics
Capital Expenditures
15 passages across 4 documents
2025 Ace Plan
5 passages across 3 documents
Infrastructure Planning
5 passages across 3 documents
Generator Interconnection
3 passages across 2 documents
Confidentiality
1 passages across 1 documents
Cost Deferral
1 passages across 1 documents
Distribution
1 passages across 1 documents
Distribution Planning
1 passages across 1 documents
Rate Rider
1 passages across 1 documents
Regulatory Approval Processes
1 passages across 1 documents
Renewable Electricity Regulations
1 passages across 1 documents
System Reliability
1 passages across 1 documents
Transmission Planning
1 passages across 1 documents