N-3NSPI (CA) RIR-1 to 18 - Redacted
4 passages
CI 50518 CA IR-5 Attachment 19 Page 174 of 423 REDACTED (CONFIDENTIAL INFORMATION REMOVED) 3 # Indicators Condition Choices Data Definitions/Explanations Protection and off road vehicles appear to effectively exclude or divert visitors and...
AI summary The text outlines various indicators and condition choices related to environmental protection, consumptive uses, domestic wells, and calcareous fen within a specific area. It includes data on wildlife disturbance, sustainable consumptive uses, proximity of domestic wells, and calcareous fen identification.
CI 50518 - HYD - Ruth Falls Main Dam Refurbishment ATO (NSUARB M11927) NSPI Responses to The Consumer Advocate Information Requests 1 (b) Cost minimization will be realized by using internal labour rather than contracted labour 2 at a mark...
AI summary NS Power is responding to information requests regarding cost minimization efforts for the Ruth Falls Main Dam Refurbishment project. They mention using internal labor instead of contracted labor and employing competitive procurement to reduce material costs by approximately $780,000.
NON-CONFIDENTIAL 1 Request IR-15: 2 3 Reference: NS Power states that costs for Administrative Overhead will increase by 4 $341,503, compared to an original budget of $72,085. 5 6 (a) Please provide a full breakdown of these costs. 7 8 (b)...
AI summary NS Power has requested an increase in administrative overhead costs for a project, citing a significant increase from the original budget. The response indicates that administrative overhead is calculated based on NSUARB-approved accounting policies and includes regular and overtime labour costs.
2 (b) The cost minimization efforts related to Contract costs, as described in CA IR-11 (b), 3 would have a direct impact on the minimization of contract AO, as every dollar of Contact 4 investment attracts Contract AO. 1 2024 includes act...
AI summary The text discusses how cost minimization efforts related to contract costs, as outlined in CA IR-11 (b), directly impact the minimization of contract asset obligations (AO), noting that each dollar invested in contracts attracts contract AO. It also mentions that 2024 data includes actual costs up to August 31, 2024, and forecasted costs for the remainder of the year.
N-6NSPI (NSUARB) RIR-1 to 13 - Redacted
3 passages
- 1. OWNER ADMINISTRATION AND OVERHEAD COSTS ARE NOT INCLUDED. - 2. COSTS FOR HYDRO UNIT DOWN TIME RESULTING FROM INSTALLATION ARE NOT INCLUDED. - 3. COSTS ASSOCIATED WITH SALES TAX, HST, AND INSURANCE ARE NOT INCLUDED. - 4. MOBILIZATION A...
AI summary The text outlines several excluded costs in a project, including owner administration, hydro unit downtime, sales tax, insurance, mobilization, and indirect costs like permitting and engineering. The total direct construction cost is listed as $7,444,000 CAD.
REDACTED 1 Request IR-10: 2 3 Regarding the Account Variance Sheet on pages 5 and 6 of the current Application: 4 5 (a) For the "Materials" Line Item: 6 7 (i) Please identify the percentage increase in materials cost that NS Power has 8 al...
AI summary The text outlines an information request (IR-10) directed at NS Power concerning cost variances in the Account Variance Sheet related to the 2019 ACE Plan Application, specifically focusing on materials, contracts, and additional costs such as archaeological site security and pumping expenses.
REDACTED Description Increase in costs (in Thousands) ADDITIONAL SCOPE: NEW PERMITTING REQUIREMENTS Fish Passage upgrades $1,630 Engineering support for environmental permit $15 application Barn Swallow nest removal $11 Pre-tree clearing n...
AI summary The text outlines various cost increases associated with a project, including fish passage upgrades, archaeological engagement, and extended construction timelines. The table details specific line items with associated costs, such as engineering support, environmental permits, and construction-related expenses.
N-8Midgard Evidence - Redacted
3 passages
- The IPPI data suggests that an increase for inflationary reasons on the order of 25.4% across all sectors is in - line with general economic trends. However, more specific categories, such as fabricated metal products and - construction...
AI summary The text discusses the impact of inflation on material costs for a construction project, noting a 25.4% overall increase, with higher increases in specific sectors like fabricated metal and construction materials. A 47% increase in material costs is attributed to an extended construction timeframe, though savings in certain line items reduced the overall increase to 85% of the original budget, with concrete costs alone contributing $689,000 of the increase.
3.1.3 Conclusion - In general Midgard concludes that NS Power did face an environment of dramatically increasing costs from - the time of its original submission to the time of the ATO Application. Inflationary pressures, as seen in both -...
AI summary Midgard concludes that NS Power faced significant cost increases due to inflation and other factors between the original submission and the ATO Application. Inflationary pressures, as seen in CPI and IPPI data, contributed to a 35-40% increase in certain categories, though the 85% increase in some line items may also be due to localized impacts or scope changes.
6.2.1 Material Cost Increases - In general Midgard concludes that NS Power did face an environment of dramatically increasing costs from - the time of its original submission to the time of the ATO Application. On its face the available in...
AI summary Midgard concludes that NS Power faced significant material cost increases from the time of its original submission to the ATO Application, which may not be fully explained by general inflation data. The analysis suggests that localized impacts and potential scope increases may have contributed to the overspending.
N-9Amended Evidence - Midgard - Redacted
14 passages
Table 3: Nova Scotia CPI Trend19 Table 4: Canada IPPI Trend20 Table 5: Ruth Falls Archaeological Costs24 Table 6: Comparison of Recent Project Archaeological Costs25 Table 7: Ruth Falls Main Dam Refurbishment Variance Summary28 Table 8: 20...
AI summary The document presents a series of tables detailing various cost-related data, including archaeological costs, labour costs, materials costs, administrative overhead, and other expenses associated with projects such as the Ruth Falls Main Dam Refurbishment and the 2019 ACE and ATO applications.
3.1.1 Analysis - Midgard has referenced additional metrics to provide context to NS Power's claim that an extended - construction timeline contributed significantly to the $2 million cost variance. The Consumer Price Index - (" CPI ") is a...
AI summary Midgard has referenced the Consumer Price Index (CPI) to provide context for NS Power's claim that an extended construction timeline caused a $2 million cost variance. The CPI measures inflation and is used to track price trends in Nova Scotia from May 2019 to October 2024.
3.1.2 Conclusion - In general Midgard concludes that NS Power did face an environment of dramatically increasing costs from - the time of its original submission to the time of the ATO Application. Inflationary pressures, as seen in both -...
AI summary Midgard concludes that NS Power faced significantly increased costs due to inflation, as reflected in CPI and IPPI data, particularly in categories like concrete and fabricated metal products, which saw increases of 35-40% between the original submission and the ATO Application.
7 5.1.1 NS Power Submission 3 8 NS Power reported labour cost increases from the 2019 ACE to the ATO Application as detailed in [Table 8](#page-28-0) and 9 [Table 9](#page-28-1) which resulted in labour expense overspending of $545,477. co...
AI summary NS Power reported labour cost increases from the 2019 ACE to the ATO Application, resulting in a labour expense overspending of $545,477. The details are outlined in Table 8 and Table 9.
5.2.1 NS Power Submission - NS Power reported material cost increases from the 2019 ACE to the ATO Application as detailed in [Table 11](#page-30-0) - an[d Table 12,](#page-30-1) which resulted in labour expense overspending of $1,408,689....
AI summary NS Power submitted a report detailing material cost increases from the 2019 ACE to the ATO Application, resulting in a labour expense overspending of $1,408,689, as outlined in Table 11 and Table 12.
5 5.2.3 Analysis – Extended Construction Timelines - 6 The extended project timeline, resulting from delays in securing environmental permitting approvals, - 7 contributed to fluctuations in the costs of key construction materials, includi...
AI summary Extended construction timelines caused delays in environmental permitting, leading to increased material costs for NS Power. The cost increase of $741k is attributed to factors beyond inflation, with some line items showing savings. The original 2019 ACE application had limited material categories, raising questions about the scope of additional costs.
4 5.3.1 NS Power Submission - 5 NS Power reported contract cost increases from the 2019 ACE to the ATO Application as detailed in [Table 14](#page-33-0) - 6 an[d Table 15,](#page-34-0) which resulted in contract expense overspending of $2,...
AI summary NS Power reported increased contract costs from the 2019 ACE to the ATO Application, leading to an overspending of $2,595,802 as detailed in Table 14 and Table 15.
2 1. Fish Passage Upgrades ($1,630,000): Updated environmental permit requirements, including design, 3 construction, and installation 4 2. Construction Supervision ($241,000): Extended timeline and project execution delays 5 3. Security S...
AI summary The document outlines increased contracting costs for a project due to expanded scope items, including fish passage upgrades, construction supervision, and security services. These increases are attributed to changes in design, environmental permit requirements, and compliance with regulations. NS Power attempted to minimize costs through a Limited Notice to Proceed (LNTP), but this resulted in additional expenses.
- 1. Increased Contract Costs: AO charges are directly proportional to total contract costs. These costs rose significantly due to new scope items, higher commodity prices, and additional work required to meet regulatory demands. - 2. Exte...
AI summary The text discusses increased administrative overhead (AO) charges due to rising contract costs, driven by new scope items, higher commodity prices, and regulatory demands. Delays in environmental permits extended the project timeline, increasing AO costs. NS Power highlighted that cost minimization efforts helped control AO variance.
5.3.5 Conclusion - 1. Contracts: The $2,689,000 increase in contract costs reflects the expanded project scope and evolving requirements, including fish passage upgrades, construction supervision, and archaeological mitigation. While the $...
AI summary The conclusion discusses the reasons for increased contract and contractor administrative overhead (AO) costs, attributing them to expanded project scope, regulatory delays, and environmental permitting. Midgard concludes that these cost increases are reasonable, except for archaeological costs, which may not be a valid reason for variance.
Power states: "Cost minimization will be realized by using internal labour rather than contracted labour at a marked-up rate during the upcoming monitoring during the nine months drawdown of Ruth Falls reservoir. NS Power also sought to mi...
AI summary NS Power implemented cost-saving measures by using internal labor, leveraging regulatory experience, and assigning familiar staff to the Sheet Harbour Hydro Project. The AO variance of $341,503 is justified by project complexities and extended timelines. Midgard concludes that the increased administrative overhead is reasonable.
5.8.2 Analysis - The increase in the additional travel, legal, and meal expenses can be attributed to the extended construction - timeline and associated environmental permitting requirements. Specific comments on each of expense is as - f...
AI summary The analysis discusses increased travel, legal, meal, and equipment costs due to project delays, environmental permitting, and expanded project scope. These costs are attributed to extended timelines, regulatory requirements, and unexpected vendor selections. NS Power explains these variances as necessary for project compliance and cost efficiency.
Table 31: Cost Increase – Other Goods & Services (Contingency)[89](#page-50-1) Description NSUARB Approved ($) ATO Submission ($) Variance ($) Other Goods & Services (Contingency) $842,715 $1,342,714 $499,999 5.9.2 Analysis
AI summary Table 31 shows a significant variance between the NSUARB-approved amount and the ATO submission for Other Goods & Services (Contingency), with the ATO requesting an additional $499,999.
Table 32: Summary of Overspending Amount Conclusions Cost Category Midgard Conclusion Labour Reasonable Materials Recommend that NS Power provide additional clarity on the source of the material cost overspending. Contracts Reasonable, wit...
AI summary Table 32 summarizes conclusions regarding cost category overspending. Most categories are deemed reasonable, but additional clarity is requested for material costs, and archaeology-related costs are questioned as valid reasons for variance.