CI# 38942 - P-128.10 - NSPI WO - TUC-Unit #3 Generator Rotor Rewind - $1,798,080
What's happened
Filing Timeline
-
OrderUARB approved Nova Scotia Power's $1,798,080 capital expenditure for the Tufts Cove Unit #3 Generator Rotor Rewind (CI# 38942) as necessary for safe and continuous generation operations.
The filings themselves
Documents
Key documents
1 file
- 05302 Board Decision Letter 9/20/2010
Exhibits
1 file
- N-1 Redacted Work Order 9/2/2010
Other documents
1 file
- 05302 Board Decision Letter 9/20/2010
What's discussed — click to drill in
Topics
Capital Expenditures
14 passages across 3 documents
Regulatory Approval Processes
5 passages across 2 documents
Cost Considerations
2 passages across 1 documents
Cost Recovery
2 passages across 2 documents
Generator Interconnection
2 passages across 1 documents
Unplanned Outage
2 passages across 1 documents
Confidentiality
1 passages across 1 documents
Cost To Customer
1 passages across 1 documents
Infrastructure Planning
1 passages across 1 documents
Planned Outage
1 passages across 1 documents
Rates And Money
1 passages across 1 documents
Renewable Energy
1 passages across 1 documents