Request IR-9:
Request IR-9: - On page 4 of the application, NS Power provided a Cost Variance Sheet showing a variance of $1,499,051 in the "Contracts" line item. - a) Please provide detailed breakdowns for all unplanned works included in the Contracts...
AI summary NS Power submitted a Cost Variance Sheet showing a $1,499,051 variance in the 'Contracts' line item. The request asks for detailed breakdowns of all unplanned works included in this variance, including supporting documents like invoice work orders or service records.