Matter: CI# 28726 - P-128.10 - NSPI WO - HYD Carlton Lake Refurbishment - $3,978,895
2 passages 1 document

Cost To Customer across all matters →

N-1Redacted Application 6/28/2010 2 passages
Section 1 p. p. 0
June 25, 2010 Nancy McNeil Clerk of the Board Nova Scotia Utility and Review Board 1601 Lower Water Street, 3 rd Floor P.O. Box 1692, Unit "M" Halifax, NS B3J 3S3 Re: CI# 28726 - HYD Carlton Lake Refurbishment - ACE 2010 Item Greater Than...

AI summary The document discusses the confidentiality of pricing terms for the HYD Carlton Lake Refurbishment project, emphasizing the need to protect competitive advantages and prevent higher costs to customers. NSPI argues that disclosing such information could lead to higher prices and less competitive terms.

REDACTED p. p. 20
REDACTED 1 Generation Responses 2 3 Request IR-G7: 4 5 With respect to page 25, CI# 28726, HYD - Carlton Lake Dam Refurbishment, 6 7 What is the value of energy from the Tusket system? Has a 10 year or longer replacement 8 capital budget b...

AI summary The document discusses a request regarding the value of energy from the Tusket hydro system and the preparation of a 10-year capital budget for the system. The response provides the average annual generation and mentions a confidential capital works plan, highlighting concerns about transparency and its potential impact on competition and customer costs.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →