Topic:"Cost Recovery" in M03506

Matter: CI# 38942 - P-128.10 - NSPI WO - TUC-Unit #3 Generator Rotor Rewind - $1,798,080
2 passages 2 documents

Cost Recovery across all matters →

N-1Redacted Work Order 9/2/2010 1 passage
rue -Unit 3 Generator Rotor Rewind Summary of Alternatives p. p. 12
rue -Unit 3 Generator Rotor Rewind Summary of Alternatives Budget Year: Division: Department: Originator: Alternative A Rotor Rewind 20101 Power Production Tuft's Cove Date: 23-Aug-10 CI Number: 38942 Project No. : After Tax WACC PV of EVA...

AI summary The document evaluates alternatives for the Unit 3 Generator Rotor Rewind, including rotor rewind and replacement. It provides financial metrics such as WACC, PV of EVA/NPV, IRR, and discounted payback period, concluding that rotor rewind is more economical. Assumptions include a capital cost of $1,798,080 with a 20-year life for the rewind option.

05302Board Decision Letter 9/20/2010 1 passage
CI# 38942 - ruc Unit #3 Generator Rotor Rewind $1,798,080 p. p. 0
CI# 38942 - ruc Unit #3 Generator Rotor Rewind $1,798,080 Board Staff issued Information Requests on February 5, 2010 as part of NSPl's 2010 ACE Plan, and NSPI's responses were received by the Board on March 5, 2010. The Board has consider...

AI summary The Board approved NSPI's request for $1,798,080 to rewind the Tufts Cove Unit #3 generator rotor, damaged in 2009, as part of NSPI's 2010 ACE Plan. The project aims to restore the rotor to original specifications for safe and continuous operation.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →