N-1Redacted Work Order 9/2/2010
2 passages
CI Number 38942 - TUC - Unit # 3 Generator Rotor Rewind Parent CI Number Cost Centre 319 - 319-TC Unit 3 Capital Budget Version - 201007/05 Forecast Forecast Start Operational 08/01/2010 11/30/2010 2010 $1,798,079.52 12/30/2010 Final Cost...
AI summary This document details a capital project related to the rewinding of Unit #3 generator rotor at Cost Centre 319, initiated due to displaced coil insulating barriers discovered during an unplanned bus duct replacement project in 2009. The rewinding is necessary to prevent potential short circuits and unplanned outages.
The more a supplier is aware of NSPI's specific requirements, the better their ability to obtain the highest price, reduce competition and ultimately increase the cost for NSPI and its customers. The cost of such transparency is not always...
AI summary The text discusses how supplier awareness of NSPI's requirements can affect pricing and competition, potentially increasing costs for customers. It also outlines the findings from a 2009 project involving the inspection and repair of a generator that has been in service since 1976 and is nearing the end of its operational life.
Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →