Matter: Nova Scotia Power Inc. - CI C0083451 - Seton Ridge Underground Network - $3,656,609 (U&U)Unforeseen & Unbudgeted (U&U) Capital Items:C0083451 - Seton Ridge Underground Network - $3,656,609 $0 spent as at March 31, 2026 Partially Confidential
4 passages 4 documents

Cost Recovery across all matters →

N-1CI C0083451 - Seton Ridge Underground Network - Report - Redacted 1 passage
7.0 COST & RIGHT OF WAY RESPONSIBILITY p. p. 36
7.0 COST & RIGHT OF WAY RESPONSIBILITY In accordance with NSPI Regulation 2.6, a load customer is responsible for providing the following: - a. A capital contribution for all line extension work in excess of 92 m - i. If a line previously...

AI summary NSPI regulations outline customer responsibilities for line extensions beyond 92m, including capital contributions, easements, and ROW clearing. Cost splits for 3-phase line extensions are specified, with NSPI handling network upgrades based on load studies. Customers bear 90% of costs for line extensions under certain conditions, while NSPI manages the remaining 10%.

N-2NSPI (NSEB) RIRs 1-18 1 passage
Replacement of Existing Systems - The Company will be responsible for costs associated with the best (generally lowest cost) supply option should an p. pp. 12-29
Replacement of Existing Systems - The Company will be responsible for costs associated with the best (generally lowest cost) supply option should an 1 2 3 4 5 6 7 underground system (or any part thereof) have to be replaced. Where this opt...

AI summary The Company is responsible for replacing underground systems with the lowest cost option, which may be overhead supply. If a customer prefers underground service, they must cover the additional cost difference. A planning-level estimate was prepared for an overhead alternative, including approximately 1,750 m of three-phase and 1,350 m of single-phase overhead infrastructure.

102357Letter NSPI re: Capital Items Filed Outside the Quarter Package 1 passage
Commercial Information p. p. 0
Commercial Information Items 1-2: Partial confidentiality was applied to costs associated with materials, contracts and freight details provided in the capital work order(s). To protect value for customers and mitigate the risk of prospect...

AI summary NS Power applies partial confidentiality to costs related to materials, contracts, and freight in capital work orders to protect customer value and prevent competitive advantages to other suppliers. This ensures NS Power can secure the most competitive terms for services and equipment, which benefits customers as rates are cost-based.

102523NSEB (NSPI) IR 1 to 18 1 passage
2.11 UNDERGROUND ELECTRIC SERVICES
2.11 UNDERGROUND ELECTRIC SERVICES Distribution Systems - The Company may supply, install, maintain and own underground distribution systems. A party requesting the installation of an underground distribution system will be required to mak...

AI summary The document outlines the responsibilities and cost-sharing arrangements for underground electric services, including capital contributions by parties requesting installations or conversions, ownership and maintenance responsibilities, and cost implications for replacements or repairs. The Board is requested to provide detailed cost breakdowns and confirm ownership and responsibility assumptions.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →