p. p. 1
Please refer to the variance sheet for more detail. 51956 - 6P Mobile Substation Rewind Account Approved Current Submission Variance Reason for Variance Regular Labour 21,414 38,366 16,952 Increased amount of labour required for techs to t...
AI summary The variance sheet details discrepancies between approved and submitted costs for the 51956 - 6P Mobile Substation Rewind project, with significant variances attributed to increased labour requirements, vendor bids under original estimates, and missed milestones impacting Factory Acceptance tests.