Cost Centre 800 - 800-Services - Admin. Budget Version - 2010 09/03 Forecast Forecast Start 08/01/2010 Operational 12/31/2010 Final Cost 12/31/2010 2010 $313,330.94 Total: $313,330.94 Original Cost: $0.00 This project provides for the cost...
AI summary This document outlines the forecasted budget for Cost Centre 800-Services in 2010, detailing the costs associated with upgrading protection systems at three substations to meet NPCC criteria as part of a three-phase project.