HomeCost RecoveryM12874Evidence
Topic/Matter Intersection

Topic:"Cost Recovery" in M12874

Matter: Lunenburg Electric Utility Capital Approval 2026 Transformer Project
4 passages 4 documents

Cost Recovery across all matters →

L-2Lunenburg Electric (NSEB) RIR 1 to 10 1 passage
1 Request IR-1: p. p. 7
1 Request IR-1: - 2 Regarding the cost summary table on page 1, please expand the table to clearly describe the - 3 components included under each cost item and provide a more detailed cost estimate. For each - 4 item in the table, please...

AI summary Request IR-1 asks for an expansion of the cost summary table on page 1, requiring detailed descriptions of each cost item, including unit, quantity, unit estimate, and total estimate.

L-3LEU (NSEB) RIR 11 to 15 1 passage
LEU Response to IR-13
LEU Response to IR-13 - a) LEU intends to fund this project with Debt financing. The Debt financing will be secured through a debenture with the Province of Nova Scotia Municipal Finance. The debenture is anticipated to be secured in Sprin...

AI summary The LEU plans to fund a project through a 10-year debenture with the Province of Nova Scotia Municipal Finance, secured in Spring 2027, and will seek approval to recover these costs in the next Rate Study, expected in the first quarter of 2027.

102318NSEB (Lunenburg Electric) IR 1 to 10 1 passage
Request IR-1:
Request IR-1: - Regarding the cost summary table on page 1, please expand the table to clearly describe the - components included under each cost item and provide a more detailed cost estimate. For each - item in the table, please include...

AI summary Request IR-1 asks for an expansion of the cost summary table on page 1, requiring detailed descriptions of each cost item, including unit, quantity, unit estimate, and total estimate.

103060Decision letter 1 passage
Section 2 p. p. 0
on July 13, 2026, and LEU provided its responses on July 23, 2026. In response to IRs, LEU stated that the estimated project budget of $600,000 includes a 10% contingency allowance but excludes HST. LEU stated that the project is planned s...

AI summary LEU submitted its response to IRs regarding the 2026 Transformer Project, explaining the project's budget, scope, and financing. The project aims to replace PCB transformers and upgrade infrastructure to meet regulatory deadlines. The Board approves the project as reasonable and necessary, with a total cost of $600,000 excluding HST.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →